NPM : 16612015020
MATA KULIAH : STUDY KELAYAKAN BISNIS
SEMESTER : 7 (REGULER B)
DOSEN : DIAH ISMAYANTI, SE., MM
0 Rp 125.015.020 - -
1 - Rp 15.015.020 Rp 35.015.020
2 - Rp 16.015.020 Rp 40.015.020
3 - Rp 16.015.020 Rp 50.015.020
4 - Rp 16.015.020 Rp 50.015.020
5 - Rp 17.015.020 Rp 50.015.020
6 - Rp 16.015.020 Rp 45.015.020
Ditanya : a. Hitunglah Net Present Value (NPV)!
Penyelesaian :
Tahu DF
Benefit Total Cost Net Benefit Present Value
n 15%
0 - 125.015.020 -125.015.020 1 -125.015.020
1 35.015.020 15.015.020 20.000.000 0,870 17.400.000
2 40.015.020 16.015.020 24.000.000 0,756 18.144.000
3 50.015.020 16.015.020 34.000.000 0,658 22.372.000
4 50.015.020 16.015.020 34.000.000 0,572 19.448.000
5 50.015.020 17.015.020 33.000.000 0,497 16.401.000
6 45.015.020 16.015.020 29.000.000 0,432 12.528.000
∑ Net Present Value (NPV) - 18.722.020
Rumus :
n =1
NBi
∑ (1+i)²
i=1
Analisis :
Berdasarkan dari perhitungan Net Present Value (NPV) diatas dapat diketahui
bahwa Net Present Value (NPV) sebesar - 18.722.020 < 0 (nol) yang
mengartikan bahwa proyek ini tidak layak untuk dikerjakan.
b. Internal Rate of Return (IRR)
DF DF Present
Tahun Net Benefit Present Value
15% 9% Value
0 -125.015.020 1 -125.015.020 1 -125.015.020
1 20.000.000 0,870 17.400.000 0,917 18.340.000
2 24.000.000 0,756 18.144.000 0,842 20.208.000
3 34.000.000 0,658 22.372.000 0,772 26.248.000
4 34.000.000 0,572 19.448.000 0,708 24.072.000
5 33.000.000 0,497 16.401.000 0,650 21.450.000
6 29.000.000 0,432 12.528.000 0,596 17.284.000
∑ - 18.722.020 2.586.980
Rumus :
NPV ₁
IRR= i1 + X (i2 – i1)
NPV ₁−NPV ₂
Perhitungannya :
NPV ₁
IRR = i1 + X (i2 – i1)
NPV ₁−NPV ₂
- 18.722.020
= 0,15 + X (0,09 – 0,15)
(-18.722.020) - 2.586.980
( -18.722.020)
= 0,15 + X (-0,06 )
(- 21.309.000 )
= 0,15 + (- 0,053)
= 0,0973
= 9,73%