SISTEM PRODUKSI

MODUL I
MATERIAL REQUIREMENTS PLANNING

Disusun Oleh:
Kelas S5E
Kelompok II

Muhammad Mujadid (202044500275)


Akmal Hibatulloh (202044500277)
Hariyadi Sasi Pamungkas (202044500278)
Ferina Agustin (202044500283)
Rahmadytha Putri Apsari (202044500284)
Abdul Gusdi Oky Wedano (202044500304)
Ummul Maratis Shalihah (202044500309)
Cecep Indra Setia Lesmana (202044500312)

PROGRAM STUDI TEKNIK INDUSTRI


FAKULTAS TEKNIK DAN ILMU KOMPUTER
UNIVERSITAS INDRAPRASTA PGRI
2022
LEMBAR PENGESAHAN

Kelompok II : 1. Muhammad Mujadid (202044500275)

2. Akmal Hibatulloh (202044500277)

3. Hariyadi Sasi Pamungkas (202044500278)

4. Ferina Agustin (202044500283)

5. Rahmadytha Putri Apsari (202044500284)

6. Abdul Gusdi Oky Wedano (202044500304)

7. Ummul Maratis Shalihah (202044500309)

8. Cecep Indra Setia Lesmana (202044500312)

Program Studi : Teknik Industri

Fakultas : Teknik dan Ilmu Komputer

Modul : Sistem Produksi

MRP (Material Requirements Planning)

Penanggung Jawab I Penanggung Jawab II

(Hanisah Khaerul) (Tania Nur Azizah)

PIC I PIC II

(Aji Sumarna) (Velyda Noer Praniasty)

Koordinator Asisten Laboratorium Teknik Industri

(Siti Humayro Billah)

i
LEMBAR PENILAIAN

MODUL I

MATERIAL REQUIREMENTS PLANNING

SISTEM PRODUKSI

ISI LAPORAN NILAI

BAB I PENDAHULUAN

BAB II TINJAUAN PUSTAKA

BAB III METODOLOGI PENELITIAN

BAB IV PENGOLAHAN DATA DAN ANALISIS

BAB V SIMPULAN DAN SARAN

Total Nilai :

Jakarta, 14 Oktober 2022

Penanggung Jawab I,

(Hanisah Khaerul)

ii
LEMBAR ORISINALITAS

Yang bertanda tangan dibawah ini:

1. Muhammad Mujadid (202044500275)


2. Akmal Hibatulloh (202044500277)
3. Hariyadi Sasi Pamungkas (202044500278)
4. Ferina Agustin (202044500283)
5. Rahmadytha Putri Apsari (202044500284)
6. Abdul Gusdi Oky Wedano (202044500304)
7. Ummul Maratis Shalihah (202044500309)
8. Cecep Indra Setia Lesmana (202044500312)

Menyatakan bahwa laporan modul ini adalah benar-benar pekerjaan


kami sendiri. Bila terbukti tidak demikian, kami bersedia menerima segala
konsekuensi yang telah disepakati, yaitu nilai praktikum Sistem Produksi MRP
(Material Requirements Planning) mendapat nilai E.
Jakarta, 14 Oktober 2022
Tim Penyusun,

(Muhammad Mujadid) (Akmal Hibatulloh)

(Hariyadi Sasi Pamungkas) (Ferina Agustin)

(Rahmadytha Putri Apsari) (Abdul Gusdi Oky Wedano)

(Ummul Maratis Shalihah) (Cecep Indra Setia Lesmana)

iii
ABSTRAK

A. 1. Muhammad Mujadid (202044500275)


2. Akmal Hibatulloh (202044500277)
3. Hariyadi Sasi Pamungkas (202044500278)
4. Ferina Agustin (202044500283)
5. Rahmadytha Putri Apsari (202044500284)
6. Abdul Gusdi Oky Wedano (202044500304)
7. Ummul Maratis Shalihah (202044500309)
8. Cecep Indra Setia Lesmana (202044500312)
B. Material Requirements Planning; Program Studi Teknik Industri; Falkustas Teknik dan
Ilmu Komputer; Universitas Indraprasta PGRI.
C. Xviii + 5 Bab + 116 Halaman
D. Kata Kunci : Bill Of Material, Capacity Requirement Planning, Forcasting, Master
Production Schedule, Rough Cut Capacity Planning.
E. Sistem perencanaan dan pengendalian produksi terdiri dari beberapa sub-sistem yang
dirancang untuk mencapai secara utuh dua sasaran pokok perencanaan dan pengendalian
produksi yaitu tercapainya kepuasan pelanggan dan tingginya tingkat utilisasi penggunaan
sumber daya produksi. Jadwal induk produksi disusun dengan memperhatikan potensi
permintaan, dan potensi kapasitas. Potensi kapasitas dievaluasi dengan menggunakan
teknik rough-cut capacity planning (RCCP). Berdasarkan jadwal induk produksi kemudian
disusun jadwal perakitan produk akhir (final assembly schedule) dan rencana kebutuhan
bahan (material requirements plan atau MRP). Pada penelitian ini menggunakan data yang
telah dikumpulkan dari PT. Se Wooden Toys, dimana diketahui bahwa total waktu siklus
adalah 89 detik dan total waktu keseluruhan adalah 698 detik. Kemudian dibutuhkan 1168
unit Spray gun untuk periode Januari sampai Desember 2022.
F. Daftar Pustaka : 1. Buku 2 Buah
2. Jurnal 2 Buah
G. Penanggung Jawab : (Hanisah Khaerul) penanggung Jawab I
(Tania Nur Azizah) penanggung Jawab II

iv
KATA PENGANTAR

Penyusun memanjatkan puji dan syukur ke hadirat Tuhan Yang Maha

ESA yang telah melimpahkan rahmat dan karunia-Nya kepada penyusun,

sehingga akhirnya dapat menyusun modul ini tepat pada waktunya.

Modul yang berjudul “Material Requirements Planning” ini disusun

untuk memenuhi salah satu tugas dari praktikum Proses Produksi pada Program

Studi Teknik Industri, Fakultas Teknik dan Ilmu Komputer. Pada kesempatan ini

yang baik ini, ijinkanlah penyusun menyampaikan rasa hormat dan ucapan terima

kasih kepada semua pihak yang dengan tulus ikhlas telah memberikan bantuan

dan dorangan kepada penyusun dalam menyelesaikan modul ini.

Jakarta, 14 Oktober 2022

Penyusun

v
DAFTAR ISI

Halaman

LEMBAR PENGESAHAN ................................................................................... i

LEMBAR PENILAIAN ........................................................................................ ii

LEMBAR ORISINALITAS ................................................................................ iii

ABSTRAK ............................................................................................................ iv

KATA PENGANTAR ........................................................................................... v

DAFTAR ISI ......................................................................................................... vi

DAFTAR TABEL............................................................................................... viii

DAFTAR GAMBAR .......................................................................................... xvi

DAFTAR LAMPIRAN ..................................................................................... xvii

BAB I PENDAHULUAN ..................................................................................... 1

A. Latar Belakang..................................................................................... 1

B. Identifikasi Masalah............................................................................. 3

C. Batasan Masalah .................................................................................. 3

D.Rumusan Masalah ................................................................................ 4

E.Tujuan Penulisan ................................................................................... 4

F.Sistematika Penulisan............................................................................ 5

BAB II TINJAUAN PUSTAKA........................................................................... 6

A.Kajian Pustaka ...................................................................................... 6

B.Kerangka Berpikir .............................................................................. 23

C.Penelitian Yang Relevan..................................................................... 24

vi
BAB III METODOLOGI PENELITAN ........................................................... 28

A.Waktu Dan Tempat Penelitian ............................................................ 28

B. Metode Penelitian .............................................................................. 29

C. Metode Pengumpulan Data ................................................................ 29

D. Teknik Analisis Data ......................................................................... 30

E. Flowchart Penelitian .......................................................................... 35

BAB IV PENGUMPULAN DAN PENGOLAHAN DATA ............................ 36

A. Pengumpulan Data ............................................................................. 36

B. Pengolahan Data ................................................................................ 40

C. Pembahasan dan Analisis................................................................. 108

BAB V SIMPULAN DAN SARAN .................................................................. 129

A. Simpulan .......................................................................................... 129

B. Saran ................................................................................................ 129

DAFTAR PUSTAKA

LAMPIRAN

vii
DAFTAR TABEL

Halaman

Tabel 3.1 Grantt Chart Penelitian........................................................................ 28

Tabel 4.1 Direct Material Mainan Kereta Api Kayu ........................................... 37

Tabel 4.2 Indirect Material Mainan Kereta Api Kayu ........................................ 38

Tabel 4.3 Data Forecasting .................................................................................. 40

Tabel 4.4 Data WMA PT SE Wooden Toys ........................................................ 40

Tabel 4.5 Waktu Operasi Pembuatan Komponen Badan Bawah ......................... 42

Tabel 4.6 Waktu Operasi Pembuatan Komponen As Roda Depan ...................... 42

Tabel 4.7 Waktu Operasi Pembuatan Komponen As Roda Belakang ................. 43

Tabel 4.8 Waktu Operasi Pembuatan Komponen Roda Depan Kanan ................ 43

Tabel 4.9 Waktu Operasi Pembuatan Komponen Roda Depan Kiri .................... 44

Tabel 4.10 Waktu Operasi Pembuatan Komponen Roda Belakang Kanan ......... 44

Tabel 4.11 Waktu Operasi Pembuatan Komponen Roda Belakang Kiri ............. 45

Tabel 4.12 Waktu Operasi Pembuatan Komponen Perangkai Roda Kanan ........ 45

Tabel 4.13 Waktu Operasi Pembuatan Komponen Perangkai Roda Kiri ............ 46

Tabel 4.14 Waktu Operasi Pembuatan Komponen Pengunci Roda Depan Kanan

......................................................................................................... 46

Tabel 4.15 Waktu Operasi Pembuatan Komponen Pengunci Roda Depan Kiri .. 47

Tabel 4.16 Waktu Operasi Pembuatan Komponen Pengunci Roda Belakang

Kanan .............................................................................................. 47

Tabel 4.17 Waktu Operasi Pembuatan Komponen Pengunci Roda Belakang

Kiri .................................................................................................. 48

viii
Tabel 4.18 Waktu Operasi Pembuatan Komponen Badan Atas .......................... 48

Tabel 4.19 Waktu Operasi Pembuatan Komponen Atap ..................................... 49

Tabel 4.20 Waktu Operasi Pembuatan Komponen Pasak belakang .................... 49

Tabel 4.21 Waktu Operasi Pembuatan Komponen Badan Lokomotif ................. 50

Tabel 4.22 Waktu Operasi Pembuatan Komponen Badan Cerobong .................. 50

Tabel 4.23 Waktu Operasi Pembuatan Komponen Pasak Depan ........................ 51

Tabel 4.24 Waktu Operasi Pembuatan Komponen Sub-Sub Assembling 1 ........ 51

Tabel 4.25 Waktu Operasi Pembuatan Komponen Sub-Sub Assembling 2 ......... 52

Tabel 4.26 Waktu Operasi Pembuatan Komponen Sub-Sub Assembling 3 ......... 52

Tabel 4.27 Waktu Operasi Pembuatan Komponen Sub Assembling 1................. 52

Tabel 4.28 Waktu Operasi Pembuatan Komponen Sub Assembling 2................. 53

Tabel 4.29 Waktu Operasi Pembuatan Komponen Assembling 1....................... 53

Tabel 4.30 Waktu Operasi Pembuatan Komponen Pengemasan Mika................ 53

Tabel 4.31 Waktu Operasi Pembuatan Komponen Pengemasan Kardus ............ 54

Tabel 4.31 Master Production Schedule (MPS) .................................................. 55

Tabel 4.32 RCCP Komponen Badan Bawah ....................................................... 56

Tabel 4.33 RCCP Komponen As Roda Depan .................................................... 57

Tabel 4.34 RCCP Komponen Roda Belakang .................................................... 58

Tabel 4.35 RCCP Komponen Roda Depan Kanan .............................................. 59

Tabel 4.36 RCCP Komponen Roda Depan Kiri .................................................. 60

Tabel 4.37 RCCP Komponen Roda Belakang Kanan .......................................... 61

Tabel 4.38 RCCP Komponen Roda Belakang Kiri .............................................. 62

Tabel 4.39 RCCP Komponen Perangkai Roda Kanan ......................................... 63

ix
Tabel 4.40 RCCP Komponen Perangkai Roda Kiri ............................................. 64

Tabel 4.41 RCCP Komponen Pengunci Roda Depan Kanan .............................. 65

Tabel 4.42 RCCP Komponen Pengunci Roda Depan Kiri .................................. 66

Tabel 4.43 RCCP Komponen Pengunci Roda Belakang Kanan .......................... 67

Tabel 4.44 RCCP Komponen Pengunci Roda Belakang Kiri .............................. 68

Tabel 4.45 RCCP Komponen Badan Atas ........................................................... 69

Tabel 4.46 RCCP Komponen Atap ...................................................................... 70

Tabel 4.47 RCCP Komponen Pasak Belakang .................................................... 71

Tabel 4.48 RCCP Komponen Badan Lokomotif ................................................. 72

Tabel 4.49 RCCP Komponen Cerobong .............................................................. 73

Tabel 4.50 RCCP Komponen Pasak Depan ......................................................... 74

Tabel 4.51 RCCP Komponen Sub-Sub Assembling 1 .......................................... 75

Tabel 4.52 RCCP Komponen Sub-Sub Assembling 2 .......................................... 76

Tabel 4.53 RCCP Komponen Sub Assembling 1 ................................................. 77

Tabel 4.54 RCCP Komponen Sub Assembling 2 ................................................. 78

Tabel 4.55 RCCP Komponen Assembling .......................................................... 79

Tabel 4.56 RCCP Komponen Pengemasan Mika ............................................... 80

Tabel 4.57 RCCP Komponen Pengemasan Kardus ............................................ 81

Tabel 4.58 Resume Jumlah Kapasitas yang Dibutuhkan ..................................... 82

Tabel 4.59 Perhitungan MRP Komponen Produk Mainan Level 0 ..................... 85

Tabel 4.60 Perhitungan MRP Komponen Rakitan Mainan Produk Mainan

Level 1 ............................................................................................... 86

Tabel 4.61 Perhitungan MRP Komponen Kemasan Level 1 ................................ 86

x
Tabel 4.62 Perhitungan MRP Komponen Bagian Atas Level 2 ........................... 86

Tabel 4.63 Perhitungan MRP Komponen Bagian Bawah Level 2........................ 87

Tabel 4.64 Perhitungan MRP Komponen Bagian Belakang Level 2.................... 87

Tabel 4.65 Perhitungan MRP Komponen Cerobong Level 3 ............................... 87

Tabel 4.66 Perhitungan MRP KomponenBadan Lokomotif Level 3 .................... 88

Tabel 4.67 Perhitungan MRP Komponen Pasak Belakang Level 3...................... 88

Tabel 4.68 Perhitungan MRP KomponenRoda Samping Kiri Level 3 ................. 88

Tabel 4.69 Perhitungan MRP KomponenAs Roda Depan Level 3 ....................... 89

Tabel 4.70 Perhitungan MRP Komponen Badan Bawah Level 3 ......................... 89

Tabel 4.71 Perhitungan MRP Komponen As Roda Belakang Level 3 ................. 89

Tabel 4.72 Perhitungan MRP Komponen Roda Samping Kanan Level 3 ............ 90

Tabel 4.73 Perhitungan MRP Komponen Pasak Depan Level 3 .......................... 90

Tabel 4.74 Perhitungan MRP Komponen Badan Atas Level 3 ............................ 90

Tabel 4.75 Perhitungan MRP KomponenAtap Level 3 ........................................ 91

Tabel 4.76 Perhitungan MRP Komponen Pengunci Roda Belakang Kiri Level 4

........................................................................................................... 91

Tabel 4.77 Perhitungan MRP Komponen Pengunci Roda Depan Kiri Level 4 .... 91

Tabel 4.78 Perhitungan MRP Komponen Perangkai Roda Kiri Level 4 .............. 92

Tabel 4.79 Perhitungan MRP Komponen Roda Depan Kiri Level 4 .................... 92

Tabel 4.80 Perhitungan MRP Komponen Roda Belakang Kiri Level 4 ............... 92

Tabel 4.81 Perhitungan MRP Komponen Pengunci Roda Belakang Kanan Level

4 ......................................................................................................... 93

Tabel 4.82 Perhitungan MRP Komponen Pengunci Roda Depan Kanan Level 4 93

xi
Tabel 4.83 Perhitungan MRP Komponen Perangkai Roda Kanan Level 4 .......... 93

Tabel 4.84 Perhitungan MRP Komponen Roda Depan Kanan Level 4 ................ 94

Tabel 4.85 Perhitungan MRP Komponen Roda Belakang Kanan Level 4 ........... 94

Tabel 4.86 Resume Planned Order Receipt MRP ................................................ 95

Tabel 4.87 Capacity Requirement Planning (CRP) Badan Bawah ..................... 96

Tabel 4.88 Capacity Requirement Planning (CRP) As Roda Depan .................. 96

Tabel 4.89 Capacity Requirement Planning (CRP) As Roda Belakang ............... 96

Tabel 4.90 Capacity Requirement Planning (CRP) Roda Depan Kanan ............. 96

Tabel 4.91 Capacity Requirement Planning (CRP) Roda Depan Kiri ................. 96

Tabel 4.92 Capacity Requirement Planning (CRP) Roda Belakang Kanan ......... 97

Tabel 4.93 Capacity Requirement Planning (CRP) Roda Belakang Kiri ............. 97

Tabel 4.94 Capacity Requirement Planning (CRP) Perangkai Roda Kanan ........ 97

Tabel 4.95 Capacity Requirement Planning (CRP) Perangkai Roda Kiri ........... 97

Tabel 4.96 Capacity Requirement Planning (CRP) Pengunci Roda Depan Kanan

........................................................................................................... 97

Tabel 4.97 Capacity Requirement Planning (CRP) Pengunci Roda Depan Kiri.. 98

Tabel 4.98 Capacity Requirement Planning (CRP) Pengunci Roda Belakang

Kanan ............................................................................................... 98

Tabel 4.99 Capacity Requirement Planning (CRP) Pengunci Roda Belakang Kiri

....................................................................................................... 98

Tabel 4.100 Capacity Requirement Planning (CRP) Roda Belakang Kiri .......... 98

Tabel 4.101 Capacity Requirement Planning (CRP) Badan Atas ........................ 98

Tabel 4.102 Capacity Requirement Planning (CRP) Atap .................................. 98

xii
Tabel 4.103 Capacity Requirement Planning (CRP) Pasak Belakang ................ 99

Tabel 4.104 Capacity Requirement Planning (CRP) Badan Lokomotif............... 99

Tabel 4.105 Capacity Requirement Planning (CRP) Cerobong .......................... 99

Tabel 4.106 Capacity Requirement Planning (CRP) Pasak Depan ...................... 99

Tabel 4.107 Capacity Requirement Planning (CRP) Sub-Sub Assembling 1 ...... 99

Tabel 4.108 Capacity Requirement Planning (CRP) Sub-Sub Assembling 2 ....... 99

Tabel 4.109 Capacity Requirement Planning (CRP) Assembling 1 .................. 100

Tabel 4.110 Capacity Requirement Planning (CRP) Assembling 2 ................... 100

Tabel 4.111 Capacity Requirement Planning (CRP) Pengemasan Mika .......... 100

Tabel 4.112 Capacity Requirement Planning (CRP) Pengemasan Kardus ........ 100

Tabel 4.113 Resume Jumlah Kebutuhan Aktual CRP ........................................ 100

Tabel 4.114 Perbandingan Alat Ukur ................................................................. 101

Tabel 4.115 Perbandingan Scrill Saw ................................................................. 101

Tabel 4.116 Perbandingan Mesin Drilling Ø6mm .............................................. 101

Tabel 4.117 Perbandingan Mesin Drilling Ø8mm .............................................. 101

Tabel 4.118 Perbandingan bubut ........................................................................ 101

Tabel 4.119 Perbandingan Pneudrem Sender ..................................................... 102

Tabel 4.120 Perbandingan Spray Gun ................................................................ 102

Tabel 4.121 Perbandingan Oven Dryer ............................................................... 102

Tabel 4.122 Perbandingan Kerja Bangku ........................................................... 102

Tabel 4.123 Perbandingan Sub-Sub Assembling 1 .............................................. 102

Tabel 4.124 Perbandingan Sub-Sub Assembling 2 .............................................. 103

Tabel 4.125 Perbandingan Sub Assembling 1 ..................................................... 103

xiii
Tabel 4.126 Perbandingan Sub Assembling 2 ..................................................... 103

Tabel 4.127 Perbandingan Assembling .............................................................. 103

Tabel 4.128 Perbandingan Kerja Bangku Pengemasan ...................................... 103

Tabel 4.129 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Alat Ukur......................................................................................... 104

Tabel 4.130 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Scrill Saw ...................................................................................... 104

Tabel 4.131 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Mesin Drilling Ø6mm ................................................................... 104

Tabel 4.132 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Mesin Drilling Ø8mm ................................................................... 104

Tabel 4.133 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

bubut.............................................................................................. 104

Tabel 4.134 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Pneudrem Sender .......................................................................... 105

Tabel 4.135 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Spray Gun ..................................................................................... 105

Tabel 4.136 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Oven Dryer .................................................................................... 105

Tabel 4.137 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Kerja Bangku ................................................................................ 105

Tabel 4.138 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Sub-Sub Assembling 1 ................................................................... 106

xiv
Tabel 4.139 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Sub-Sub Assembling 2 ................................................................... 106

Tabel 4.140 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Sub Assembling 1 .......................................................................... 106

Tabel 4.141 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Sub Assembling 2 .......................................................................... 106

Tabel 4.142 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Assembling ................................................................................... 107

Tabel 4.143 Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Kerja Bangku Pengemasan ........................................................... 107

xv
DAFTAR GAMBAR

Halaman

Gambar 2.1 Masukan dan keluaran PKM ............................................................. 22

Gambar 2.2 Kerangka Berpikir ............................................................................. 23

Gambar 3.1 Flowchart Penelitian ......................................................................... 35

Gambar 4.1 Bill Of Material Chart....................................................................... 37

Gambar 4.2 Grafik Forecasting dengan POMQM ............................................... 41

Gambar 4.3 Grafik Load Profile Alat Ukur ....................................................... 104

Gambar 4.4 Grafik Load Profile Scrill Saw ........................................................ 104

Gambar 4.5 Grafik Load Profile Mesin Drilling Ø6mm .................................... 104

Gambar 4.6 Grafik Load Profile Mesin Drilling Ø8mm .................................... 104

Gambar 4.7 Grafik Load Profile bubut .............................................................. 105

Gambar 4.8 Grafik Load Profile Pneudrem Sender............................................ 105

Gambar 4.9 Grafik Load Profile Spray Gun ....................................................... 105

Gambar 4.10 Grafik Load Profile Oven Dryer ................................................... 105

Gambar 4.11 Grafik Load Profile Kerja Bangku ................................................ 106

Gambar 4.12 Grafik Load Profile Sub-Sub Assembling 1 .................................. 106

Gambar 4.13 Grafik Load Profile Sub-Sub Assembling 2 .................................. 106

Gambar 4.14 Grafik Load Profile Sub Assembling 1.......................................... 107

Gambar 4.15 Grafik Load Profile Sub Assembling 2......................................... 107

Gambar 4.16 Grafik Load Profile Assembling .................................................. 107

Gambar 4.17 Grafik Load Profile Kerja Bangku Pengemasan ........................... 107

xvi
DAFTAR LAMPIRAN

Lampiran 1 Lampiran OPC (A1).

