ABSTRACT
In various construction projects often change order or request change. Change order can
occur during the construction project and cannot be avoided. The occurrence of change order on
construction projects often have a negative impact that can affect project costs and time. This study
aims to determine the effect of change order on supervision consultants on cost and time, because
not only are executing contractors undergoing change order, supervisory consultants also often
experience change order.
This research begins with data retrieval related to the project in the supervision consultant.
Furthermore, the data is analyzed and a legal basis study related to contract changes. The result is
the effect of change order on the supervision consultant is the loss experienced by the supervis io n
consultant both in terms of losses in terms of costs and losses in terms of time. Based on the
analysis of the legal basis, through Presidential Regulation Number 16 of 2018 and Circular Letter
of the Director General of Highways Number 02 / SE / Db / 2016 the state regulates the addition
of a contract value of a maximum of 10% if a contract change occurs, and the data allocation can
be taken from the ceiling the activity concerned.
5.2 Saran
Dimyati, H.A. Hamdan & Nurjaman,
1. Untuk mengurangi kerugian yang Kadar, 2014. Manajemen Proyek.
terjadi pada konsultan supervis i, Bandung : Pustaka Setia
pemilik proyek seharusnya
menambah biaya karena adanya Direktorat Penanganan Permasalaha n
pertambahan waktu. melalui Hukum, 2012. Perpanjangan Waktu
Peraturan Presiden No. 16 tahun 2018 dan Pemberian Kesempatan
negara menjamin penambahan nila i
Penyelesaian Pekerjaan. Jakarta :
LKPP Surat Edaran Dirjen Bina Marga No.
02, 2016. Prosedur Standar
Fisk, Edward R, and Reynolds Wayne Pelaksanaan Perubahan (Addendum)
D, 2006. Construction Project Kontrak. Jakarta : Kementeria n
Administration, Eight Edition. New Pekerjaan Umum dan Perumahan
Jersey : Prentice Hall. Rakyat
Gilberth, Robert D, 1992. Mananging Surat Edaran Dirjen Bina Marga No.
Construction Contract Operational 18, 2012. Prosedur Standar
Control for Comersial Risk, Second Pelaksanaan Perubahan (Addendum)
Edition. John Wiley & Sons. Inc. Kontrak. Jakarta : Kementeria n
Pekerjaan Umum dan Perumahan
Peraturan Presiden No. 16, 2018, Rakyat
Pengadaan Barang/Jasa Pemerinta h,
Jakarta : Bappenas. Willem Sapulette, 2009. Analisa dan
Pengaruh Change Order pada Proyek
Peraturan Presiden No. 54, 2010, Insfrastruktur dan Bangunan Gedung
Pengadaan Barang/Jasa Pemerinta h, di Ambon. Jurnal Teknologi. Volume
Jakarta : Bappenas. 6 No. 2, Universitas Kristen
Indonesia Maluku.
Peraturan Presiden No. 70, 2012,
Pengadaan Barang/Jasa Pemerinta h,
Jakarta : Bappenas.