Lampiran 2 Lampiran Penyesuaian & Kelonggaran.

Lampiran 3 Lampiran Forecasting dengan POMQM.

Lampiran 4 Lampiran MRP dengan POMQM.

Lampiran 5 Jurnal Perencanaan Kebutuhan Material Menggunakan

Metode Lot-Sizing Dengan Penerapan Metode Forecasting

Time Series Dalam Perencanaan Produksi Di Konveksi XYZ.

Lampiran 6 Jurnal Perencanaan dan Penentuan Jadwal Induk Produksi di

P.T. Arwina Triguna Sejahtera.

xvii
BAB I

PENDAHULUAN

A. Latar Belakang

Sistem perencanaan dan pengendalian produksi terdiri dari beberapa

sub-sistem yang dirancang untuk mencapai secara utuh dua sasaran pokok

perencanaan dan pengendalian produksi yaitu tercapainya kepuasan

pelanggan dan tingginya tingkat utilisasi penggunaan sumber daya

produksi. Kerangka dasar pada sistem perancangan memperlihatkan dua

tipe integrasi yaitu pertama integrasi antara rencana jangka panjang, rencana

jangka menengah dan rencana operasional atau rencana eksekusi di lantai

pabrik dan kedua ialah integrasi antara unit-unit fungsional dalam setiap

fase perencanaan.

Rencana jangka menengah yang berjangka waktu paling lama satu

tahun yang sering dikenal sebagai rencana kerja tahunan memuat omset

tahunan yang merupakan terjemahan rencana jangka panjang ke dalam

rencana operasional. Perencanaan ini meliputi penguraian product group

menjadi satuan-satuan produk akhir (individual end products) yang disusun

dalam bentuk rencana induk produksi (master production schedule atau

MPS). Rencana induk produksi adalah suatu daftar yang memuat iumlah

masing-masing produk akhir yang akan dihasilkan per team-bucket. Time

bucket biasanya dinyatakan dalam mingguan sepanjang rentang/jangkauan

waktu perencanaan (time horizon) yang lamanya 6-12 bulan. Jadwal induk

1
2

produksi disusun dengan memperhatikan potensi permintaan, dan potensi

kapasitas. Potensi kapasitas dievaluasi dengan menggunakan teknik rough-

cut capacity planning (RCCP). Berdasarkan jadwal induk produksi

kemudian disusun jadwal perakitan produk akhir (final assembly schedule)

dan rencana kebutuhan bahan (material requirements plan atau MRP).

Rencana kebutuhan bahan (material requirements plan) disusun

dengan menguraikan produk akhir pada jadwal induk produksi kepada

kebutuhan part dan komponen berdasarkan bill of materials (BOM) dari

produk tersebut. bill of materials menjelaskan struktur/ hirarkis komponen

dan part yang membentuk produk akhir. Bill of materials menjelaskan

bagaimana produk akhir disusun dari komponen-komponennya secara

berjenjang. Dengan demikian hasil penguraian ini ialah sebuah daftar

panjang tentang part / komponen apa yang harus dibuat, berapa banyak

harus dibuat dan kapan harus sudah selesai dibuat sehingga jadwal perakitan

produk akhir dapat tedukung. Sebelum daftar panjang ini difinalkan,

kebutuhan bersih masing-masing part dan komponen dihitung dengan

mengurangi jumlah part atau komponen yang sebelumnya sudah tersedia di

gudang. Kemudian rencana kebutuhan kapasitas untuk pembuatan masing-

masing part dan komponen dihitung dengan bantuan bill of capacity.

Berdasarkan latar belakang permasalahan di atas, maka dalam praktikum

kali ini akan digunakan menggunakan pendekatan ilmu sistem produksi

yaitu dengan metode MRP. Data yang telah dikumpulkan


3

yaitu Bill of material dari komponen-komponen dan bahan yang digunakan

dalam produksi mainan kereta api kayu oleh PT Se Wooden Toys secara

rinci dari quantity, ukuran produk awal serta ukuran produk jadi.

B. Identifikasi Masalah

Dalam penelitian kali ini penulis akan mengidentifikasi

permasalahan yang akan dihadapi, adapun permasalahannya yaitu :

1. Belum diketahuinya total waktu siklus dan waktu keseluruhan pada

CRP.

2. Belum diketahuinya jumlah kapasitas mesin yang dibutuhkan pada

periode Januari sampai Desember 2022.

3. Belum diketahuinya jumlah kebutuhan aktual dengan Reated Capacity

pada produksi mainan kereta api.

C. Batasan Masalah

Adapun batasan masalah agar materi tidak meluas dan sesuai seperti

yang diharapkan kami menetapkan batasan masalah seperti berikut:

1. Penelitian dilakukan di PT. Se Wooden Toys.

2. Menggunakan data pada periode Januari 2021 sampai periode Desember

2022.

3. Pengolahan data hanya dilakukan dengan aplikasi Ms Excel dan

POMQM.
4

D. Rumusan Masalah

Dalam penulisan modul ini, penulis mencoba menguraikan sedikit

rumusan permasalahan yang akan dibahas dari materi yang berkaitan

dengan tema penulisan modul, adapun dalam penelitian ini juga terdapat

berbagai macam masalah yang ditemukan, diantaranya:

1. Berapa total waktu siklus dan waktu keseluruhan pada CRP?

2. Berapa jumlah kapasitas mesin yang dibutuhkan pada periode Januari

sampai Desember 2022?

3. Berapa jumlah kebutuhan aktual dengan Reated Capacity pada produksi

mainan kereta api?

E. Tujuan Penulisan

Adapun tujuan penulisan modul ini yaitu, sebagai berikut:

1. Untuk mengetahui total waktu siklus dan waktu keseluruhan pada CRP.

2. Untuk mengetahui jumlah kapasitas mesin yang dibutuhkan pada

periode Januari sampai Desember 2022.

3. Untuk mengetahui jumlah kebutuhan aktual dengan Reated Capacity

pada produksi mainan kereta api.


5

F. Sistematika Penulisan

Untuk memahami lebih jelas modul ini, maka materi-materi yang

tertera pada modul ini dikelompokan menjadi beberapa sub bab dengan

sistematika penyimpanan sebagai berikut:

BAB I PENDAHULUAN

Berisi latar belakang, identifikasi masalah, batasan masalah,

rumusan masalah, tujuan penulisan, dan sistematika penulisan

BAB II TINJAUAN PUSTAKA

Berisi kajian pustaka, kerangka berpikir dan penelitian yang relevan,

Dalam bab ini berisi materi yang berhubungan dengan material

requirements plan (MRP).

BAB III METEDOLOGI PENELITIAN

Berisi waktu dan tempat penelitian, metode penelitian, metode

pengumpulan data, teknik analisis data, dan flowchart penelitian.

BAB IV PENGOLAHAN DATA DAN ANALISIS

Berisi pengumpulan data, pengolahan data, serta pembahasan dan

analisis. Bab ini berisi pembahasan dan penyajian data yang

diperoleh.

BAB V SIMPULAN DAN SARAN

Berisi simpulan dan saran. Dalam bab ini berisi hasil penyajian data

yang telah diperoleh.

DAFTAR PUSTAKA

LAMPIRAN
BAB II

TINJAUAN PUSAKA

A. Kajian Pustaka

Pada umumnya tujuan akhir dari suatu perusahaan adalah untuk

memperoleh keuntungan, keberlanjutan dan pengembangan usaha. Di sisi

lain ada tuntutan konsumen yang harus dipenuhi perusahaan. Tuntutan

konsumen pada umumnya meliputi kualitas baik, harga murah, penyerahaan

tepat volume dan waktu, produk fleksibel dan variatif. Supaya tujuan kedua

belah pihak (produsen dan konsumen) terpenuhi maka perusahaan harus

mampu membuat perencanaan dan pengendalian produksi dengan

memperhatikan semua tujuan tersebut. (Rus Indiyanto, 2008)

1. Forecast

Peramalan adalah suatu usaha untuk meramalkan keadaan dimasa

yang akan datang berdasarkan keadaan atau data-data di masa lalu.

Dengan demikian peramalan merupakan salah satu hal yang harus

diperhatikan oleh perusahaan karena dapat menjadi dasar dalam

menentukan berapa jumlah barang yang akan diproduksi dan berapa

jumlah bahan baku yang dibutuhkan agar produksi dapat berjalan lancar.

(Muhammad Nasir Sidiq, dkk,2017)

Ada banyak teknik peramalan yang dibuat untuk berbagai

keadaan. Hal tersebut dimaksudkan untuk meminimumkan kesalahan

6
7

forecast, karena suatu teknik peramalan cocok untuk meramal dalam

kondisi ini, tetapi tidak cocok untuk meramal pada kondisi lain.

Pendapat para ahli mengenai teknik peramalan adalah sama. Sehingga

penjelasan hal tersebut dari salah satu ahli sudah mewakili pendapat dari

ahli-ahli yang lain. (Handoko) menjelaskan bahwa ada berbagai teknik

peramalan yang tersedia diantaranya adalah sebagai berikut.

(Muhammad Nasir Sidiq, dkk,2017) :

a. Teknik Peramalan Kualitatif

Teknik peramalan kualitatif adalah "judgmental" atau

berdasarkan estimasi-estimasi dan pendapat-pendapat. Berbagai

peramalan kualitatif yang dapat digunakan, secara ringkas dapat

diuraikan sebagai berikut :

1) Metode Delphi

Metode Delphi merupakan teknik yang mempergunakan

suatu prosedur yang sistematik untuk mendapatkan suatu

konsensus pendapat dari suatu kelompok ahli.

2) Riset Pasar

Riset pasar adalah peralatan peramalan yang berguna bila

ada kekurangan data historik. teknik ini secara khusus digunakan

untuk meramal permintaan jangka panjang dan penjualan

produk baru.

3) Analogi Historik
8

Peramalan dilakukan dengan menggunakan pengalaman-

pengalaman historik dari suatu produk yang sejenis.

4) Konsensus Panel

Gagasan yang didiskusikan oleh kelompok yang akan

menghasilkan ramalan yang lebih baik daripada dilakukan oleh

seorang saja.

a) Peramalan dengan Rata-Rata Bergerak

Rata-rata bergerak diperoleh melalui penjumlahan

dan pencarian nilai rata-rata dari sejumlah periode tertentu,

Setiap kali menghilangkan nilai terlama dan menambah

nilai baru. Ada dua sifat khusus dari metode moving

average atau rata-rata bergerak menurut Subagyo dalam

yaitu pertama untuk membuat forecast dengan metode

moving average membutuhkan data historis selama jangka

waktu tertentu. Kedua semakin lama jangka waktu moving

average akan menghasilkan moving averages yang

semakin halus. (Muhammad Nasir Sidiq, dkk,2017)

b) Peramalan dengan single exponential smoothing

Menurut Subagyo dalam metode exponential

smoothing adalah perkembangan dari metode moving

average. Metode ini menggunakan nilai a yang relative

bebas. Besarnya a antara 0 sampai dengan 1. Kalau a

mendekati 1 berarti data terakhir lebih diperhatikan atau


9

diberi weight lebih besar dari pada data-data

sebelumnya.Selain itu metode single eksponential

smoothing cocok digunakan untuk meramal hal-hal yang

fluktuasinya random (acak). (Muhammad Nasir Sidiq,

dkk,2017)

2. Capacity Requriments planning ( CRP )

Capacity Requirements planning (perencanaan kebutuhan

kapasitas jangka pendek) adalah proses penentuan kebutuhan kapasitas

untuk memenuhi rencana pembuatan bahan yang tertera dalam program

manufaktur di lantai pabrik. Perlu diketahui bahwa perencanaan

kebutuhan kapasitas ini hanya difokuskan pada kapasitas stasiun kerja

yang bersifat kritis yang disebut bottleneck work center capacity.

Pengalaman lapangan dalam proses manufaktur memberikan pelajaran

bahwa tidak semua stasiun kerja yang digunakan dalam proses

manufaktur mengalami masalah misalnya sering mengalami situasi

overloaded sehingga memunculkan antrian Panjang dibelakang stasiun

kerja itu. Kenyataan menunjukkan bahwa paling banyak hanya 1 - 3

stasiun kerja saja yang sering mengalami overloaded sedangkan sisanya

bahkan underloaded. Oleh karena itu hanya terhadap stasiun kerja kritis

saja yang perlu dilakukan perencanaan kebutuhan kapasitas secara

detail. Teknik perencanaan kebutuhan kapasitas jangka pendek dapat

dibedakan atas cara yaitu capacity planning Factors, Bill of Capacity,


10

Time-phased Bill of Capacity dan Timephased CRP. (Sukaria

Sinulingga,2019)

a. capacity planning Factors (CPF)

Capacity Planning Factor adalah unit konversi yang

digunakan untuk mengkonversikan rencana output stasiun kerja ke

dalam jumlah unit kapasitas yang dibutuhkan untuk memproduksi

jumlah output tersebut. Teknik ini mendasarkan perhitungan

kebutuhan kapasitas standar. Ada beberapa cara untuk menentukan

kapasitas standar, salah satu di antaranya ialah berdasarkan rata-

rata kapasitas riil selama satu tahun terakhir. Kebutuhan kapasitas

rata-rata ialah jumlah kapasitas yang digunakan pada masa lalu

misalnya dalam tahun lalu dibagi dengan jumlah unit output yang

dihasilkan dalam periode tersebut. (Sukaria Sinulingga,2019)

b. Bill of Capacity (BOC)

Bill of Capacity (BOC) menyatakan besarnya kapasitas

stasiun kerja yang dibutuhkan untuk memproduksi satu unit produk

A selain data dari Bill of Materials product structure tree, data-data

utama lain yang dibutuhkan daram menentukan Bill of Capacity

ialah data-data rute operasi. Data rute operasi memperlihatkan rute

proses operasi pembuatan masing-masing part, komponen dan sub-

assembly yang dibutuhkan dalam tiap unit produk akhir yang akan

dihasilkan, stasiun kerja yang digunakan, waktu setup, waktu


11

operasi dan waktu pindah antar operasi (interoperation time) dan

ukuran lot. (Sukaria Sinulingga,2019)

c. Time Phased Bitt of Capacity (TPBOC)

Time-Phased Bill of Capacity sering juga disebut product

load profile menetapkan kebutuhan kapasitas berdasarkan

backward scheduling terhadap jadwal induk produksi dengan

menggunakan waktu ancang-ancang standar. (Sukaria

Sinulingga,2019)

d. Time Phased Capacity Requirements

Time-Phased Capacity Requirements menghitung

kebutuhan kapasitas setiap stasiun kerja berdasarkan proses

backward scheduling hanya saja dalam pendekatan ini tidak

digunakan bill of capacity. Kebutuhan kapasitas pada setiap stasiun

kerja dihitung dengan cara mengalikan jumlah unit yang akan

dikerjakan pada stasiun kerja tersebut dengan waktu operasi/unit

dan kemudian ditambah dengan waktu setup. (Sukaria

Sinulingga,2019)

3. Master Production Schedule (MPS)

Rencana induk produksi atau biasa disingkat MPS/JIP adalah

pernyataan tentang produk akhir, atau disebut juga produk akhir pada

perusahaan manufaktur yang membuat rencana produksi, dimana

keluarannya berkaitan dengan jumlah, jangka waktu, dan rencana. Data


12

master produksi ini dipecah dan rencana produksi diimplementasikan di

perusahaan industri manufaktur. (Peppy Anggela, dkk, 2017)

Menurut Vincent Gaspersz, Pada dasarnya jadwal produksi

induk (master production schedule) merupakan suatu pernyataan

tentang produk akhir (termasuk parts pengganti dan suku cadang) dari

suatu perusahaan industry manufaktur yang merencanakan

memproduksi output berkaitan dengan kuantitas dan periode waktu.

Aktivitas Master Production Scheduling (MPS) pada dasarnya berkaitan

dengan bagaimana menyusun dan memperbaharui jadwal produksi

induk (master production schedule), memproses transaksi dari MPS,

dan memberikan laporan evaluasi dalam periode waktu yang teratur

untuk keperluan umpan balik dan tinjauan ulang. (Muhammad Nasir

Sidiq, dkk,2017)

Penjadwalan produksi induk ada dasarnya berkaitan dengan

aktivitas melakukan empat fungsi utama berikut. (Muhammad Nasir

Sidiq, dkk,2017) :

a. Menyediakan atau memberikan input utama kepada sistem

perencanaan kebutuhan material dan kapasitas (material and

capacity planning/M&CRP).

b. Menjadwalkan pesanan-pesanan produksi dan pembelian

(production and purchase ordes) untuk item-item MPS.

c. Memberikan landasan untuk penentuan kebutuhan sumber daya dan

kapasitas.
13

d. Memberikan basis untuk pembuatan janji tentang penyerahan

produk (delivery promises) kepada pelanggan.

Adapun beberapa yang menjadi tujuan penjadwalan produksi

induk diantaranya yaitu. (Muhammad Nasir Sidiq, dkk,2017) :

a. Memenuhi target tingkat pelayanan terhadap konsumen.

b. Efisiensi dalam penggunaan sumber daya produksi.

c. Mencapai target tingkat produksi.

sebagai suatu aktivitas proses, penjadwalan produksi induk

(MPS) membutuhkan lima input utama, yaitu. (Muhammad Nasir Sidiq,

dkk,2017) :

a. Data permintaan total merupakan salah satu sumber data bagi proses

penjadwalan produksi induk. Data permintaan total berkaitan

dengan ramalan penjualan (sales forecasts) dan pesanan-pesanan

(orders).

b. Status inventori berkaitan dengan informasi tentang on-hand

inventory, persediaan yang dialokasikan untuk penggunaan tertentu

(allocated stock), pesanan-pesanan produksi dan pembelian yang

dikeluarkan (released production and purchase orders), danfirm

planned orders.

c. Rencana produksi memberikan sekumpulan batasan kepada MPS.

MPS harus menjumlahkannya untuk menentukan

tingkat produksi, inventory, dan sumber-sumber daya lain dalam

rencana produksi tersebut.


14

d. Data perencanaan berkaitan dengan aturan-aturan tentang lot-sizing

yang harus digunakan, shrinkage factor, persediaan pengaman

(safety stock), dan waktu tunggu (lead time) dari masing-masing

item yang biasanya tersedia dalam file induk dari item (Item Master

File).

e. Informasi dari Rough Cut Capacity Planning (RCCP) berupa

kebutuhan kapasitas untuk mengimplementasikan MPS menjadi

salah satu input bagi MPS. RCCP menentukan kebutuhan kapasitas

untuk mengimplementasikan MPS, menguji kelayakan dari MPS,

dan memberikan umpan-balik kepada perencana atau penyusun

jadwal produksi induk untuk mengambil tindakan perbaikan apabila

ditemukan adanya ketidaksesuaian antara penjadwalan produksi

induk dan kapasitas yang tersedia.

Tugas dan Tanggung Jawab Penyusun Jadwal Produksi Induk

Tugas dan tanggung jawab profesional dari penyusun jadwal produksi

induk (master production schedule) dalam adalah membuat perubahan

perubahan pada catatan MPS, mendisagregasikan rencana produksi

untuk menciptakan MPS, menjamin bahwa keputusan-keputusan

produksi yang ada dalam MPS itu telah sesuai dengan rencana produksi,

dan yang terpenting adalah mengkomunikasikan hal-hal utama dalam

MPS itu kepada bagian-bagian lain yang terkait dalam perusahaan.

(Muhammad Nasir Sidiq, dkk,2017)


15

Beberapa Pertimbangan dalam Desain MPS Ketika akan

mendesain MPS, perlu diperhatikan beberapa faktor utama yang

menentukan proses penjadwalan produksi induk (MPS). Beberapa

faktor utama tersebut adalah Lingkungan manufakturing sangat

menentukan proses penjadwalan produksi induk (MPS). (Muhammad

Nasir Sidiq, dkk,2017)

Lingkungan manufakturing yang umum dipertimbangkan ketika

akan mendesain MPS adalah make to stock,make to order, dan assemble

to order. Produk-produk dari lingkungan make to stock biasanya dikirim

secara langsung dari gudang produk akhir, dan karena itu harus ada

persediaan sebelum pesanan pelanggan (customer order) tiba. Hal ini

berarti produk akhir harus dibuat atau diselesaikan terlebih dahulu

sebelum menerima pesanan pelanggan. Produk-produk dari lingkungan

make to order biasanya baru dikerjakan atau diselesaikan setelah

menerima pesanan pelanggan. Seringkali komponen-komponen yang

mempunyai waktu tunggu panjang (long lead time) direncanakan atau

dibuat lebih awal guna mengurangi waktu tunggu penyerahan kepada

pelanggan, apabila pelanggan memesan produk. (Muhammad Nasir

Sidiq, dkk,2017)

Pada dasarnya produk-produk dalam lingkungan assemble to

order adalah make to order product, dimana semua komponen

(semifinished, intermediate, subassembly, fabricated, purchased,dan

lain-lain) yang digunakan dalam assembly, pengepakan, atau proses


16

akhir, direncanakan atau dibuat lebih awal, kemudian disimpan dalam

persediaan guna mengantisipasi pesanan pelanggan. (Muhammad Nasir

Sidiq, dkk,2017)

Berikut ini akan dikemukakan penjelasan singkat berkaitan

dengan informasi yang ada dalam MPS seperti di bawah ini.

(Muhammad Nasir Sidiq, dkk,2017) :

a. Lead Time adalah waktu (banyaknya periode) yang dibutuhkan

untuk memproduksi atau membeli suatu item.

b. On Hand adalah posisi inventori awal yang secara fisik tersedia

dalam stock, yang merupakan kuantitas dari item yang ada dalam

stock.

c. Lot Size adalah kuantitas dari item yang biasanya dipesan dari pabrik

atau pemasok.

d. Safety Stock adalah persediaan tambahan dari item yang

direncanakan untuk berada dalam inventori yang dijadikan sebagai

persediaan pengaman guna mengatasi fluktuasi dalam ramalan

penjualan, pesananpesanan pelanggan dalam waktu singkat,

penyerahan item untuk pengisian Kembali inventori.

e. Time Bucket pembagian planning periode yang digunakan dalam

MPS atau MRP.

f. Time Phase Plan adalah penyajian perencanaan, dimana demand,

order, inventory disajikan dalam time bucket.

g. Time Fences adalah batas waktu penyesuaian pesanan.


17

h. Demand Time fence (DTF) adalah periode mendatang dari MPS

dimana dalam periode ini perubahan-perbahan terhadap MPS tidak

diijinkan atau tidak diterima karena akan menimbulkan kerugian

biaya yang besar akibat ketidaksesuaian atau kekacuan jadwal.

i. Planning Time Fence (PTF) adalah periode mendatang dari MPS

dimana dalam periode ini perubahan-perubahan terhadap MPS

dievaluasi guna mencegah ketidaksesuaian atau kekacuan jadwal

yang akan menimbulkan kerugian.

j. Time Periods For Display adalah banyaknya periode waktu yang

ditampilkan dalam format MPS.

k. Sales Plan (sales Forecast) merupakan rencana penjualan atau

peramalan penjualan untuk item yang dijadwalkan itu.

l. Actual Orders merupakan pesanan-pesanan yang diterima dan

bersifat pasti (certain).

m. Profected Available Balances (PAB) merupakan informasi proyeksi

on-hand inventory dari waktu ke waktu selama horizon perencanaan

MPS.

n. Available-To-Promise (ATP) merupakan informasi yang sangat

berguna bagi departemen pemasaran untuk mampu memberikan

jawaban yang tepat terhadap pertanyaan pelanggan.

o. Master Production Schedule (MPS) merupakan jadwal produksi atau

manufacturing yang diantisipasi untuk item tertentu.


18

p. Planning Horizon adalah jangka waktu perencanaan yang

digunakan.

4. Rought Cut Capacity Planning (RCCP)

Rought Cut Capacity Planning dapat didefinisikan sebagai

proses konversi dari Rencana Produksi dan atau MPS ke dalam

kebutuhan kapasitas yang berkaitan dengan sumber-sumber daya kritis.

Rought Cut Capacity Planning digunakan untuk menguji kelayakan

kapasitas dari suatu rencana jadwal induk produksi (MPS) sebelum

MPS ditetapkan Validasi pada RCCP dikatakan layak apabila kapasitas

yang dibutuhkan semuanya dapat dipenuhi oleh kapasitas tersedia.

Menurut Kusuma, untuk melakukan perhitungan kebutuhan kapasita

dengan menggunakan metode Rought Cut Capacity Planning

dibutuhkan masukan berupa. (Muhammad Nasir Sidiq, dkk,2017):

a. Ramalan permintaan dan rencana produksi yang dihasilkan dari

proses peramalan, perencanaan agregat serta disagregasi

b. Struktur produk dan bill of material (BOM).

c. Waktu setup dan waktu proses suatu produk disuatu departemen.

d. Jumlah produksi yang ekonomis dari produk tersebut.

5. Material Requirement Planning (MRP )

Perkembangan teknologi komputer telah memberikan

sumbangan yang besar artinya di dalam sistem pengendalian persediaan.

Sumbangan ini dibuktikan dengan dimungkinkan lahirnya metoda baru

yang disebut Perencanaan Kebutuhan Material (PKM) atau lebih


19

dikenal dengan Material Requirement Planning (MRP). Metoda ini

terdiri dari sekumpulan prosedur, aturan-aturan keputusan dan

seperangkat mekanisme pencatatan yang berkaitan secara logis dan

dirancang untuk menjabarkan suatu jadwal induk produksi (JIP) ke

dalam kebutuhan setiap konsumen atau material yang dibutuhkan.

Jadwal kebutuhan ini meliputi kapan dan berapa jumlah komponen atau

material yang diperlukan atau dipesan. (Rus Indiyanto, 2008)

Perencanaan kebutuhan material merupakan suatu sistem time

phase order point, karena mampu mengintegrasikan antara waktu dan

jumlah kebutuhan komponen atau material. Penambahan dimensi waktu

ini mengharuskan adanya informasi tentang status persediaan untuk

menjawab pertanyaan-pertanyaan berikut. (Rus Indiyanto, 2008):

a. Apa yang dipunyai ?

b. Apa yang dibutuhkan ?

c. Apa yang harus dilakukan ?

Adanya dimensi waktu inilah yang membedakan dan sekaligus

merupakan kelebihan PKM terhadap teknik pengendalian persediaan

tradisional. Ada dua tipe sistem PKM yang dikenal sampai saat ini, yaitu

sistem regeneratif dan sistem net change. Perbedaan utama

antarakeduanya terletak pada frekuensi perencanaan ulang. (Rus

Indiyanto, 2008)

a. Sistem regeneratif
20

Sistem regeneratif melakukan perencanaan ulang secara

periodik (biasanya mingguan) berdasarkan keadaan JIP yang

terakhir. Semua kebutuhan di explode secara periodik dan lengkap

dari JIP, mulai dari produk akhir yang akan dibuat sampai ke bahan

baku yang akan dibeli. Sistem ini sesuai untuk keadaan dimana

frekuensi perencanaan ulang rendah di dalam sistem manufaktur

yang membuat produk secara batch. Keuntungan sistem ini adalah

penggunaan alat pemrosesan data lebih efisien jika digunakan pada

keadaan yang cukup stabil. Sedangkan kerugiannya adalah sistem

ini tidak terlalu peka terhadap ketidak seimbangan permintaan dan

kemampuan untuk memenuhinya. (Rus Indiyanto, 2008)

b. Sistem net change

Sistem net change merupakan sistem yang relatif baru.

Konsep dasarnya adalah proses explosion hanya dilakukan apabila

terjadi perubahan pada JIP atau keadaan persediaan maupun status

pemesanan untuk semua item. Keuntungan sistem ini akan selalu

memberikan catatan-catatan pada kondisi yang baru. Kerugiannya,

sistem ini lebih mahal karena pemrosesan data lebih sering

dilakukan. Sistem ini baik dipakai unuk kondisi dimana keadaan

sangat tidak menentu (berubah-ubah). (Rus Indiyanto, 2008)

Persyaratan untuk Material Requirement Planning (MRP)

adalah sebagai berikut. (Rus Indiyanto, 2008) :


21

a. Tersedianya jadwal induk produksi, yaitu suatu rencana yang rinci

yang menetapkan jumlah serta waktu suatu produk akhir harus

tersedia.

b. Setiap komponen atau material harus mempunyai identifikasi yang

khusus, hal ini disebabkan karena biasanya PKM menggunakan

komputer. Tersedianya struktur produk,.

c. Tersedianya catatan tentang persediaan untuk semua item yang

menyatakan status persediaan yang ada sekarang dan yang akan

datang (direncanakan)

Sedangkan asumsi yang diperlukan untuk Material

Requirement Planning (MRP) adalah sebagai berikut. (Rus

Indiyanto, 2008):

a. Adanya data file yang terintegrasi dengan melibatkan data status

persediaan dan data tentang struktur produk.

b. Waktu ancang-ancang (lead time) untuk semua item diketahui,

paling tidak dapat diperkirakan.

c. Setiap item persediaan selalu ada dalam pengendalian.

d. Pengadaan dan pemakaian komponen bersifat diskrit.

Secara skematis masukan dan keluaran Material Requirement

Planning (MRP) atau Sistem Perencanaan Kebutuhan (PKM) dapat

dilihat pada gambar 2.1 berikut ini :


22

Gambar 2.1
Masukan dan keluaran PKM
Sumber : Ebook Perencanaan dan pengendalian produksi

Ada tigas masukan utama yang diperlukan dalam mekanisme

bekerjanya PKM yaitu. (Rus Indiyanto, 2008) :

a. Jadwal Induk Produksi (JIP)

b. Catatan Status Persediaan

c. Struktur Produk
23

B. Kerangka Berpikir

Permasalahan
1. Belum diketahuinya total waktu siklus dan waktu keseluruhan pada
CRP.
2. Belum diketahuinya jumlah kapasitas mesin yang dibutuhkan pada
periode Januari sampai Desember 2022.
3. Belum diketahuinya jumlah kebutuhan aktual dengan Reated Capacity
pada produksi mainan kereta api.

Data
Data yang terkumpul adalah data yang didapat dari
pengobservasi langsung melihat data pembuatan mainan
kereta api yang dibuatkan chart dan table bill of
material.

Pengolahan data
1. Mengolah data dengan metode Forecasting, Rough Cut Capacity
Planning, Master Planning Schedule, Capacity Rrequirement Planning
2. Menyimpulkan data dengan membuat grafik Load Actual Capacity dan
Material Requirement Planning

Analisis
Penelitian ini bertujuan untuk menganalisa pembuatan mainan kereta api kayu
dengan penggunaan metode Forecasting, Rough Cut Capacity Planning,
Capacity Requirement Planning dan akhiri dengan table Material Requirement
Planning dan pembuatan grafik Load Actual Capacity, Master Planning
Schedule

Hasil yang diharapkan


Dapat mengetahui jumlah kebutuhan aktual yang diperlukan untuk
membuat komponen-komponen mainan kereta api serta dapat menghitung
perbandingan kebutuhan aktual dengan kapasitas yang tersedia.

Gambar 2.2
Kerangka berpikir
Sumber : penelitian
24

C. Penelitian Yang Relevan

1. Angela, Peppy. 2022. Perencanaan Kebutuhan Material Menggunakan

Metode Lot-Sizing Dengan Penerapan Metode Forecasting Time Series

Dalam Perencanaan Produksi Di Konveksi XYZ. Journal of Industrial

& Quality Engineering, Vol. 10.e-ISSN : 2622-5816.

Isi jurnal : Konveksi XYZ merupakan industri yang bergerak di bidang

produksi sekaligus memasarkan atau melakukan penjualan baju gamis.

Usaha ini didirikan pada tahun 2012 di Kabupaten Sambas, Kalimantan

Barat. Berdasarkan data historis yang diperoleh, permintaan baju gamis

di Konveksi XYZ mengalami fluktuasi tidak menentu yang

menyebabkan perusahaan terkadang melakukan produksi dalam jumlah

yang berlebih dan memproduksi dalam jumlah yang tidak mencukupi,

sehingga menyebabkan kegiatan penjualan yang tidak optimal. Tujuan

dari penelitian ini adalah untuk mengoptimalkan rencana produksi untuk

memenuhi permintaan di masa mendatang. Tahapan dalam penelitian

ini adalah pengumpulan data, plotting data, peramalan dengan

menggunakan metode time series yaitu metode peramalan yang

digunakan tergantung pada pola data yang didapatkan, melakukan uji

validasi terhadap metode yang terpilih, membuat RRP untuk

mengetahui slot kapasitas produksi yang dapat digunakan dari over time

dan regular time, melakukan perencanaan agregat, membuat jadwal

induk produksi, membuat RCCP dan melakukan perencanaan

kebutuhan material menggunakan 4 metode lot-sizing, yaitu metode


25

LFL yaitu metode perhitungan yang dilakukan bersifat dinamis, EOQ

yaitu metode perhitungan yang menggunakan besar lot yang tetap,

namun menggunakan ongkos simpan dan pesan , POQ yaitu metode

perhitungan pemesanannya berdasarkan hasil EOQ dan FPR yaitu

metode dengan teknik waktu antar tetap namun ukuran lot yg digunakan

sesuai dengan kebutuhan bersih. Hasil penelitian menunjukkan bahwa

metode terbaik adalah metode centered moving average, dikarenakan

memiliki nilai MSE terkecil yaitu 4050,13, MAD terkecil yaitu 47,11

serta MAPE terkecil yaitu 11,06%. Total biaya yang dibutuhkan untuk

produksi baju gamis selama 12 periode yaitu sebesar Rp

319.120.000,00. Sedangkan perencanaan kebutuhan bahan baku

digunakan metode LFL dan metode POQ, dengan total biaya bahan baku

baju gamis yang diperlukan untuk 12 periode kedepan yaitu sebesar Rp

428.884.300. Diperoleh biaya untuk masing-masing bahan baku yaitu,

bahan baku kain sebesar Rp 456.460.000, resleting sebesar Rp

10.448.000, kancing baju sebesar 1.036.000, kain vislin sebesar Rp

1.840.000, benang jahit sebesar Rp 7.836.000 dan benang obras sebesar

Rp 5.224.000. . Sehingga dampak dari penelitian ini ialah, dapat

meminimalkan biaya kebutuhan bahan baku.


26

2. Sidiq, Muhammad Nasir. 2022. Perencanaan dan Penentuan Jadwal

Induk Produksi di P.T. Arwina Triguna Sejahtera. Jurnal Media Teknik

& Sistem Industri , Vol. 1(2017) hal.11-25. e-issn:2581-0561

Isi jurnal : P.T. Arwina Triguna Sejahtera merupakan perusahaan yang

bergerak dalam bidang produksi moulding. Masalah umum pada tiap

perusahaan termasuk P.T. Arwina Triguna Sejahtera adalah mengalami

kendala dalam merencanakan jumlah produksi sesuai kapasitas

produksi. Sehingga direncanakan dibuat jadwal induk produksi agar

biaya tidak terlalu tinggi. Langkah-langkah yang dilakukan yaitu

dengan dimulai melakukan pengolahan data masa lalu dengan

menggunakan agregasi demand, kemudian melakukan peramalan yang

sesuai dengan karakteristik demand. Perencanaan prosuksi agregat

dilakukan untuk 1 periode (tahun) ke depan dengan menggunakan

strategi tenaga kerja tetap. Kemudian berlanjut pada tahap disagregasi

dengan menggunakan metode proporsi, perhitungan Master Production

Schedule untuk mengetahui berapa banyak jumlah produk yang harus

diproduksi, serta kapan harus memulai produksi tersebut. Terakhir

melakukan perhitungan Rought Cut Capacity Planning agar diketahui

keseimbangan antara kapasitas yang tersedia dengan kapasitas yang

dibutuhkan. Jadwal induk produksi yang diperoleh, produksi akan

lancar dan mampu memenuhi actual demand yang ada sebanyak 20,000

pcs dengan cara menambahkan jam lembur dan menghasilkan end item

sebanyak 2,368 pcs untuk produk sendok deabetamil, sedangkan untuk


27

produk plastic featherlock s brown permintaan aktual dapat terpenuhi.

Kelayakan jadwal induk produksi dihitung berdasarkan kesesuaian

antara Regular Man Hour pada rencana produksi, dengan jumlah waktu

pada perhitungan kapasitas tersedia yang berjumlah sama yaitu

sebanyak 171,360 jam dalam memenuhi permintaan untuk tahun ini.


BAB III

METODOLOGI PENELITIAN

A. Waktu dan Tempat Penelitian

1. Waktu penelitian

Proses penelitian ini dilakukan seminggu dimulai sejak tanggal 23

september 2022 hingga 14 Oktober 2022 untuk pengumpulan data dan

mengolah penelitian pada modul ini.

Tabel 3.1

Ganttchart Penelitian
SEPTEMBER OKTOBER
MINGGU
MINGGU KE 2 MINGGU KE 3 MINGGU KE 4
Kegiatan KE 1
2 2 2 2 2 2 2 3 1 1 1 1
3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 14
BAB I
BAB II
BAB III
BAB IV
BAB V
ASISTE
NSI
PJM
PENGU
MPULA
N
MODUL
Sumber : hasil Penelitian

2. Tempat Penelitian

Penelitian dilakukan di PT SE Wooden Toys yang beralamat di

Jl.MelatiRaya No.4A Kalisari Ps.Rebo Jakarta Timur DKI Jakarta 13710

yang lalu diolah oleh tim.

28
29

B. Metode Penelitian

Metode yang kami gunakan untuk penelitian ini adalah metode MRP

dan penelitian kuantitatif yaitu cara yang digunakan untuk menjawab

masalah penelitian yang berkaitan data yang dapat diukur angka dan

berkaitan dengan ilmu statistika.

Karakteristik dari MRP biasanya tidak rinci, hal ini dikarenakan

perencanaan produksi dinyatakan dalam kelompok produk atau famili

(agregat). Satuan unit yang dipakai dalam perencanaan produksi bervariasi

dari satu pabrik ke pabrik lain. faktor konversi harus ditetapkan sebagai alat

komunikasi dengan deperatemen lainnya seperti departemen pemasaran

danakuntansi bisa berdasarkan satuan menit atau satuan harga yang sudah

ditetapkan dan disesuaikan dengan kebutuhan perusahaan.

Adapun tujuan dari penelitian ini adalah sebagai berikut :

a. Mengetahui bagaimana menetukan jumlah produk yang harus di

produksi untuk periode berikutnya

b. Mengetahui rencana produksi untuk periode mendatang dapat

ditanggulangi atau tidak oleh perusahaan dengan ketentuan

kemampuan kapasitas produksi perusahaan.

C. Metode pengumpulan data

Dalam metode pengumpulan data pada penelitian ini penulis

menggunakan metode berupa data primer dan sekunder. Data primer yaitu

data yang diperoleh langsung dari subjek sumber pertama.


30

1. Data Primer

Pengumpulan data primer dalam penelitian ini adalah Data primer

merupakan sumber data penelitian yang diperoleh secara langsung dari

sumber aslinya yaitu diperoleh dari hasil observasi terhadap komponen

mainan kereta api kayu baik secara visual atau dimensi.

Dalam hal ini tugas peneliti adalah menentukan 19 bentuk data yang

akan diukur, karakteristik yang akan diteliti dan melakukan pengukuran

serta pengumpulan data dengan teknik-teknik seperti BOM (Bill Of

Material), direct dan Indirect material.

2. Data Sekunder

Pengumpulan Data sekunder didapat dengan cara tidak langsung,baik

dari literatur maupun jurnal-jurnal yang memfokuskan tentang

penelitian terdahulu. Penghitungan data terkait Forecasting, Rough Cut

Capacity Planning, Master Planning Schedule, Capacity Rrequirement

Planning.

D. Teknik Analisis Data

1. Forecasting (Peramalan)

Peramalan menurut pandangan (Nasution, 2008) adalah Proses

memperkirakan permintaan masa depan dengan memasukkan kuantitas,

kualitas, waktu, dan lokasi yang dibutuhkan untuk memenuhi

permintaan barang atau jasa.

Langkah-langkah berikut diperlukan untuk melakukan peramalan :

a. Tentukan tujuan ramalan


31

b. Mengevaluasi serta menganalisis data yang sesuai

c. Memilih dan menguji metode peramalan

d. Memantau keakurasian peramalan

Fungsi peramalan adalah memprediksi apa yang akan terjadi di masa

depan berdasarkan variabel atau kemungkinan yang ada. Potensi dan

kelemahan perusahaan harus benar-benar diperhatikan. Buatlah prediksi

sebelum membuat rencana.

Menurut (Hanke, 2005), ada 4 jenis pola data, yakni sebagai berkut

a. Pola data horizontal

b. Pola data trend

c. Pola data musiman

d. Pola data siklis

Metode Peramalan yang dipergunakan tergantung dari pola data

yang didapatkan. Peramalan data menggunanakan metode time series

membutuhkan teknik peramalan yang baik dan benar. Contoh data time

series seperti pertumbuhan ekonomi suatu negara dalam setahun,

produksi minyak perbulan, atau indeks harga saham harian..

2. Capacity Requirement Planning

Tujuan dari Resource Requirement Planning adalah untuk

mengetahui seberapa besar slot kapasitas dari nilai Over Time dan

Regular Time, apabila kapasitas dan Regular Time tidak dapat

memenuhi permintaan maka dapat digunakan. RRP dapat digunakan


32

untuk merencanakan sumber daya produksi seperti mesin/peralatan,

pekerja, dan modal sesuai dengan rencana produksi

Tujuan Agregat Planning yaitu untuk mengecilkan biaya produksi

dengan mengecilkan kuantitas produksi, tenaga kerja, inventory , dan

faktor lainnya..

a. Menghitung Rencana Produksi Σ RP = Σ demand + safety stock –

inventory awal

b. Menghitung reguler man hour (RMH) RMH = jmltenagakerja x

harikerja x jam kerja

c. Menghitung Produksi Normal / Unit Production Regular

Time(UPRT)
𝑅𝑀𝐻
Produksi Normal = 𝑊𝑎𝑘𝑡𝑢 𝑏𝑎𝑘𝑢 X Persen produktivitas

d. Menghitung kapasitas Produksi Normal (UPRT) KAP produksi

𝐽𝑢𝑚𝑙𝑎ℎ 𝑡𝑒𝑛𝑎𝑔𝑎 𝑘𝑒𝑟𝑗𝑎 𝑥 ℎ𝑎𝑟𝑖 𝑘𝑒𝑟𝑗𝑎 𝑥 𝑗𝑎𝑚 𝑘𝑒𝑟𝑗𝑎


normal = 𝑊𝑎𝑘𝑡𝑢 𝑏𝑎𝑘𝑢

3. Master Production Schedule

Menurut Vincent Gaspersz dalam, Pada dasarnya jadwal produksi

induk (master production schedule) merupakan suatu pernyataan

tentang produk akhir (termasuk parts pengganti dan suku cadang) dari

suatu perusahaan industri manufaktur yang merencanakan

memproduksi output berkaitan dengan kuantitas dan periode waktu.

Aktivitas Master Production Scheduling (MPS) dalam pada dasarnya


33

berkaitan dengan bagaimana menyusun dan memperbaharui jadwal

produksi induk (master production schedule)..

Penjadwalan produksi induk dalam pada dasarnya berkaitan dengan

aktivitas melakukan empat fungsi utama berikut :

1. Menyediakan atau memberikan input utama kepada sistem

perencanaan kebutuhan material dan kapasitas (material and

capacity planning/M&CRP).

2. Menjadwalkan pesanan-pesanan produksi dan pembelian

(production and purchase ordes) untuk item-item MPS.

3. Memberikan landasan untuk penentuan kebutuhan sumber

daya dan kapasitas.

4. Memberikan basis untuk pembuatan janji tentang

penyerahan produk (delivery promises) kepada pelanggan.

4. Rough Cut Capacity Planning

Rough Cut Capacity Planning (RCCP) merupakan metode yang

dapat menentukan kecukupan jumlah sumber daya yang akan

direncanakan untuk membuat MPS. RCCP digunakan untuk

memvalidasi JIP yang telah ditetapkan. Adapun informasi-informasi

yang dapat diperoleh dari RCCP yaitu seperti kebutuhan tenaga kerja,

kapasitas Gudang, mesin dan peralatan, kapasitas pemasok material

serta sumber daya keuangan (Gasperz , 2005).


34

e. Menentukan Routhing Sheet


𝑠𝑒𝑡𝑢𝑝 𝑡𝑖𝑚𝑒𝑠
{ }
𝑙𝑜𝑡 𝑠𝑖𝑧𝑒
Standar Hours = 𝑅𝑢𝑛 𝑡𝑖𝑚𝑒 + 3600

f. Menentukan RCCP = MasterSchedule x Standart Hours c.

Menentukan kapasitas yang dibutuhkan Menjumlahkan total RCCP

dari aetiap Work Station (WS). d. Menentukan kapasitas yang

tersedia Kapasitas tersedia = Jam kerja x Hari kerja x Tenaga kerja


35

E.Flowchart Penelitian

Mulai

Menentukan Topik Studi Pustaka


Material Requirement Planning 2 Jurnal dan 2 E-book

Permasalahan
1. Belum diketahuinya total waktu siklus dan waktu keseluruhan
pada CRP.
2. Belum diketahuinya jumlah kapasitas mesin yang dibutuhkan
pada periode Januari sampai Desember 2022.
3. Belum diketahuinya jumlah kebutuhan aktual dengan Reated
Capacity pada produksi mainan kereta api. .

Pengumpulan Data
Pengumpulan data didapat dari data proses
perangkaian komponen mainan kereta api dari kayu
pada periode Januari sampai Desember 2022.

Mengolah Data
1. Mengolah data dengan metode Forecasting, Rough Cut Capacity
Planning, dan Capacity Requirement Planning
2. Menyimpulkan data dengan membuat grafik Load actual capacity
dan material Requirement Planning

Menganalisa Data
Penelitian ini bertujuan untuk menganalisa pembuatan mainan kereta
api kayu dengan penggunaan metode Forecasting, Rough Cut Capacity
Planning, Capacity Requirement Planning dan akhiri dengan table Material
Requirement Planning dan pembuatan grafik Load Actual Capacity, Master
Planning Schedule

Kesimpulan

Selesai
Gambar 3.1
Flowchart Penelitian
Sumber: Penelitian
BAB IV
PENGOLAHAN DAN ANALISIS DATA

A. Pengumpulan Data
1. Bill Of Material Chart

Produk Mainan Kereta Api Kayu Level 0

Level 1
Rakitan Mainan Kemasan
Level 2

Bagian Atas Bagian Bawah Bagian Belakang

Level 3

Roda Badan As Roda Roda Samping Pasak Atap


Cerobong Badan Pasak As Roda Badan Atas
Samping Bawah Belakang Kanan
Lokomotif Depan
Kiri

Level 4

Pengunci Pengunci Roda Roda Pengunci Pengunci Perangkai Roda Roda


Perangkai Roda Roda
Roda Roda Belakang Depan Roda Belakang Depan
Roda Kiri Kiri Belakang Depan
Belakang Depan Kiri Kanan Kanan Kanan
Kiri Kiri Kanan Kanan

Gambar 4.1
Bill Of Material Chart
Sumber : Pengumpulan data

36
37

2 Bill Of Material Table


a. Direct Material Mainan Kereta Api Kayu
Tabel 4.1
Direct Material Mainan Kereta Api Kayu

Produk Awal (mm) Ukuran Produk Jadi (mm)


No Gambar Part Nama Part Q/U
P L T D P L T D

Badan
1 1 142 52 22 - 110 50 24 -
Bawah

As Roda
2 1 179 - - 8 64 - - 6
Depan

As Roda
3 1 179 - - 8 64 - - 6
Belakang

Roda
4 Depan 1 - 72 - 32 - 15 - 39
Kanan

Roda
5 1 - 72 - 32 - 15 - 39
Depan Kiri

Roda
6 Belakang 1 - 72 - 32 - 15 - 39
Kanan

Roda
7 Belakang 1 - 72 - 32 - 15 - 39
Kiri

Perangkai
8 Roda 1 50 3 12 - 48 3 7 6
Kanan

Perangkai
9 1 50 3 12 - 48 3 7 6
Roda Kiri
38

Pengunci
Roda
10 1 - 3 12 10 - 3 10 6
Depan
Kanan

Pengunci
11 Roda 1 - 3 12 10 - 3 10 6
Depan Kiri

Pengunci
Roda
12 1 - 3 12 10 - 3 10 6
Belakang
Kanan
Pengunci
Roda
13 1 - 3 12 10 - 3 10 6
Belakang
Kiri

Badan
14 1 75 51 51 - 56 55 55 -
Atas

15 Atap 1 100 56 10 - 61 60 14 -

Pasak
16 1 40 - - 8 26 - - 12
Belakang

Badan
17 1 100 - - 40 66 - - 40
Lokomotif

18 Cerobong 1 - 4 20 8 - 4 19 8

Pasak
19 1 40 - - 8 26 - - 8
Depan

Sumber : Pengamatan data

b. Indirect Material Mainan Kereta Api Kayu


Tabel 4.2
Indirect Material Mainan Kereta Api Kayu

Produk Awal(mm) Ukuran Produk Jadi(mm)


No Gambar Part Nama Part Q/U
P L T D P L T D

Cat Kayu
1 Warna 1 - - - - - - 200 150
Abu
39

Cat Kayu
2 Warna 1 - - - - - - 201 150
Pink

Cat Kayu
3 Warna 1 - - - - - - 202 150
Biru

4 Mika 1 - - - - 150 125 90 -

5 Kardus 1 - - - - 300 250 90 -

Sumber : Pengamatan data


40

B. Pengolahan Data
1 Forecasting
Tabel 4.3
Data Forecasting
PART LEVEL Q/U
Produk Mainan Kereta Api Kayu 0 1
Rakitan Mainan 1 1
Kemasan 1 1
Bagian Atas 2 1
Bagian Bawah 2 1
Bagian Belakang 2 1
Cerobong 3 1
Badan Lokomotif 3 1
Pasak Belakang 3 1
Roda Samping Kiri 3 1
As Roda Depan 3 1
Badan Bawah 3 1
As Roda Belakang 3 1
Roda Samping Kanan 3 1
Pasak Depan 3 1
Badan Atas 3 1
Atap 3 1
Pengunci Roda Belakang Kiri 4 1
Pengunci Roda Depan Kiri 4 1
Perangkai Roda Kiri 4 1
Roda Depan Kiri 4 1
Roda Belakang Kiri 4 1
Pengunci Roda Belakang Kanan 4 1
Pengunci Roda Depan Kanan 4 1
Perangkai Roda Kanan 4 1
Roda Depan Kanan 4 1
Roda Belakang Kanan 4 1
Sumber : Pengolahan data

Metode Weighted Moving Average (WMA)


Tabel 4.4
Data PT Se Wooden Toys
Permintaan
Tahun Bulan
Peramalan
Januari 1592
Februari 1583

2021
41

Maret 1599
April 1582
Mei 1592
Juni 1592
2021
Juli 1607
Agustus 1585
September 1588
Mei 1592
November 1582
Desember 1585
Januari 1599
Februari 1584
Maret 1609
April 1584
Mei 1598
Juni 1587
2022
Juli 1602
Agustus 1596
September 1592
Mei 1583
November 1607
Desember 1605
Sumber : Pengolahan data

Gambar 4.2
Grafik Peramalan Forecasting dengan aplikasi POMQM
Sumber : Pengolahan data
B. Pengolahan Data
2 Waktu Operasi Unit for Capacity Requirement Planning (CRP )
Keterangan Waktu Dalam Hitungan Detik
a. Pembuatan Komponen Badan Bawah
Tabel 4.5
Waktu Operasi Pembuatan Komponen Badan Bawah
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O-1 0.0 6 7 8 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O-2 5.0 5 6 7
Driling Ø 8 mm Pelubangan O-3 3.0 3 4 5
Driling Ø 6 mm Pelubangan O-4 3.0 3 4 5
Pneudrem Sender Penghalusan O-5 4.0 4 5 6
Spray Gun Pewarnaan O-6 4.0 7 8 9
Oven Dryer Pengeringan O-7 3.0 5 6 7
Kerja Bangku Pemeriksaan Pemeriksaan I-1 0.0 4 5 6
Total 37 46 53
Sumber : Pengolahan Data

b. Komponen As Roda Depan


Tabel 4.6
Waktu Operasi Pembuatan Komponen As Roda Depan
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O-8 0.0 6 8 10 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O-9 4.0 5 6 8
Pneudrem Sender Penghalusan O - 10 8.0 4 5 7
Spray Gun Pewarnaan O - 11 3.0 7 9 12
Oven Dryer Pengeringan O - 12 6.0 5 6 8
Kerja Bangku Pemeriksaan Pemeriksaan I-2 0.0 4 5 7
Total 31 40 52
Sumber : Pengolahan Data

42
c Komponen As Roda Belakang
Tabel 4.7
Waktu Operasi Pembuatan Komponen As Roda Belakang
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 13 0.0 6 2 2 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 14 4.0 5 2 2
Pneudrem Sender Penghalusan O - 15 3.0 4 1 2
Spray Gun Pewarnaan O - 16 6.0 7 2 3
Oven Dryer Pengeringan O - 17 3.0 5 2 2
Kerja Bangku Pemeriksaan Pemeriksaan I-3 0.0 4 1 2
Total 31 9 12
Sumber : Pengolahan Data

d. Komponen Roda Depan Kanan


Tabel 4.8
Waktu Operasi Pembuatan Komponen Roda Depan Kanan
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 18 0.0 5 6 7 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 19 4.0 6 7 8
Driling Ø 6 mm Pelubangan O - 20 3.0 3 3 4
Pneudrem Sender Penghalusan O - 21 8.0 4 5 5
Spray Gun Pewarnaan O - 22 7.0 7 8 9
Oven Dryer Pengeringan O - 23 5.0 5 6 7
Kerja Bangku Pemeriksaan Pemeriksaan I-3 0.0 4 5 5
Total 34 39 46
Sumber : Pengolahan Data

43
e. Komponen Roda Depan Kiri
Tabel 4.9
Waktu Operasi Pembuatan Komponen Roda Depan Kiri
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 18 0.0 5 7 9 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 19 4.0 6 8 11
Driling Ø 6 mm Pelubangan O - 20 8.0 3 4 6
Pneudrem Sender Penghalusan O - 21 7.0 4 5 8
Spray Gun Pewarnaan O - 22 6.0 7 10 13
Oven Dryer Pengeringan O - 23 7.0 5 7 9
Kerja Bangku Pemeriksaan Pemeriksaan I-4 0.0 4 5 8
Total 34 47 64
Sumber : Pengolahan Data

f. Komponen Roda Belakang Kanan


Tabel 4.10
Waktu Operasi Pembuatan Komponen Roda Belakang Kanan
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 50 0.0 5 5 6 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 51 4.0 6 7 7
Driling Ø 6 mm Pelubangan O - 52 8.0 3 3 4
Pneudrem Sender Penghalusan O - 53 9.0 4 4 5
Spray Gun Pewarnaan O - 54 6.0 7 8 8
Oven Dryer Pengeringan O - 55 5.0 5 5 6
Kerja Bangku Pemeriksaan Pemeriksaan I - 11 0.0 4 4 5
Total 34 37 40
Sumber : Pengolahan Data

44
g. Komponen Roda Belakang Kiri
Tabel 4.11
Waktu Operasi Pembuatan Komponen Roda Belakang Kiri
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 24 0.0 5 6 6 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 25 4.0 6 7 8
Driling Ø 6 mm Pelubangan O - 26 3.0 3 3 4
Pneudrem Sender Penghalusan O - 27 8.0 4 4 5
Spray Gun Pewarnaan O - 28 6.0 7 8 9
Oven Dryer Pengeringan O - 29 5.0 5 6 6
Kerja Bangku Pemeriksaan Pemeriksaan I-5 0.0 4 4 5
Total 34 38 43
Sumber : Pengolahan Data

i. Komponen Perangkai Roda Kanan


Tabel 4.12
Waktu Operasi Pembuatan Komponen Perangkai Roda Kanan
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 50 0.0 6 8 10 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 51 3.0 4 5 7
Driling Ø 8 mm Pelubangan O - 52 8.0 3 4 5
Driling Ø 6 mm Pelubangan O - 53 6.0 4 5 7
Pneudrem Sender Penghalusan O - 54 6.0 3 4 5
Spray Gun Pewarnaan O - 55 9.0 7 9 12
Oven Dryer Pengeringan O - 56 8.0 5 6 8
Kerja Bangku Pemeriksaan Pemeriksaan I - 10 0.0 4 5 7
Total 36 46 60
Sumber : Pengolahan Data

45
f. Komponen Perangkai Roda Kiri
Tabel 4.13
Waktu Operasi Pembuatan Komponen Perangkai Roda Kiri
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 30 0.0 6 8 10 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 31 4.0 4 5 7
Driling Ø 8 mm Pelubangan O - 32 2.0 3 4 5
Driling Ø 6 mm Pelubangan O - 33 6.0 4 5 7
Pneudrem Sender Penghalusan O - 34 6.0 3 4 5
Spray Gun Pewarnaan O - 35 9.0 7 9 12
Oven Dryer Pengeringan O - 36 8.0 5 7 8
Kerja Bangku Pemeriksaan Pemeriksaan I-6 0.0 4 5 7
Total 36 47 61
Sumber : Pengolahan Data

l. Komponen Pengunci Roda Depan Kanan


Tabel 4.14
Waktu Operasi Pembuatan Komponen pengunci Roda depan Kanan
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 69 0.00 5 7 9 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 70 4.00 5 7 9
Bubut Pembubutan O - 71 2.00 4 5 7
Pneudrem Sender Penghalusan O - 72 6.00 4 5 7
Spray Gun Pewarnaan O - 73 6.00 7 9 13
Oven Dryer Pengeringan O - 74 5.00 5 7 9
Kerja Bangku Pemeriksaan Pemeriksaan I - 13 0.00 4 5 7
Total 34 46 61
Sumber : Pengolahan Data

46
k. Komponen Pengunci Roda Depan Kiri
Tabel 4.15
Waktu Operasi Pembuatan Komponen Pengunci Roda Depan Kiri
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 37 0.0 5 6 8 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 38 4.0 5 6 8
Bubut Pembubutan O - 39 8.0 4 5 6
Pneudrem Sender Penghalusan O - 40 3.0 4 5 6
Spray Gun Pewarnaan O - 41 6.0 7 9 11
Oven Dryer Pengeringan O - 42 5.0 5 6 8
Kerja Bangku Pemeriksaan Pemeriksaan I-7 0.0 4 5 6
Total 34 42 51
Sumber : Pengolahan Data

l. Komponen Pengunci Roda Belakang Kanan


Tabel 4.16
Waktu Operasi Pembuatan Komponen Pengunci Roda Belakang Kanan
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 56 0.0 5 6 7 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 57 4.0 5 6 7
Bubut Pembubutan O - 58 4.0 4 5 6
Pneudrem Sender Penghalusan O - 59 3.0 4 5 6
Spray Gun Pewarnaan O - 60 6.0 7 8 10
Oven Dryer Pengeringan O - 61 5.0 5 6 7
Kerja Bangku Pemeriksaan Pemeriksaan I - 11 0.0 4 5 6
Total 34 40 47
Sumber : Pengolahan Data

47
m. Komponen Pengunci Roda Belakang Kiri
Tabel 4.17
Waktu Operasi Pembuatan Komponen Pengunci Roda Belakang Kiri
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 43 0.0 5 6 7 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 44 4.0 5 6 7
Bubut Pembubutan O - 45 8.0 4 5 5
Pneudrem Sender Penghalusan O - 46 2.0 4 5 5
Spray Gun Pewarnaan O - 47 6.0 7 8 9
Oven Dryer Pengeringan O - 48 3.0 5 6 7
Kerja Bangku Pemeriksaan Pemeriksaan I-8 0.0 4 5 5
Total 34 39 46
Sumber : Pengolahan Data

n. Komponen Badan Atas


Tabel 4.18
Waktu Operasi Pembuatan Komponen Badan Atas
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 93 0.0 5 6 7 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 94 4.0 5 6 7
Driling Ø 6 mm Pelubangan O - 95 8.0 3 4 4
Pneudrem Sender Penghalusan O - 96 3.0 4 5 6
Spray Gun Pewarnaan O - 97 3.0 7 8 10
Oven Dryer Pengeringan O - 98 5.0 5 6 7
Kerja Bangku Pemeriksaan Pemeriksaan I - 19 0.0 4 5 6
Total 33 39 47
Sumber : Pengolahan Data

48
o. Komponen Atap
Tabel 4.19
Waktu Operasi Pembuatan Komponen Atap
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 111 0.0 5 6 8 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 112 4.0 5 6 8
Pneudrem Sender Penghalusan O - 113 5.0 4 5 6
Spray Gun Pewarnaan O - 114 6.0 7 9 11
Oven Dryer Pengeringan O - 115 4.0 5 6 8
Kerja Bangku Pemeriksaan Pemeriksaan I - 23 0.0 5 6 8
Total 31 38 47
Sumber : Pengolahan Data

p. Komponen Pasak Belakang


Tabel 4.20
Tabel 4.20 Waktu Operasi Pembuatan Komponen Pasak Belakang
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 100 0.0 6 7 8 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 101 6.0 4 5 5
Pneudrem Sender Penghalusan O - 102 2.0 5 6 7
Spray Gun Pewarnaan O - 103 5.0 7 8 9
Oven Dryer Pengeringan O - 104 4.0 5 6 7
Kerja Bangku Pemeriksaan Pemeriksaan I - 21 0.0 4 5 5
Total 31 36 41
Sumber : Pengolahan Data

49
q Komponen Badan Lokomotif
Tabel 4.21
Waktu Operasi Pembuatan Komponen Lokomotif
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 105 0.0 11 13 14 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 106 4.0 5 6 6
Driling Ø 6 mm Pelubangan O - 107 5.0 3 3 4
Pneudrem Sender Penghalusan O - 108 3.0 4 5 5
Spray Gun Pewarnaan O - 109 6.0 7 8 9
Oven Dryer Pengeringan O - 110 5.0 5 6 6
Kerja Bangku Pemeriksaan Pemeriksaan I - 22 0.0 4 5 5
Total 39 44 51
Sumber : Pengolahan Data

r. Komponen Cerobong
Tabel 4.22
Waktu Operasi Pembuatan Komponen Cerobong
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 106 0.0 6 8 10 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 107 4.0 5 6 8
Pneudrem Sender Penghalusan O - 108 8.0 3 4 5
Spray Gun Pewarnaan O - 109 2.0 7 9 11
Oven Dryer Pengeringan O - 110 4.0 5 6 8
Kerja Bangku Pemeriksaan Pemeriksaan I - 22 0.0 4 5 6
Total 30 38 48
Sumber : Pengolahan Data

50
s. Komponen Pasak Depan
Tabel 4.23
Waktu Operasi Pembuatan Komponen Pasak Depan
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Alat Ukur Pengukuran O - 83 0.0 6 8 11 WB = WN x (1 + Kelonggaran)
Scrill Saw Pemotongan O - 84 4.0 4 5 7
Pneudrem Sender Penghalusan O - 85 8.0 5 7 9
Spray Gun Pewarnaan O - 86 6.0 7 9 12
Oven Dryer Pengeringan O - 87 6.0 5 7 9
Kerja Bangku Pemeriksaan Pemeriksaan I - 17 0.0 4 5 7
Total 31 41 55
Sumber : Pengolahan Data

t. Sub-Sub Assembling 1
Tabel 4.24
Waktu Operasi Pembuatan Komponen Sub-Sub Assembling 1
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Kerja Bangku Perakitan Perakitan O - 49 0.0 5 7 8 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I-9 0.0 5 7 8
Total 10 13 17
Sumber : Pengolahan Data

51
u. Sub-Sub Assembling 2
Tabel 4.25
Waktu Operasi Pembuatan Komponen Sub-Sub Assembling 2
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Kerja Bangku Perakitan Perakitan O - 81 0.0 5 6 6 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I - 15 0.0 5 6 6
Total 10 11 12
Sumber : Pengolahan Data

v. Sub-Sub Assembling 3
Tabel 4.26
Waktu Operasi Pembuatan Komponen Sub-Sub Assembling 3
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Kerja Bangku Perakitan Perakitan O - 116 0.0 5 6 6 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I - 24 0.0 5 6 6
Total 10 11 12
Sumber : Pengolahan Data

w. Sub Assembling 1
Tabel 4.27
Waktu Operasi Pembuatan Komponen Sub Assembling 1
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Kerja Bangku Perakitan Perakitan O - 117 0.0 5 6 7 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I - 25 0.0 5 6 7
Total 10 12 14
Sumber : Pengolahan Data

52
x. Sub Assembling 2
Tabel 4.28
Waktu Operasi Pembuatan Komponen Sub Assembling 2
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Kerja Bangku Perakitan Perakitan O - 117 0.0 5 6 7 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I - 25 0.0 5 6 7
Total 10 12 15
Sumber : Pengolahan Data

y. Assembling
Tabel 4.29
Waktu Operasi Pembuatan Komponen Assembling (Keseluruhan)
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Kerja Bangku Perakitan Perakitan O - 117 0.0 5 6 7 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I - 25 0.0 5 6 7
Total 10 12 14
Sumber : Pengolahan Data

z. Pengemasan Mika
Tabel 4.30
Waktu Operasi Pembuatan Komponen Pengemasan Mika
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Meja Pengemasan Perakitan O - 120 0.0 3 3 4 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I - 28 0.0 3 3 4
Total 5 6 7
Sumber : Pengolahan Data

53
aa. Pengemasan Kardus
Tabel 4.31
Waktu Operasi Pembuatan Komponen Pengemasan Kardus
Operating Set-up Waktu Waktu Waktu Keterangan :
Mesin Process
Code Mesin Siklus Normal Baku WN = WS x Penyesuaian
Meja Pengemasan Perakitan O - 120 0.0 3 3 4 WB = WN x (1 + Kelonggaran)
Meja Pemeriksaan Pemeriksaan I - 28 0.0 3 3 4
Total 5 6 7
Sumber : Pengolahan Data

Total Waktu Siklus = 89 Detik


Total Waktu Keseluruhan = 708 Detik

54
3 Master Production Schedule (MPS )
Tabel 4.31
Master Production Schedule (MPS)
Perminta Perminta
Periode Lost MPS
an an
Januari 1599 1607 225 1832
Februari 1584 1592 223 1815
Maret 1609 1617 226 1843
April 1584 1592 223 1815
Mei 1598 1606 225 1831
Juni 1587 1595 223 1818
Juli 1602 1610 225 1835
Agustus 1596 1604 225 1829
September 1592 1600 224 1824
Oktober 1583 1591 223 1814
November 1607 1615 226 1841
Desember 1605 1613 226 1839
Sumber : Pengolahan Data

Keterangan :
LM (Lost Material ) = 12%
LP (Lost Produk ) = 2%
Total = 14%

55
4 Rough Cut Capacity Planning (RCCP )
a. Perhitungan RCCP
1) Komponen Badan Bawah
Tabel 4.32
RCCP Komponen Badan Bawah
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Drilling Spray Oven
m aan
Ukur Saw Ø6mm Ø8mm Gun dryer
Sender
Januari 15063 12957 8743 8743 10850 17170 12957 10850
Februari 14922 12835 8661 8661 10748 17009 12835 10748
Maret 15158 13038 8798 8798 10918 17278 13038 10918
April 14922 12835 8661 8661 10748 17009 12835 10748
Mei 15054 12949 8738 8738 10843 17159 12949 10843
Juni 14950 12859 8677 8677 10768 17041 12859 10768
Juli 15092 12981 8760 8760 10870 17202 12981 10870
Agustus 15035 12932 8727 8727 10830 17138 12932 10830
September 14997 12900 8705 8705 10802 17095 12900 10802
Oktober 14913 12827 8656 8656 10741 16998 12827 10741
November 15139 13021 8787 8787 10904 17256 13021 10904
Desember 15120 13005 8776 8776 10891 17235 13005 10891
Sumber : Pengolahan Data

56
2) Komponen As Roda Depan
Tabel 4.33
RCCP Komponen As Roda Depan
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
m aan
Ukur Saw Gun dryer
Sender
Januari 18292 15243 12194 21340 15243 12194
Februari 18120 15100 12080 21140 15100 12080
Maret 18406 15338 12271 21474 15338 12271
April 18120 15100 12080 21140 15100 12080
Mei 18280 15233 12187 21327 15233 12187
Juni 18154 15129 12103 21180 15129 12103
Juli 18326 15272 12217 21380 15272 12217
Agustus 18257 15214 12171 21300 15214 12171
September 18211 15176 12141 21247 15176 12141
Oktober 18109 15090 12072 21127 15090 12072
November 18383 15319 12255 21447 15319 12255
Desember 18360 15300 12240 21420 15300 12240
Sumber : Pengolahan Data

57
3) Komponen As Roda Belakang
Tabel 4.34
RCCP Komponen As Roda Belakang
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
m aan
Ukur Saw Gun dryer
Sender
Januari 4287 3572 2858 5001 3572 2858
Februari 4247 3539 2831 4954 3539 2831
Maret 4314 3595 2876 5033 3595 2876
April 4247 3539 2831 4954 3539 2831
Mei 4284 3570 2856 4998 3570 2856
Juni 4255 3546 2836 4964 3546 2836
Juli 4295 3579 2863 5011 3579 2863
Agustus 4279 3566 2853 4992 3566 2853
September 4268 3557 2845 4979 3557 2845
Oktober 4244 3537 2829 4951 3537 2829
November 4308 3590 2872 5026 3590 2872
Desember 4303 3586 2869 5020 3586 2869
Sumber : Pengolahan Data

58
4) Komponen Roda Depan Kanan
Tabel 4.35
RCCP Komponen Roda Depan Kanan
Mesin
Periode Pneudre
Alat Scrill Drilling Spray Oven Pemeriks
m
Ukur Saw Ø6mm Gun dryer aan
Sender
Januari 12326 14791 7395 9860 17256 12326 9860
Februari 12210 14652 7326 9768 17094 12210 9768
Maret 12403 14883 7442 9922 17364 12403 9922
April 12210 14652 7326 9768 17094 12210 9768
Mei 12318 14781 7391 9854 17245 12318 9854
Juni 12233 14680 7340 9786 17126 12233 9786
Juli 12349 14818 7409 9879 17288 12349 9879
Agustus 12302 14763 7381 9842 17223 12302 9842
September 12272 14726 7363 9817 17180 12272 9817
Oktober 12202 14643 7321 9762 17083 12202 9762
November 12387 14865 7432 9910 17342 12387 9910
Desember 12372 14846 7423 9897 17320 12372 9897
Sumber : Pengolahan Data

59
5) Komponen Roda Depan Kiri
Tabel 4.36
RCCP Komponen Roda Depan Kiri
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Spray Oven
m aan
Ukur Saw Ø6mm Gun dryer
Sender
Januari 17192 20631 10315 13754 24069 17192 13754
Februari 17031 20437 10219 13625 23843 17031 13625
Maret 17300 20760 10380 13840 24220 17300 13840
April 17031 20437 10219 13625 23843 17031 13625
Mei 17181 20618 10309 13745 24054 17181 13745
Juni 17063 20476 10238 13651 23888 17063 13651
Juli 17224 20669 10335 13780 24114 17224 13780
Agustus 17160 20592 10296 13728 24024 17160 13728
September 17117 20540 10270 13694 23964 17117 13694
Oktober 17020 20424 10212 13616 23828 17020 13616
November 17278 20734 10367 13823 24189 17278 13823
Desember 17257 20708 10354 13805 24159 17257 13805
Sumber : Pengolahan Data

60
6) Komponen Roda Belakang Kanan
Tabel 4.37
RCCP Komponen Roda Belakang Kanan
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Spray Oven
m aan
Ukur Saw Ø6mm Gun dryer
Sender
Januari 10883 13059 6530 8706 15236 10883 8706
Februari 10781 12937 6468 8625 15093 10781 8625
Maret 10951 13141 6571 8761 15331 10951 8761
April 10781 12937 6468 8625 15093 10781 8625
Mei 10876 13051 6526 8701 15226 10876 8701
Juni 10801 12961 6481 8641 15122 10801 8641
Juli 10903 13084 6542 8723 15265 10903 8723
Agustus 10862 13035 6517 8690 15207 10862 8690
September 10835 13002 6501 8668 15169 10835 8668
Oktober 10774 12929 6464 8619 15084 10774 8619
November 10937 13125 6562 8750 15312 10937 8750
Desember 10924 13108 6554 8739 15293 10924 8739
Sumber : Pengolahan Data

61
7) Komponen Roda Belakang Kiri
Tabel 4.38
RCCP Komponen Roda Belakang Kiri
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Spray Oven
m aan
Ukur Saw Ø6mm Gun dryer
Sender
Januari 11490 13788 6894 9192 16086 11490 9192
Februari 11382 13659 6829 9106 15935 11382 9106
Maret 11562 13874 6937 9250 16187 11562 9250
April 11382 13659 6829 9106 15935 11382 9106
Mei 11483 13780 6890 9186 16076 11483 9186
Juni 11404 13685 6842 9123 15965 11404 9123
Juli 11512 13814 6907 9209 16116 11512 9209
Agustus 11469 13762 6881 9175 16056 11469 9175
September 11440 13728 6864 9152 16016 11440 9152
Oktober 11375 13650 6825 9100 15925 11375 9100
November 11548 13857 6929 9238 16167 11548 9238
Desember 11533 13840 6920 9227 16147 11533 9227
Sumber : Pengolahan Data

62
8) Komponen Perangkai Roda Kanan
Tabel 4.39
RCCP Komponen Perangkai Roda Kanan
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Drilling Spray Oven
m aan
Ukur Saw Ø6mm Ø8mm Gun dryer
Sender
Januari 18292 12194 12194 9146 9146 21340 15243 12194
Februari 18120 12080 12080 9060 9060 21140 15100 12080
Maret 18406 12271 12271 9203 9203 21474 15338 12271
April 18120 12080 12080 9060 9060 21140 15100 12080
Mei 18280 12187 12187 9140 9140 21327 15233 12187
Juni 18154 12103 12103 9077 9077 21180 15129 12103
Juli 18326 12217 12217 9163 9163 21380 15272 12217
Agustus 18257 12171 12171 9129 9129 21300 15214 12171
September 18211 12141 12141 9106 9106 21247 15176 12141
Oktober 18109 12072 12072 9054 9054 21127 15090 12072
November 18383 12255 12255 9192 9192 21447 15319 12255
Desember 18360 12240 12240 9180 9180 21420 15300 12240
Sumber : Pengolahan Data

63
9) Komponen Perangkai Roda Kiri
Tabel 4.40
RCCP Komponen Perangkai Roda Kiri
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Drilling Spray Oven
m aan
Ukur Saw Ø6mm Ø8mm Gun dryer
Sender
Januari 18576 12384 12384 9288 9288 21672 15480 12384
Februari 18402 12268 12268 9201 9201 21469 15335 12268
Maret 18692 12462 12462 9346 9346 21808 15577 12462
April 18402 12268 12268 9201 9201 21469 15335 12268
Mei 18565 12376 12376 9282 9282 21659 15471 12376
Juni 18437 12291 12291 9218 9218 21510 15364 12291
Juli 18611 12407 12407 9306 9306 21713 15509 12407
Agustus 18541 12361 12361 9271 9271 21632 15451 12361
September 18495 12330 12330 9247 9247 21577 15412 12330
Oktober 18390 12260 12260 9195 9195 21455 15325 12260
November 18669 12446 12446 9335 9335 21781 15558 12446
Desember 18646 12431 12431 9323 9323 21754 15538 12431
Sumber : Pengolahan Data

64
10) Komponen Pengunci Roda Depan Kanan
Tabel 4.41
RCCP Komponen Pengunci Roda Depan Kanan
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
Bubut m aan
Ukur Saw Gun dryer
Sender
Januari 16447 16447 13158 13158 23026 16447 13158
Februari 16293 16293 13035 13035 22810 16293 13035
Maret 16550 16550 13240 13240 23170 16550 13240
April 16293 16293 13035 13035 22810 16293 13035
Mei 16437 16437 13150 13150 23012 16437 13150
Juni 16324 16324 13059 13059 22854 16324 13059
Juli 16478 16478 13183 13183 23070 16478 13183
Agustus 16417 16417 13133 13133 22983 16417 13133
September 16375 16375 13100 13100 22926 16375 13100
Oktober 16283 16283 13026 13026 22796 16283 13026
November 16530 16530 13224 13224 23142 16530 13224
Desember 16509 16509 13207 13207 23113 16509 13207
Sumber : Pengolahan Data

65
11) Komponen Pengunci Roda Depan Kiri
Tabel 4.42
RCCP Komponen Pengunci Roda Depan Kiri
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
Bubut m aan
Ukur Saw Gun dryer
Sender
Januari 13858 13858 11086 11086 19401 13858 11086
Februari 13728 13728 10982 10982 19219 13728 10982
Maret 13945 13945 11156 11156 19522 13945 11156
April 13728 13728 10982 10982 19219 13728 10982
Mei 13849 13849 11079 11079 19389 13849 11079
Juni 13754 13754 11003 11003 19256 13754 11003
Juli 13884 13884 11107 11107 19438 13884 11107
Agustus 13832 13832 11066 11066 19365 13832 11066
September 13797 13797 11038 11038 19316 13797 11038
Oktober 13719 13719 10975 10975 19207 13719 10975
November 13927 13927 11142 11142 19498 13927 11142
Desember 13910 13910 11128 11128 19474 13910 11128
Sumber : Pengolahan Data

66
12) Komponen Pengunci Roda Belakang Kanan
Tabel 4.43
RCCP Komponen Pengunci Roda Belakang Kanan
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
Bubut m aan
Ukur Saw Gun dryer
Sender
Januari 12754 12754 10203 10203 17856 12754 10203
Februari 12635 12635 10108 10108 17688 12635 10108
Maret 12834 12834 10267 10267 17968 12834 10267
April 12635 12635 10108 10108 17688 12635 10108
Mei 12746 12746 10197 10197 17845 12746 10197
Juni 12658 12658 10127 10127 17722 12658 10127
Juli 12778 12778 10223 10223 17889 12778 10223
Agustus 12730 12730 10184 10184 17822 12730 10184
September 12698 12698 10159 10159 17778 12698 10159
Oktober 12627 12627 10101 10101 17677 12627 10101
November 12818 12818 10254 10254 17945 12818 10254
Desember 12802 12802 10242 10242 17923 12802 10242
Sumber : Pengolahan Data

67
13) Komponen Pengunci Roda Belakang Kiri
Tabel 4.44
RCCP Komponen Pengunci Roda Belakang Kiri
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
Bubut m aan
Ukur Saw Gun dryer
Sender
Januari 12326 12326 9860 9860 17256 12326 9860
Februari 12210 12210 9768 9768 17094 12210 9768
Maret 12403 12403 9922 9922 17364 12403 9922
April 12210 12210 9768 9768 17094 12210 9768
Mei 12318 12318 9854 9854 17245 12318 9854
Juni 12233 12233 9786 9786 17126 12233 9786
Juli 12349 12349 9879 9879 17288 12349 9879
Agustus 12302 12302 9842 9842 17223 12302 9842
September 12272 12272 9817 9817 17180 12272 9817
Oktober 12202 12202 9762 9762 17083 12202 9762
November 12387 12387 9910 9910 17342 12387 9910
Desember 12372 12372 9897 9897 17320 12372 9897
Sumber : Pengolahan Data

68
14) Komponen Badan Atas
Tabel 4.45
RCCP Komponen Badan Atas
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Spray Oven
m aan
Ukur Saw Ø6mm Gun dryer
Sender
Januari 12971 12971 7783 10377 18160 12971 10377
Februari 12850 12850 7710 10280 17989 12850 10280
Maret 13052 13052 7831 10442 18273 13052 10442
April 12850 12850 7710 10280 17989 12850 10280
Mei 12963 12963 7778 10371 18148 12963 10371
Juni 12874 12874 7724 10299 18024 12874 10299
Juli 12996 12996 7797 10397 18194 12996 10397
Agustus 12947 12947 7768 10358 18126 12947 10358
September 12915 12915 7749 10332 18080 12915 10332
Oktober 12841 12841 7705 10273 17978 12841 10273
November 13036 13036 7822 10429 18251 13036 10429
Desember 13020 13020 7812 10416 18228 13020 10416
Sumber : Pengolahan Data

69
15) Komponen Atap
Tabel 4.46
RCCP Komponen Atap
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
m aan
Ukur Saw Gun dryer
Sender
Januari 13858 13858 11086 19401 13858 13858
Februari 13728 13728 10982 19219 13728 13728
Maret 13945 13945 11156 19522 13945 13945
April 13728 13728 10982 19219 13728 13728
Mei 13849 13849 11079 19389 13849 13849
Juni 13754 13754 11003 19256 13754 13754
Juli 13884 13884 11107 19438 13884 13884
Agustus 13832 13832 11066 19365 13832 13832
September 13797 13797 11038 19316 13797 13797
Oktober 13719 13719 10975 19207 13719 13719
November 13927 13927 11142 19498 13927 13927
Desember 13910 13910 11128 19474 13910 13910
Sumber : Pengolahan Data

70
16) Komponen Pasak Belakang
Tabel 4.47
RCCP Komponen Pasak Belakang
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
m aan
Ukur Saw Gun dryer
Sender
Januari 14537 9691 12114 16960 12114 9691
Februari 14400 9600 12000 16800 12000 9600
Maret 14628 9752 12190 17066 12190 9752
April 14400 9600 12000 16800 12000 9600
Mei 14528 9685 12106 16949 12106 9685
Juni 14428 9618 12023 16832 12023 9618
Juli 14564 9709 12137 16991 12137 9709
Agustus 14509 9673 12091 16928 12091 9673
September 14473 9649 12061 16885 12061 9649
Oktober 14391 9594 11993 16790 11993 9594
November 14609 9740 12175 17044 12175 9740
Desember 14591 9728 12159 17023 12159 9728
Sumber : Pengolahan Data

71
17) Komponen Badan Lokomotif
Tabel 4.48
RCCP Komponen Badan Lokomotif
Mesin
Pneudre Pemeriks
Periode Alat Scrill Drilling Spray Oven
m aan
Ukur Saw Ø6mm Gun dryer
Sender
Januari 26189 11904 7143 9523 16666 11904 9523
Februari 25943 11792 7075 9434 16509 11792 9434
Maret 26353 11979 7187 9583 16770 11979 9583
April 25943 11792 7075 9434 16509 11792 9434
Mei 26173 11897 7138 9517 16655 11897 9517
Juni 25993 11815 7089 9452 16541 11815 9452
Juli 26238 11927 7156 9541 16697 11927 9541
Agustus 26140 11882 7129 9505 16635 11882 9505
September 26075 11852 7111 9482 16593 11852 9482
Oktober 25927 11785 7071 9428 16499 11785 9428
November 26320 11964 7178 9571 16749 11964 9571
Desember 26287 11949 7169 9559 16728 11949 9559
Sumber : Pengolahan Data

72
18) Komponen Cerobong
Tabel 4.49
RCCP Komponen Cerobong
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
m aan
Ukur Saw Gun dryer
Sender
Januari 17729 14774 8864 20684 14774 11819
Februari 17562 14635 8781 20490 14635 11708
Maret 17840 14866 8920 20813 14866 11893
April 17562 14635 8781 20490 14635 11708
Mei 17718 14765 8859 20671 14765 11812
Juni 17596 14663 8798 20528 14663 11730
Juli 17762 14802 8881 20722 14802 11841
Agustus 17695 14746 8848 20645 14746 11797
September 17651 14709 8826 20593 14709 11767
Oktober 17551 14626 8776 20477 14626 11701
November 17817 14848 8909 20787 14848 11878
Desember 17795 14829 8898 20761 14829 11864
Sumber : Pengolahan Data

73
19) Komponen Pasak Depan
Tabel 4.50
RCCP Komponen Pasak Depan
Mesin
Pneudre Pemeriks
Periode Alat Scrill Spray Oven
m aan
Ukur Saw Gun dryer
Sender
Januari 19443 12962 16203 22684 16203 12962
Februari 19261 12841 16051 22471 16051 12841
Maret 19565 13043 16304 22826 16304 13043
April 19261 12841 16051 22471 16051 12841
Mei 19431 12954 16193 22670 16193 12954
Juni 19298 12865 16081 22514 16081 12865
Juli 19480 12987 16233 22727 16233 12987
Agustus 19407 12938 16172 22641 16172 12938
September 19358 12906 16132 22585 16132 12906
Oktober 19249 12833 16041 22457 16041 12833
November 19541 13027 16284 22798 16284 13027
Desember 19516 13011 16264 22769 16264 13011
Sumber : Pengolahan Data

74
20) Sub-Sub Assembling 1
Tabel 4.51
RCCP Sub-Sub Assembling 1
Kerja Meja
Periode Bangku Pemeriks
Perakitan aan
Januari 15480 15480
Februari 15335 15335
Maret 15577 15577
April 15335 15335
Mei 15471 15471
Juni 15364 15364
Juli 15509 15509
Agustus 15451 15451
September 15412 15412
Oktober 15325 15325
November 15558 15558
Desember 15538 15538
Sumber : Pengolahan Data

75
21) Sub-Sub Assembling 2
Tabel 4.52
RCCP Sub-Sub Assembling 2
Kerja Meja
Periode Bangku Pemeriks
Perakitan aan
Januari 11286 11286
Februari 11180 11180
Maret 11356 11356
April 11180 11180
Mei 11279 11279
Juni 11201 11201
Juli 11307 11307
Agustus 11265 11265
September 11236 11236
Oktober 11173 11173
November 11342 11342
Desember 11328 11328
Sumber : Pengolahan Data

76
22) Sub Assembling 1
Tabel 4.53
RCCP Sub Assembling 1
Kerja Meja
Periode Bangku Pemeriks
Perakitan aan
Januari 12539 12539
Februari 12421 12421
Maret 12617 12617
April 12421 12421
Mei 12531 12531
Juni 12445 12445
Juli 12562 12562
Agustus 12515 12515
September 12484 12484
Oktober 12413 12413
November 12602 12602
Desember 12586 12586
Sumber : Pengolahan Data

77
23) Sub Assembling 2
Tabel 4.54
RCCP Sub Assembling 2
Kerja Meja
Periode Bangku Pemeriks
Perakitan aan
Januari 13634 13634
Februari 13506 13506
Maret 13719 13719
April 13506 13506
Mei 13625 13625
Juni 13531 13531
Juli 13659 13659
Agustus 13608 13608
September 13574 13574
Oktober 13497 13497
November 13702 13702
Desember 13685 13685
Sumber : Pengolahan Data

78
24) Assembling
Tabel 4.55
RCCP Assembling
Kerja Meja
Periode Bangku Pemeriks
Perakitan aan
Januari 12971 12971
Februari 12850 12850
Maret 13052 13052
April 12850 12850
Mei 12963 12963
Juni 12874 12874
Juli 12996 12996
Agustus 12947 12947
September 12915 12915
Oktober 12841 12841
November 13036 13036
Desember 13020 13020
Sumber : Pengolahan Data

79
25) Pengemasan Mika
Tabel 4.56
RCCP Pengemasan Mika
Kerja Meja
Periode Bangku Pemeriks
Perakitan aan
Januari 6817 6817
Februari 6753 6753
Maret 6859 6859
April 6753 6753
Mei 6813 6813
Juni 6766 6766
Juli 6830 6830
Agustus 6804 6804
September 6787 6787
Oktober 6749 6749
November 6851 6851
Desember 6842 6842
Sumber : Pengolahan Data

80
26) Pengemasan Kardus
Tabel 4.57
RCCP Pengemasan Kardus
Kerja Meja
Periode Bangku Pemeriks
Perakitan aan
Januari 6817 6817
Februari 6753 6753
Maret 6859 6859
April 6753 6753
Mei 6813 6813
Juni 6766 6766
Juli 6830 6830
Agustus 6804 6804
September 6787 6787
Oktober 6749 6749
November 6851 6851
Desember 6842 6842
Sumber : Pengolahan Data

81
b. Resume Jumlah Kapasitas yang Dibutuhkan
Tabel 4.58
Resume Jumlah Kapasitas yang Dibutuhkan
Mesin Kerja Bangku
Alat Jig Saw Drilling Drilling Bubut Pneudre Spray Oven Pemer Sub- Sub- Sub Sub Sub Peraki Penge
Periode Ukur Ø6mm Ø8mm m Gun Dryer iksaan Sub Sub Assem Assem Assem tan masan
Sender Assem Assem bling bling bling
bling bling 1 2 3
Januari 80 69 22 8 12 55 98 70 79 4 3 3 4 0 4 4
Februari 79 69 22 7 12 55 97 69 78 4 3 3 4 0 4 4
Maret 80 70 22 8 12 55 98 70 79 4 3 4 4 0 4 4
April 79 69 20 7 12 55 97 69 78 4 3 3 4 0 4 4
Mei 80 69 22 8 12 55 98 70 79 4 3 3 4 0 4 4
Juni 79 69 22 7 12 55 97 69 78 4 3 3 4 0 4 4
Juli 80 70 22 8 12 55 98 70 79 4 3 3 4 0 4 4
Agustus 79 69 22 8 12 55 97 70 79 4 3 3 4 0 4 4
September 79 69 22 8 12 55 97 70 79 4 3 3 4 0 4 4
Oktober 79 69 22 7 12 55 97 69 78 4 3 3 4 0 4 4
November 80 70 22 8 12 55 98 70 79 4 3 4 4 0 4 4
Desember 80 70 22 8 12 55 98 70 79 4 3 3 4 0 4 4
Jumlah Mesin 953 832 262 90 147 660 1168 837 945 51 38 42 45 0 43 45
Sumber : Pengolahan Data

82
c. Kapasitas Perusahaan

Keterangan :

Jam Kerja = 8 Jam/Shift


Shift = 3 Shift/Hari
Hari Kerja = 20 Hari/Bulan

Jumlah Alat Ukur = 953 Unit


Jumlah Mesin Jig Saw = 832 Unit
Jumlah Mesin Drilling Ø6mm = 262 Unit
Jumlah Mesin Drilling Ø8mm = 90 Unit
Jumlah Mesin Bubut = 147 Unit
Jumlah Mesin Pneudrem Sender = 660 Unit
Jumlah Mesin Spray Gun = 1168 Unit
Jumlah Mesin Oven Dryer = 837 Unit
Jumlah Kerja Bangku Pemeriksaan = 945 Unit
Sub- Sub Assembling 1 = 51 Unit
Sub- Sub Assembling 2 = 38 Unit
Sub Assembling 1 = 42 Unit
Sub Assembling 2 = 45 Unit
Perakitan = 43 Unit
Pengemasan = 45 Unit

83
Kapasitas yang tersedia :

Kapasitas Alat Ukur = 457417 Jam/Bulan


Kapasitas Mesin Jig Saw = 399388 Jam/Bulan
Kapasitas Mesin Drilling Ø6mm = 125789 Jam/Bulan
Kapasitas Mesin Drilling Ø8mm = 43388 Jam/Bulan
Kapasitas Mesin Bubut = 70738 Jam/Bulan
Kapasitas Mesin Pneudrem Sender = 316625 Jam/Bulan
Kapasitas Mesin Spray Gun = 560792 Jam/Bulan
Kapasitas Mesin Oven Dryer = 401671 Jam/Bulan
Kapasitas Kerja Bangku Pemeriksaan = 453526 Jam/Bulan
Sub- Sub Assembling 1 = 24714 Jam/Bulan
Sub- Sub Assembling 2 = 18018 Jam/Bulan
Sub Assembling 1 = 20018 Jam/Bulan
Sub Assembling 2 = 21766 Jam/Bulan
Assembling = 20709 Jam/Bulan
Pengemasan = 21766 Jam/Bulan

84
Gross Requirement = MPS / 4 Khusus pada level 0), level 1-4 dari planned order release level sebelumnya

Projected Hand = ON HAND - Safety Stock (sisanya 0)

Net Requirement = GR - Project Hand

Planned Order Receipt = Net Requirement

Planned Order Release = GR - Project Hand (pada minggu berikutnya)

Penentuan Safety Stock dengan menggunakan Metode Konservatif

(sum(MPS januari-desember)) / (hari kerja perbulan x =12) unit per


Pemakaian Rata-Rata (U) = 91
hari
Lead Time Rata-Rata (L) = 1 minggu = 7 hari
unit per
Pemakaian Terbesar (U max) =((max(MPS januari-desember)) / hari kerja per bulan= 92
hari
Lead Time Terlama (L max) = 1 minggu = 7 hari

ROP - (UxL)
ROP = (U max) x (L max) Safety Stock =

x 645 - (91 x 7)
= 7 =
92
=
= 645 5

5 Material Requirement Planning (MRP )


a. Perhitungan MRP
1) Nama Komponen = Produk Mainan Safety Stock = 5
Level = 0 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.59
Perhitungan MRP Komponen Produk Mainan Level 0
Periode
Level 0 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454
Planned Order Receipt 342 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454
Planned Order Release 342 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
Sumber : Pengolahan Data

85
2) Nama Komponen = Rakitan Mainan Safety Stock = 5
Level = 1 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.60
Perhitungan MRP Komponen Rakitan Mainan Level 1
Periode
Level 1 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 342 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
Planned Order Receipt 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
Planned Order Release 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0
Sumber : Pengolahan Data

3) Nama Komponen = Kemasan Safety Stock = 5


Level = 1 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.61
Perhitungan MRP Komponen Kemasan Level 1
Periode
Level 1 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 342 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
Planned Order Receipt 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
Planned Order Release 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0
Sumber : Pengolahan Data

4) Nama Komponen = Bagian Atas Safety Stock = 5


Level = 2 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.62
Perhitungan MRP Komponen Bagian Atas Level 2
Periode
Level 2 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 226 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Planned Order Receipt 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Planned Order Release 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Sumber : Pengolahan Data

86
5) Nama Komponen = Bagian Bawah Safety Stock = 5
Level = 2 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.63
Perhitungan MRP Komponen Bagian Bawah Level 2
Periode
Level 2 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 226 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Planned Order Receipt 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Planned Order Release 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Sumber : Pengolahan Data

6) Nama Komponen = Bagian Belakang Safety Stock = 5


Level = 2 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.64
Perhitungan MRP Komponen Bagian Belakang Level 2
Periode
Level 2 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 226 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Planned Order Receipt 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
Planned Order Release 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Sumber : Pengolahan Data

7) Nama Komponen = Cerobong Safety Stock = 5


Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.65
Perhitungan MRP Komponen Cerobong Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

87
8) Nama Komponen = Badan Lokomotif Safety Stock = 5
Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.66
Perhitungan MRP Komponen Badan Lokomotif Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

9) Nama Komponen = Pasak Belakang Safety Stock = 5


Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.67
Perhitungan MRP Komponen Badan Pasak Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

10) Nama Komponen = Roda Samping Kiri Safety Stock = 5


Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.68
Perhitungan MRP Komponen Roda Samping Kiri Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

88
11) Nama Komponen = As Roda Depan Safety Stock = 5
Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.69
Perhitungan MRP Komponen As Roda Depan Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

12) Nama Komponen = Badan Bawah Safety Stock = 5


Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.70
Perhitungan MRP Komponen Badan Bawah Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

13) Nama Komponen = As Roda Belakang Safety Stock = 5


Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.71
Perhitungan MRP Komponen As Roda Belakang Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

89
14) Nama Komponen = Roda Samping Kanan Safety Stock = 5
Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.72
Perhitungan MRP Komponen Roda Samping Kanan Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

15) Nama Komponen = Pasak Depan Safety Stock = 5


Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.73
Perhitungan MRP Komponen Pasak Depan Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

16) Nama Komponen = Badan Atas Safety Stock = 5


Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.74
Perhitungan MRP Komponen Badan Atas Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

90
17) Nama Komponen = Atap Safety Stock = 5
Level = 3 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.75
Perhitungan MRP Komponen Atap Level 3
Periode
Level 3 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Receipt 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
Planned Order Release 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

18) Nama Komponen = Pengunci Roda Belakang Kiri Safety Stock = 5


Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.76
Perhitungan MRP Komponen Pengunci Roda Belakang Kiri Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

19) Nama Komponen = Pengunci Roda Depan Kiri Safety Stock = 5


Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.77
Perhitungan MRP Komponen Pengunci Roda Depan Kiri Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

91
20) Nama Komponen = Perangkai Roda Kiri Safety Stock = 5
Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.78
Perhitungan MRP Komponen Perangkai Roda Kiri Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

21) Nama Komponen = Roda Depan Kiri Safety Stock = 5


Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.79
Perhitungan MRP Komponen Roda Depan Kiri Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

22) Nama Komponen = Roda Belakang Kiri Safety Stock = 5


Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.80
Perhitungan MRP Komponen Roda Belakang Kiri Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

92
23) Nama Komponen = Pengunci Roda Belakang Kanan Safety Stock = 5
Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.81
Perhitungan MRP Komponen Pengunci Roda Belakang Kanan Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

24) Nama Komponen = Pengunci Roda Depan Kanan Safety Stock = 5


Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.82
Perhitungan MRP Komponen Pengunci Roda Depan Kanan Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

25) Nama Komponen = Perangkai Roda Kanan Safety Stock = 5


Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.83
Perhitungan MRP Komponen Perangkai Roda Kanan Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

93
26) Nama Komponen = Roda Depan Kanan Safety Stock = 5
Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.84
Perhitungan MRP Komponen Roda Depan Kanan Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

27) Nama Komponen = Roda Belakang Kanan Safety Stock = 5


Level = 4 Lead Time = 1 Minggu
On Hand = 121 Lot Size Method = Lot Per Lot
Tabel 4.85
Perhitungan MRP Komponen Roda Belakang Kanan Level 4
Periode
Level 4 Desember Januari Febuari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Gross Requirement 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Projected Hand 116 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Net Requirement 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Receipt 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Planned Order Release 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0 0
Sumber : Pengolahan Data

94
b. Resume Planned Order Receipt
Tabel 4.86
Resume Planned Order Receipt MRP
Periode
Level Komponen Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
0 Produk Mainan Kereta Api Kayu 342 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454
1 Rakitan Mainan 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
1 Kemasan 226 458 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0
2 Bagian Atas 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
2 Bagian Bawah 0 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
2 Bagian Belakang 0 110 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0
3 Cerobong 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Badan Lokomotif 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Pasak Belakang 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Roda Samping Kiri 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 As Roda Depan 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Badan Bawah 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 As Roda Belakang 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Roda Samping Kanan 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Pasak Depan 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Badan Atas 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
3 Atap 0 458 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0
4 Pengunci Roda Belakang Kiri 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Pengunci Roda Depan Kiri 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Perangkai Roda Kiri 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Roda Depan Kiri 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Roda Belakang Kiri 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Pengunci Roda Belakang Kanan 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Pengunci Roda Depan Kanan 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Perangkai Roda Kanan 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Roda Depan Kanan 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
4 Roda Belakang Kanan 342 458 454 454 454 454 461 461 461 461 454 454 454 454 0 0 0 0 0
Sumber : Pengolahan Data

95
Capacity Requirement Planning (CRP)
a. Perhitungan CRP
1) Nama Komponen = Badan Bawah Jumlah Komponen/Produk = 1
Tabel 4.87
Capacity Requirement Planning (CRP) Badan Bawah
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 0 904 3766 3766 3731 3731 3731 3731 3789 3789 3789 3789 3731 3731 3731 3731 0 0 0
Scrill Saw 25 25 803 3264 3264 3234 3234 3234 3234 3284 3284 3284 3284 3234 3234 3234 3234 25 25 25
Driling Ø 8 mm 15 15 540 2201 2201 2180 2180 2180 2180 2214 2214 2214 2214 2180 2180 2180 2180 15 15 15
Driling Ø 6 mm 15 15 540 2201 2201 2180 2180 2180 2180 2214 2214 2214 2214 2180 2180 2180 2180 15 15 15
Pneudrem Sender 20 20 671 2732 2732 2707 2707 2707 2707 2749 2749 2749 2749 2707 2707 2707 2707 20 20 20
Spray Gun 20 20 1051 4313 4313 4272 4272 4272 4272 4339 4339 4339 4339 4272 4272 4272 4272 20 20 20
Oven Dryer 15 15 793 3254 3254 3224 3224 3224 3224 3274 3274 3274 3274 3224 3224 3224 3224 15 15 15
Kerja Bangku Pemeriksaan 0 0 651 2712 2712 2687 2687 2687 2687 2729 2729 2729 2729 2687 2687 2687 2687 0 0 0
Sumber : Pengolahan Data

2) Nama Komponen = As Roda Depan Jumlah Komponen/Produk = 1


Tabel 4.88
Capacity Requirement Planning (CRP) As Roda Depan
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 0 4573 4573 4530 4530 4530 4530 4601 4601 4601 4601 4530 4530 4530 4530 0 0 0 0
Scrill Saw 20 20 3831 3831 3795 3795 3795 3795 3855 3855 3855 3855 3795 3795 3795 3795 20 20 20 20
Pneudrem Sender 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40
Spray Gun 15 15 5350 5350 5300 5300 5300 5300 5383 5383 5383 5383 5300 5300 5300 5300 15 15 15 15
Oven Dryer 30 30 3841 3841 3805 3805 3805 3805 3865 3865 3865 3865 3805 3805 3805 3805 30 30 30 30
Kerja Bangku Pemeriksaan 0 0 3049 3049 3020 3020 3020 3020 3068 3068 3068 3068 3020 3020 3020 3020 0 0 0 0
Sumber : Pengolahan Data

3) Nama Komponen = As Roda Belakang Jumlah Komponen/Produk = 1


Tabel 4.89
Capacity Requirement Planning (CRP) As Roda Belakang
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 0 1072 1072 1062 1062 1062 1062 1078 1078 1078 1078 1062 1062 1062 1062 0 0 0 0
Scrill Saw 20 20 913 913 905 905 905 905 919 919 919 919 905 905 905 905 20 20 20 20
Pneudrem Sender 15 15 729 729 723 723 723 723 734 734 734 734 723 723 723 723 15 15 15 15
Spray Gun 30 30 923 923 915 915 915 915 929 929 929 929 915 915 915 915 30 30 30 30
Oven Dryer 0 0 714 714 708 708 708 708 719 719 719 719 708 708 708 708 0 0 0 0
Kerja Bangku Pemeriksaan 0 0 5537 5537 5485 5485 5485 5485 5572 5572 5572 5572 5485 5485 5485 5485 0 0 0 0
Sumber : Pengolahan Data

4) Nama Komponen = Roda Depan Kanan Jumlah Komponen/Produk = 1


Tabel 4.90
Capacity Requirement Planning (CRP) Roda Depan Kanan
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 2301 3081 3052 3052 3052 3052 3101 3101 3101 3101 3052 3052 3052 3052 0 0 0 0 0
Scrill Saw 20 2781 3718 3683 3683 3683 3683 3741 3741 3741 3741 3683 3683 3683 3683 20 20 20 20 20
Driling Ø 6 mm 15 1396 1864 1846 1846 1846 1846 1875 1875 1875 1875 1846 1846 1846 1846 15 15 15 15 15
Pneudrem Sender 40 1881 2505 2482 2482 2482 2482 2521 2521 2521 2521 2482 2482 2482 2482 40 40 40 40 40
Spray Gun 35 3256 4349 4308 4308 4308 4308 4376 4376 4376 4376 4308 4308 4308 4308 35 35 35 35 35
Oven Dryer 25 2326 3106 3077 3077 3077 3077 3126 3126 3126 3126 3077 3077 3077 3077 25 25 25 25 25
Kerja Bangku Pemeriksaan 0 1841 2465 2442 2442 2442 2442 2481 2481 2481 2481 2442 2442 2442 2442 0 0 0 0 0
Sumber : Pengolahan Data

5) Nama Komponen = Roda Depan Kiri Jumlah Komponen/Produk = 1


Tabel 4.91
Capacity Requirement Planning (CRP) Roda Depan Kiri
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 3209 4298 4258 4258 4258 4258 4325 4325 4325 4325 4258 4258 4258 4258 0 0 0 0 0
Scrill Saw 20 3871 5178 5129 5129 5129 5129 5210 5210 5210 5210 5129 5129 5129 5129 20 20 20 20 20
Driling Ø 6 mm 40 1966 2619 2595 2595 2595 2595 2635 2635 2635 2635 2595 2595 2595 2595 40 40 40 40 40
Pneudrem Sender 35 2603 3473 3441 3441 3441 3441 3495 3495 3495 3495 3441 3441 3441 3441 35 35 35 35 35
Spray Gun 30 4523 6047 5991 5991 5991 5991 6085 6085 6085 6085 5991 5991 5991 5991 30 30 30 30 30
Oven Dryer 35 3244 4333 4293 4293 4293 4293 4360 4360 4360 4360 4293 4293 4293 4293 35 35 35 35 35
Kerja Bangku Pemeriksaan 0 2568 3438 3406 3406 3406 3406 3460 3460 3460 3460 3406 3406 3406 3406 0 0 0 0 0
Sumber : Pengolahan Data

96
6) Nama Komponen = Roda Belakang Kanan Jumlah Komponen/Produk = 1
Tabel 4.92
Capacity Requirement Planning (CRP) Roda Belakang Kanan
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 2032 2721 2695 2695 2695 2695 2738 2738 2738 2738 2695 2695 2695 2695 0 0 0 0 0
Scrill Saw 20 2458 3285 3254 3254 3254 3254 3305 3305 3305 3305 3254 3254 3254 3254 20 20 20 20 20
Driling Ø 6 mm 40 1259 1672 1657 1657 1657 1657 1683 1683 1683 1683 1657 1657 1657 1657 40 40 40 40 40
Pneudrem Sender 45 1670 2222 2201 2201 2201 2201 2235 2235 2235 2235 2201 2201 2201 2201 45 45 45 45 45
Spray Gun 30 2874 3839 3803 3803 3803 3803 3863 3863 3863 3863 3803 3803 3803 3803 30 30 30 30 30
Oven Dryer 25 2057 2746 2720 2720 2720 2720 2763 2763 2763 2763 2720 2720 2720 2720 25 25 25 25 25
Kerja Bangku Pemeriksaan 0 1625 2177 2156 2156 2156 2156 2190 2190 2190 2190 2156 2156 2156 2156 0 0 0 0 0
Sumber : Pengolahan Data

7) Nama Komponen = Roda Belakang Kiri Jumlah Komponen/Produk = 1


Tabel 4.93
Capacity Requirement Planning (CRP) Roda Belakang Kiri
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 2145 2873 2846 2846 2846 2846 2891 2891 2891 2891 2846 2846 2846 2846 0 0 0 0 0
Scrill Saw 20 2594 3467 3435 3435 3435 3435 3489 3489 3489 3489 3435 3435 3435 3435 20 20 20 20 20
Driling Ø 6 mm 15 1302 1739 1722 1722 1722 1722 1749 1749 1749 1749 1722 1722 1722 1722 15 15 15 15 15
Pneudrem Sender 40 1756 2338 2316 2316 2316 2316 2352 2352 2352 2352 2316 2316 2316 2316 40 40 40 40 40
Spray Gun 30 3033 4052 4014 4014 4014 4014 4077 4077 4077 4077 4014 4014 4014 4014 30 30 30 30 30
Oven Dryer 25 2170 2898 2871 2871 2871 2871 2916 2916 2916 2916 2871 2871 2871 2871 25 25 25 25 25
Kerja Bangku Pemeriksaan 0 1716 2298 2276 2276 2276 2276 2312 2312 2312 2312 2276 2276 2276 2276 0 0 0 0 0
Sumber : Pengolahan Data

8) Nama Komponen = Perangkai Roda Kanan Jumlah Komponen/Produk = 1


Tabel 4.94
Capacity Requirement Planning (CRP) Perangkai Roda Kanan
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 3415 4573 4530 4530 4530 4530 4601 4601 4601 4601 4530 4530 4530 4530 0 0 0 0 0
Scrill Saw 15 2291 3064 3035 3035 3035 3035 3083 3083 3083 3083 3035 3035 3035 3035 15 15 15 15 15
Driling Ø 8 mm 40 1747 2326 2305 2305 2305 2305 2341 2341 2341 2341 2305 2305 2305 2305 40 40 40 40 40
Driling Ø 6 mm 30 2306 3079 3050 3050 3050 3050 3098 3098 3098 3098 3050 3050 3050 3050 30 30 30 30 30
Pneudrem Sender 30 1737 2316 2295 2295 2295 2295 2331 2331 2331 2331 2295 2295 2295 2295 30 30 30 30 30
Spray Gun 45 4029 5380 5330 5330 5330 5330 5413 5413 5413 5413 5330 5330 5330 5330 45 45 45 45 45
Oven Dryer 40 2886 3851 3815 3815 3815 3815 3875 3875 3875 3875 3815 3815 3815 3815 40 40 40 40 40
Kerja Bangku Pemeriksaan 0 2276 3049 3020 3020 3020 3020 3068 3068 3068 3068 3020 3020 3020 3020 0 0 0 0 0
Sumber : Pengolahan Data

9) Nama Komponen = Perangkai Roda Kiri Jumlah Komponen/Produk = 1


Tabel 4.95
Capacity Requirement Planning (CRP) Perangkai Roda Kiri
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 3519 4695 4651 4651 4651 4651 4724 4724 4724 4724 4651 4651 4651 4651 51 51 51 51 51
Scrill Saw 20 2346 3130 3101 3101 3101 3101 3149 3149 3149 3149 3101 3101 3101 3101 34 34 34 34 34
Driling Ø 8 mm 10 1759 2347 2326 2326 2326 2326 2362 2362 2362 2362 2326 2326 2326 2326 25 25 25 25 25
Driling Ø 6 mm 30 2346 3130 3101 3101 3101 3101 3149 3149 3149 3149 3101 3101 3101 3101 34 34 34 34 34
Pneudrem Sender 30 1759 2347 2326 2326 2326 2326 2362 2362 2362 2362 2326 2326 2326 2326 25 25 25 25 25
Spray Gun 45 4105 5477 5426 5426 5426 5426 5511 5511 5511 5511 5426 5426 5426 5426 59 59 59 59 59
Oven Dryer 40 2932 3912 3876 3876 3876 3876 3936 3936 3936 3936 3876 3876 3876 3876 42 42 42 42 42
Kerja Bangku Pemeriksaan 0 2346 3130 3101 3101 3101 3101 3149 3149 3149 3149 3101 3101 3101 3101 34 34 34 34 34
Sumber : Pengolahan Data

10) Nama Komponen = Pengunci Roda Depan Kanan Jumlah Komponen/Produk = 1


Tabel 4.96
Capacity Requirement Planning (CRP) Pengunci Roda Depan Kanan
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 3070 4112 4073 4073 4073 4073 4138 4138 4138 4138 4073 4073 4073 4073 0 0 0 0 0
Scrill Saw 20 25 34 45 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Bubut 10 2466 3299 3269 3269 3269 3269 3320 3320 3320 3320 3269 3269 3269 3269 10 10 10 10 10
Pneudrem Sender 30 2486 3319 3289 3289 3289 3289 3340 3340 3340 3340 3289 3289 3289 3289 30 30 30 30 30
Spray Gun 30 4329 5787 5733 5733 5733 5733 5823 5823 5823 5823 5733 5733 5733 5733 30 30 30 30 30
Oven Dryer 25 3095 4137 4098 4098 4098 4098 4163 4163 4163 4163 4098 4098 4098 4098 25 25 25 25 25
Kerja Bangku Pemeriksaan 0 2456 3289 3259 3259 3259 3259 3310 3310 3310 3310 3259 3259 3259 3259 0 0 0 0 0
Sumber : Pengolahan Data

97
11) Nama Komponen = Pengunci Roda Depan Kiri Jumlah Komponen/Produk = 1
Tabel 4.97
Capacity Requirement Planning (CRP) Pengunci Roda Depan Kiri
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 2587 3464 3432 3432 3432 3432 3486 3486 3486 3486 3432 3432 3432 3432 0 0 0 0 0
Scrill Saw 20 2607 3484 3452 3452 3452 3452 3506 3506 3506 3506 3452 3452 3452 3452 20 20 20 20 20
Bubut 40 2110 2812 2786 2786 2786 2786 2829 2829 2829 2829 2786 2786 2786 2786 40 40 40 40 40
Pneudrem Sender 15 2085 2787 2761 2761 2761 2761 2804 2804 2804 2804 2761 2761 2761 2761 15 15 15 15 15
Spray Gun 30 3652 4880 4835 4835 4835 4835 4911 4911 4911 4911 4835 4835 4835 4835 30 30 30 30 30
Oven Dryer 25 2612 3489 3457 3457 3457 3457 3511 3511 3511 3511 3457 3457 3457 3457 25 25 25 25 25
Kerja Bangku Pemeriksaan 0 2070 2772 2746 2746 2746 2746 2789 2789 2789 2789 2746 2746 2746 2746 0 0 0 0 0
Sumber : Pengolahan Data

12) Nama Komponen = Pengunci Roda Belakang Kanan Jumlah Komponen/Produk = 1


Tabel 4.98
Capacity Requirement Planning (CRP) Pengunci Roda Belakang Kanan
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 2381 3189 3159 3159 3159 3159 3208 3208 3208 3208 3159 3159 3159 3159 0 0 0 0 0
Scrill Saw 20 2401 3209 3179 3179 3179 3179 3228 3228 3228 3228 3179 3179 3179 3179 20 20 20 20 20
Bubut 20 1925 2571 2547 2547 2547 2547 2587 2587 2587 2587 2547 2547 2547 2547 20 20 20 20 20
Pneudrem Sender 15 1920 2566 2542 2542 2542 2542 2582 2582 2582 2582 2542 2542 2542 2542 15 15 15 15 15
Spray Gun 30 3363 4494 4452 4452 4452 4452 4522 4522 4522 4522 4452 4452 4452 4452 30 30 30 30 30
Oven Dryer 25 2406 3214 3184 3184 3184 3184 3233 3233 3233 3233 3184 3184 3184 3184 25 25 25 25 25
Kerja Bangku Pemeriksaan 0 1905 2551 2527 2527 2527 2527 2567 2567 2567 2567 2527 2527 2527 2527 0 0 0 0 0
Sumber : Pengolahan Data

13) Nama Komponen = Pengunci Roda Belakang Kiri Jumlah Komponen/Produk = 1


Tabel 4.99
Capacity Requirement Planning (CRP) Roda Belakang Kiri
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 2301 3081 3052 3052 3052 3052 3101 3101 3101 3101 3052 3052 3052 3052 0 0 0 0 0
Scrill Saw 20 2321 3101 3072 3072 3072 3072 3121 3121 3121 3121 3072 3072 3072 3072 20 20 20 20 20
Bubut 40 1881 2505 2482 2482 2482 2482 2521 2521 2521 2521 2482 2482 2482 2482 40 40 40 40 40
Pneudrem Sender 10 1851 2475 2452 2452 2452 2452 2491 2491 2491 2491 2452 2452 2452 2452 10 10 10 10 10
Spray Gun 30 3251 4344 4303 4303 4303 4303 4371 4371 4371 4371 4303 4303 4303 4303 30 30 30 30 30
Oven Dryer 15 2316 3096 3067 3067 3067 3067 3116 3116 3116 3116 3067 3067 3067 3067 15 15 15 15 15
Kerja Bangku Pemeriksaan 0 1841 2465 2442 2442 2442 2442 2481 2481 2481 2481 2442 2442 2442 2442 0 0 0 0 0
Sumber : Pengolahan Data

14) Nama Komponen = Badan Atas Jumlah Komponen/Produk = 1


Tabel 4.100
Capacity Requirement Planning (CRP) Badan Atas
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 0 3243 3243 3212 3212 3212 3212 3263 3263 3263 3263 3212 3212 3212 3212 0 0 0 0
Scrill Saw 20 20 3263 3263 3232 3232 3232 3232 3283 3283 3283 3283 3232 3232 3232 3232 20 20 20 20
Driling Ø 6 mm 40 40 1986 1986 1967 1967 1967 1967 1998 1998 1998 1998 1967 1967 1967 1967 40 40 40 40
Pneudrem Sender 15 15 2609 2609 2585 2585 2585 2585 2625 2625 2625 2625 2585 2585 2585 2585 15 15 15 15
Spray Gun 15 15 4555 4555 4512 4512 4512 4512 4583 4583 4583 4583 4512 4512 4512 4512 15 15 15 15
Oven Dryer 25 25 3268 3268 3237 3237 3237 3237 3288 3288 3288 3288 3237 3237 3237 3237 25 25 25 25
Kerja Bangku Pemeriksaan 0 0 2594 2594 2570 2570 2570 2570 2610 2610 2610 2610 2570 2570 2570 2570 0 0 0 0
Sumber : Pengolahan Data

15) Nama Komponen = Atap Jumlah Komponen/Produk = 1


Tabel 4.101
Capacity Requirement Planning (CRP) Atap
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 0 3464 3464 3432 3432 3432 3432 3486 3486 3486 3486 3432 3432 3432 3432 0 0 0 0
Scrill Saw 20 20 3484 3484 3452 3452 3452 3452 3506 3506 3506 3506 3452 3452 3452 3452 20 20 20 20
Pneudrem Sender 25 25 2797 2797 2771 2771 2771 2771 2814 2814 2814 2814 2771 2771 2771 2771 25 25 25 25
Spray Gun 30 30 4880 4880 4835 4835 4835 4835 4911 4911 4911 4911 4835 4835 4835 4835 30 30 30 30
Oven Dryer 20 20 3484 3484 3452 3452 3452 3452 3506 3506 3506 3506 3452 3452 3452 3452 20 20 20 20
Kerja Bangku Pemeriksaan 0 0 3464 3464 3432 3432 3432 3432 3486 3486 3486 3486 3432 3432 3432 3432 0 0 0 0
Sumber : Pengolahan Data

98
16) Nama Komponen = Pasak Belakang Jumlah Komponen/Produk = 1
Tabel 4.102
Capacity Requirement Planning (CRP) Pasak Belakang
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 0 3634 3634 3600 3600 3600 3600 3657 3657 3657 3657 3600 3600 3600 3600 0 0 0 0
Scrill Saw 30 30 2453 2453 2430 2430 2430 2430 2468 2468 2468 2468 2430 2430 2430 2430 30 30 30 30
Pneudrem Sender 10 10 3038 3038 3010 3010 3010 3010 3057 3057 3057 3057 3010 3010 3010 3010 10 10 10 10
Spray Gun 25 25 4265 4265 4225 4225 4225 4225 4291 4291 4291 4291 4225 4225 4225 4225 25 25 25 25
Oven Dryer 20 20 3048 3048 3020 3020 3020 3020 3067 3067 3067 3067 3020 3020 3020 3020 20 20 20 20
Kerja Bangku Pemeriksaan 0 0 2423 2423 2400 2400 2400 2400 2438 2438 2438 2438 2400 2400 2400 2400 0 0 0 0
Sumber : Pengolahan Data

17) Nama Komponen = Badan Lokomotif Jumlah Komponen/Produk = 1


Tabel 4.103
Capacity Requirement Planning (CRP) Badan Lokomotif
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 2714 3634 3600 3600 3600 3600 3657 3657 3657 3657 3600 3600 3600 3600 0 0 0 0 0
Scrill Saw 20 1839 2453 2430 2430 2430 2430 2468 2468 2468 2468 2430 2430 2430 2430 30 30 30 30 30
Driling Ø 6 mm 25 2271 3038 3010 3010 3010 3010 3057 3057 3057 3057 3010 3010 3010 3010 10 10 10 10 10
Pneudrem Sender 15 3191 4265 4225 4225 4225 4225 4291 4291 4291 4291 4225 4225 4225 4225 25 25 25 25 25
Spray Gun 30 2281 3048 3020 3020 3020 3020 3067 3067 3067 3067 3020 3020 3020 3020 20 20 20 20 20
Oven Dryer 25 1809 2423 2400 2400 2400 2400 2438 2438 2438 2438 2400 2400 2400 2400 0 0 0 0 0
Kerja Bangku Pemeriksaan 0 14021 18777 18600 18600 18600 18600 18894 18894 18894 18894 18600 18600 18600 18600 0 0 0 0 0
Sumber : Pengolahan Data

18) Nama Komponen = Cerobong Jumlah Komponen/Produk = 1


Tabel 4.104
Capacity Requirement Planning (CRP) Cerobong
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 0 4432 4432 4391 4391 4391 4391 4460 4460 4460 4460 4391 4391 4391 4391 0 0 0 0
Scrill Saw 20 20 3713 3713 3679 3679 3679 3679 3737 3737 3737 3737 3679 3679 3679 3679 20 20 20 20
Pneudrem Sender 40 40 2256 2256 2235 2235 2235 2235 2270 2270 2270 2270 2235 2235 2235 2235 40 40 40 40
Spray Gun 10 10 5181 5181 5132 5132 5132 5132 5213 5213 5213 5213 5132 5132 5132 5132 10 10 10 10
Oven Dryer 20 25 32 40 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Kerja Bangku Pemeriksaan 0 20 25 32 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Sumber : Pengolahan Data

19) Nama Komponen = Pasak Depan Jumlah Komponen/Produk = 1


Tabel 4.105
Capacity Requirement Planning (CRP) Pasak Depan
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 3310 4432 4391 4391 4391 4391 4460 4460 4460 4460 4391 4391 4391 4391 0 0 0 0 0
Scrill Saw 20 2778 3713 3679 3679 3679 3679 3737 3737 3737 3737 3679 3679 3679 3679 20 20 20 20 20
Pneudrem Sender 40 1695 2256 2235 2235 2235 2235 2270 2270 2270 2270 2235 2235 2235 2235 40 40 40 40 40
Spray Gun 30 3871 5181 5132 5132 5132 5132 5213 5213 5213 5213 5132 5132 5132 5132 10 10 10 10 10
Oven Dryer 30 20 27 35 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Kerja Bangku Pemeriksaan 0 155 206 274 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Sumber : Pengolahan Data

20) Nama Komponen = Sub-Sub Assembling 1 Jumlah/Komponen = 1


Tabel 4.106
Capacity Requirement Planning (CRP) Sub-Sub Assembling 1
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Meja Assembling 0 0 3870 3870 3834 3834 3834 3834 3894 3894 3894 3894 3834 3834 3834 3834 0 0 0 0
Meja Pemeriksaan 0 0 3870 3870 3834 3834 3834 3834 3894 3894 3894 3894 3834 3834 3834 3834 0 0 0 0
Sumber : Pengolahan Data

21) Nama Komponen = Sub-Sub Assembling 2 Jumlah/Komponen = 1


Tabel 4.107
Capacity Requirement Planning (CRP) Sub-Sub Assembling 2
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Meja Assembling 0 0 2821 2821 2795 2795 2795 2795 2839 2839 2839 2839 2795 2795 2795 2795 0 0 0 0
Meja Pemeriksaan 0 0 2821 2821 2795 2795 2795 2795 2839 2839 2839 2839 2795 2795 2795 2795 0 0 0 0
Sumber : Pengolahan Data

99
22) Nama Komponen = Sub Assembling 1 Jumlah/Komponen = 1
Tabel 4.108
Capacity Requirement Planning (CRP) Sub Assembling 1
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Meja Assembling 0 0 753 3135 3135 3105 3105 3105 3105 3154 3154 3154 3154 3105 3105 3105 3105 0 0 0
Meja Pemeriksaan 0 0 753 3135 3135 3105 3105 3105 3105 3154 3154 3154 3154 3105 3105 3105 3105 0 0 0
Sumber : Pengolahan Data

23) Nama Komponen = Sub Assembling 2 Jumlah/Komponen = 1


Tabel 4.109
Capacity Requirement Planning (CRP) Sub Assembling 2
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Meja Assembling 0 0 819 3408 3408 3376 3376 3376 3376 3430 3430 3430 3430 3376 3376 3376 3376 0 0 0
Meja Pemeriksaan 0 0 819 3408 3408 3376 3376 3376 3376 3430 3430 3430 3430 3376 3376 3376 3376 0 0 0
Sumber : Pengolahan Data

24) Nama Komponen = Assembling Jumlah/Komponen = 1


Tabel 4.110
Capacity Requirement Planning (CRP) Assembling
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Meja Assembling 0 0 0 1600 3243 3243 3243 3212 3212 3212 3212 3263 3263 3263 3263 3212 3212 3212 3212 0
Meja Pemeriksaan 0 0 0 1600 3243 3243 3243 3212 3212 3212 3212 3263 3263 3263 3263 3212 3212 3212 3212 0
Sumber : Pengolahan Data

25) Nama Komponen = Pengemasan Mika Jumlah/Komponen = 1


Tabel 4.111
Capacity Requirement Planning (CRP) Pengemasan Mika
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Meja Assembling 0 0 0 0 1273 1704 1704 1704 1688 1688 1688 1688 1715 1715 1715 1715 1688 1688 1688 1688
Meja Pemeriksaan 0 0 0 0 1273 1704 1704 1704 1688 1688 1688 1688 1715 1715 1715 1715 1688 1688 1688 1688
Sumber : Pengolahan Data

26) Nama Komponen = Pengemasan Kardus Jumlah/Komponen = 1


Tabel 4.112
Capacity Requirement Planning (CRP) Pengemasan Kardus
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Meja Assembling 0 0 0 0 1273 1704 1704 1704 1688 1688 1688 1688 1715 1715 1715 1715 1688 1688 1688 1688
Meja Pemeriksaan 0 0 0 0 1273 1704 1704 1704 1688 1688 1688 1688 1715 1715 1715 1715 1688 1688 1688 1688
Sumber : Pengolahan Data
b. Resume Jumlah Kebutuhan Aktual
Tabel 4.113
Resume Jumlah Kebutuhan Aktual
Periode
Mesin Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Alat Ukur 0 32983 65476 67923 67732 67696 67696 68386 68705 68764 68764 68075 67755 67696 67696 24008 3781 51 51 51
Scrill Saw 390 28468 56295 58415 58206 58176 58176 58763 59037 59088 59088 58500 58226 58176 58176 20966 3603 394 394 394
Driling Ø 6 mm 210 10935 17047 18573 18555 18535 18535 18759 18790 18824 18824 18599 18569 18535 18535 4292 2364 199 199 199
Driling Ø 8 mm 65 3522 5214 6831 6831 6811 6811 6883 6883 6917 6917 6845 6845 6811 6811 2246 2246 80 80 80
Bubut 110 8381 11187 11083 11083 11083 11083 11256 11256 11256 11256 11083 11083 11083 11083 110 110 110 110 110
Pneudrem Sender 510 24798 45011 46767 46661 46636 46636 47144 47321 47363 47363 46855 46678 46636 46636 14421 3202 515 515 515
Spray Gun 540 42713 83083 85815 85580 85540 85540 86423 86814 86882 86882 85998 85607 85540 85540 29571 4776 524 524 524
Oven Dryer 465 28008 52412 54544 54335 54304 54304 54882 55105 55155 55155 54578 54355 54304 54304 17728 3601 392 392 392
Kerja Bangku Pemeriksaan 0 34839 64360 66061 65595 65569 65569 66294 66561 66604 66604 65879 65612 65569 65569 19628 2721 34 34 34
Kerja Bangku Sub Sub
0 0 3870 3870 3834 3834 3834 3834 3894 3894 3894 3894 3834 3834 3834 3834 0 0 0 0
Assembling 1
Kerja Bangku Sub Sub
Assembling 2
0 0 2821 2821 2795 2795 2795 2795 2839 2839 2839 2839 2795 2795 2795 2795 0 0 0 0
Kerja Bangku Sub Assembling 1 0 0 753 3135 3135 3105 3105 3105 3105 3154 3154 3154 3154 3105 3105 3105 3105 0 0 0
Kerja Bangku Sub Assembling 2 0 0 819 3408 3408 3376 3376 3376 3376 3430 3430 3430 3430 3376 3376 3376 3376 0 0 0
Kerja Bangku Assembling 0 0 8263 14835 18960 19762 19762 19731 19804 19906 19906 19957 19906 19803 19803 19753 13071 6589 6589 3376
Kerja Bangku Pengemasan 0 0 0 0 2545 3408 3408 3408 3376 3376 3376 3376 3430 3430 3430 3430 3376 3376 3376 3376

100
7. Perbandingan Kebutuhan Aktual dengan Kapasitas yang Tersedia
a. Alat Ukur
Tabel 4.114
Perbandingan Alat Ukur
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354 114354
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032
Kebutuhan aktual 0 32983 65476 67923 67732 67696 67696 68386 68705 68764 68764 68075 67755 67696 67696 24008 3781 51 51 51
Over/under 0.00 3.06 1.54 1.49 1.49 1.49 1.49 1.48 1.47 1.47 1.47 1.48 1.49 1.49 1.49 4.21 26.72 0.00 0.00 0.00
Sumber : Pengolahan Data

b. Scrill Saw
Tabel 4.115
Perbandingan Scrill Saw
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847 99847
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215 88215
Kebutuhan aktual 390 28468 56295 58415 58206 58176 58176 58763 59037 59088 59088 58500 58226 58176 58176 20966 3603 394 394 394
Over/under 226.19 3.10 1.57 1.51 1.52 1.52 1.52 1.50 1.49 1.49 1.49 1.51 1.52 1.52 1.52 4.21 24.49 0.00 0.00 0.00
Sumber : Pengolahan Data

c. Mesin Drilling Ø6mm


Tabel 4.116
Perbandingan Mesin Drilling Ø6mm
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447 31447
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784 27784
Kebutuhan aktual 210 10935 17047 18573 18555 18535 18535 18759 18790 18824 18824 18599 18569 18535 18535 4292 2364 199 199 199
Over/under 132.30 2.54 1.63 1.50 1.50 1.50 1.50 1.48 1.48 1.48 1.48 1.49 1.50 1.50 1.50 6.47 11.75 0.00 0.00 0.00
Sumber : Pengolahan Data

d. Mesin Drilling Ø8mm


Tabel 4.117
Perbandingan Mesin Drilling Ø8mm
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847 10847
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583 9583
Kebutuhan aktual 65 3522 5214 6831 6831 6811 6811 6883 6883 6917 6917 6845 6845 6811 6811 2246 2246 80 80 80
Over/under 147.44 2.72 1.84 1.40 1.40 1.41 1.41 1.39 1.39 1.39 1.39 1.40 1.40 1.41 1.41 4.27 4.27 0.00 0.00 0.00
Sumber : Pengolahan Data

e. Bubut
Tabel 4.118
Perbandingan Bubut
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684 17684
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624 15624
Kebutuhan aktual 110 8381 11187 11083 11083 11083 11083 11256 11256 11256 11256 11083 11083 11083 11083 110 110 110 110 110
Over/under 142.04 1.86 1.40 1.41 1.41 1.41 1.41 1.39 1.39 1.39 1.39 1.41 1.41 1.41 1.41 142.04 142.04 0.00 0.00 0.00
Sumber : Pengolahan Data

101
f Pneudrem Sender
Tabel 4.119
Perbandingan Pneudrem Sender
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156 79156
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934 69934
Kebutuhan aktual 510 24798 45011 46767 46661 46636 46636 47144 47321 47363 47363 46855 46678 46636 46636 14421 3202 515 515 515
Over/under 137.13 2.82 1.55 1.50 1.50 1.50 1.50 1.48 1.48 1.48 1.48 1.49 1.50 1.50 1.50 4.85 21.84 0.00 0.00 0.00
Sumber : Pengolahan Data

g Spray Gun
Tabel 4.120
Perbandingan Spray Gun
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198 140198
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865
Kebutuhan aktual 540 42713 83083 85815 85580 85540 85540 86423 86814 86882 86882 85998 85607 85540 85540 29571 4776 524 524 524
Over/under 229.38 2.90 1.49 1.44 1.45 1.45 1.45 1.43 1.43 1.43 1.43 1.44 1.45 1.45 1.45 4.19 25.93 0.00 0.00 0.00
Sumber : Pengolahan Data

h Oven Dryer
Tabel 4.121
Perbandingan Oven Dryer
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719
Kebutuhan aktual 465 28008 52412 54544 54335 54304 54304 54882 55105 55155 55155 54578 54355 54304 54304 17728 3601 392 392 392
Over/under 190.79 3.17 1.69 1.63 1.63 1.63 1.63 1.62 1.61 1.61 1.61 1.63 1.63 1.63 1.63 5.00 24.64 0.00 0.00 0.00
Sumber : Pengolahan Data

i. Kerja Bangku
Tabel 4.122
Perbandingan Kerja Bangku
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418 100418
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719 88719
Kebutuhan aktual 0 34839 64360 66061 65595 65569 65569 66294 66561 66604 66604 65879 65612 65569 65569 19628 2721 34 34 34
Over/under 0 2.55 1.38 1.34 1.35 1.35 1.35 1.34 1.33 1.33 1.33 1.35 1.35 1.35 1.35 4.52 32.61 0.00 0.00 0.00
Sumber : Pengolahan Data

j. Kerja Bangku Sub- Sub Assembling 1


Tabel 4.123
Perbandingan Kerja Bangku Sub - Sub Assembling 1
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179 6179
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459 5459
Kebutuhan aktual 0 0 3870 3870 3834 3834 3834 3834 3894 3894 3894 3894 3834 3834 3834 3834 0 0 0 0
Over/under 0 0 1.41 1.41 1.42 1.42 1.42 1.42 1.40 1.40 1.40 1.40 1.42 1.42 1.42 1.42 #DIV/0! 0.00 0.00 0.00
Sumber : Pengolahan Data

102
k. Kerja Bangku Sub- Sub Assembling 2
Tabel 4.124
Perbandingan Kerja Bangku Sub - Sub Assembling 2
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504 4504
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980 3980
Kebutuhan aktual 0 0 2821 2821 2795 2795 2795 2795 2839 2839 2839 2839 2795 2795 2795 2795 0 0 0 0
Over/under 0 0 1.41 1.41 1.42 1.42 1.42 1.42 1.40 1.40 1.40 1.40 1.42 1.42 1.42 1.42 #DIV/0! 0.00 0.00 0.00
Sumber : Pengolahan Data

l. Kerja Bangku Sub Assembling 1


Tabel 4.125
Perbandingan Kerja Bangku Sub Assembling 1
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005 5005
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422 4422
Kebutuhan aktual 0 0 753 3135 3135 3105 3105 3105 3105 3154 3154 3154 3154 3105 3105 3105 3105 0 0 0
Over/under 0 0 5.87 1.41 1.41 1.42 1.42 1.42 1.42 1.40 1.40 1.40 1.40 1.42 1.42 1.42 1.42 0.00 0.00 0.00
Sumber : Pengolahan Data

m. Kerja Bangku Sub Assembling 2


Tabel 4.126
Perbandingan Kerja Bangku Sub Assembling 2
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808
Kebutuhan aktual 0 0 819 3408 3408 3376 3376 3376 3376 3430 3430 3430 3430 3376 3376 3376 3376 0 0 0
Over/under 0 0 5.87 1.41 1.41 1.42 1.42 1.42 1.42 1.40 1.40 1.40 1.40 1.42 1.42 1.42 1.42 0.00 0.00 0.00
Sumber : Pengolahan Data

n. Kerja Bangku Sub Assembling


Tabel 4.127
Perbandingan Kerja Bangku Assembling
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177 5177
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574 4574
Kebutuhan aktual 0 0 8263 14835 18960 19762 19762 19731 19804 19906 19906 19957 19906 19803 19803 19753 13071 6589 6589 3376
Over/under 0 0 0.55 0.31 0.24 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.35 0.00 0.00 0.00
Sumber : Pengolahan Data

o. Kerja Bangku Pengemasan


Tabel 4.128
Perbandingan Kerja Bangku Pengemasan
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Waktu tersedia 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441 5441
Tingkat Utilitas 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93% 93%
Tingkat efisiensi 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
Rated capacity 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808 4808
Kebutuhan aktual 0 0 0 0 2545 3408 3408 3408 3376 3376 3376 3376 3430 3430 3430 3430 3376 3376 3376 3376
Over/under 0 0 0 0 1.89 1.41 1.41 1.41 1.42 1.42 1.42 1.42 1.40 1.40 1.40 1.40 1.42 0.00 0.00 0.00
Sumber : Pengolahan Data

103
104

Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity )


a. Alat Ukur
Tabel 4.129
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) alat ukur
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 32982.8 65475.7 67923.4 67731.8 67696.5 67696.5 68386 68705.3 68764.1 68764.1 68074.6 67755.4 67696.5 67696.5 24008 3781.23 50.7 50.7 50.7
Rated Capacity 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032 101032
Sumber : Pengolahan Data

Grafik Load Profile Alat Ukur


120000

100000

80000

60000
Kebutuhan Aktual
40000 Rated Capacity
20000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.3
Grafik Load Profile Alat Ukur
Sumber : Pengolahan data

b. Scrill Saw
Tabel 4.130
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Scrill Saw
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 390 28467.5 56295.2 58415.4 58206.1 58175.7 58175.7 58763 59037 59087.7 59087.7 58500.4 58226.4 58175.7 58175.7 20965.6 3602.57 393.8 393.8 393.8
Rated Capacity 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9 88214.9
Sumber : Pengolahan Data

Grafik Load Profile Scrill Saw


100000
90000
80000
70000
60000
50000
Kebutuhan Aktual
40000
Rated Capacity
30000
20000
10000
0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.4
Grafik Load Profile Scrill Saw
Sumber : Pengolahan data

c. Mesin Drilling Ø6mm


Tabel 4.131
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Mesin Drilling Ø6mm
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 210 10935.1 17047.3 18573.3 18555 18534.5 18534.5 18759.3 18789.7 18823.9 18823.9 18599.1 18568.7 18534.5 18534.5 4291.51 2364.07 198.8 198.8 198.8
Rated Capacity 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9 27991.9
Sumber : Pengolahan Data

Grafik Load Profile Mesin Drilling Ø6mm


30000

25000

20000

15000
Kebutuhan Aktual
10000 Rated Capacity

5000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.5
Grafik Load Profile Mesin Drilling Ø6mm
Sumber : Pengolahan data

d. Mesin Drilling Ø8mm


Tabel 4.132
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Mesin Drilling Ø8mm
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 65 3521.59 5213.76 6831.36 6831.36 6810.86 6810.86 6882.91 6882.91 6917.08 6917.08 6845.03 6845.03 6810.86 6810.86 2245.62 2245.62 80.35 80.35 80.35
Rated Capacity 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32 9583.32
Sumber : Pengolahan Data

Grafik Load Profile Mesin Drilling Ø8mm


12000

10000

8000

6000
Kebutuhan Aktual
4000 Rated Capacity

2000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.6
Grafik Load Profile Mesin Drilling Ø8mm
Sumber : Pengolahan data

e. Bubut
Tabel 4.133
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Bubut
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 110 8381.46 11187 11083.1 11083.1 11083.1 11083.1 11256.3 11256.3 11256.3 11256.3 11083.1 11083.1 11083.1 11083.1 110 110 110 110 110
Rated Capacity 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2 15624.2
Sumber : Pengolahan Data
105

Grafik Load Profile Bubut


18000
16000
14000
12000
10000
8000 Kebutuhan Aktual
6000 Rated Capacity
4000
2000
0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.7
Grafik Load Profile Bubut
Sumber : Pengolahan data

f. Pneudrem Sender
Tabel 4.134
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Pneudrem Sender
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 510 24798.4 45011.3 46767.3 46661 46635.6 46635.6 47144 47321.1 47363.5 47363.5 46855 46678 46635.6 46635.6 14421 3202.37 515.35 515.35 515.35
Rated Capacity 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5 69934.5
Sumber : Pengolahan Data

Grafik Load Profile Pneudrem Sender


80000
70000
60000
50000
40000
Kebutuhan Aktual
30000
Rated Capacity
20000
10000
0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.8
Grafik Load Profile Pneudrem Sender
Sumber : Pengolahan data

g. Spray Gun
Tabel 4.135
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Spray Gun
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 540 42713.2 83083.2 85814.8 85580 85539.7 85539.7 86423.1 86814.4 86881.5 86881.5 85998.2 85606.9 85539.7 85539.7 29570.8 4776.43 524.15 524.15 524.15
Rated Capacity 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865 123865
Sumber : Pengolahan Data

Grafik Load Profile Spray Gun


140000

120000

100000

80000

60000 Kebutuhan Aktual


Rated Capacity
40000

20000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.9
Grafik Load Profile Spray Gun
Sumber : Pengolahan data

h. Oven Dryer
Tabel 4.136
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Oven Dryer
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 465 28008.1 52412.1 54544.3 54334.8 54304.4 54304.4 54881.7 55104.7 55155.3 55155.3 54578 54355.1 54304.4 54304.4 17728.2 3601.02 392.25 392.25 392.25
Rated Capacity 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1
Sumber : Pengolahan Data

Grafik Load Profile Oven Dryer


100000
90000
80000
70000
60000
50000
Kebutuhan Aktual
40000
Rated Capacity
30000
20000
10000
0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.10
Grafik Load Profile Oven Dryer
Sumber : Pengolahan data

i. Kerja Bangku
Tabel 4.137
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Kerja Bangku
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 34839 64360.4 66061.3 65594.8 65569.3 65569.3 66294.4 66561.2 66603.7 66603.7 65878.6 65611.7 65569.3 65569.3 19628 2720.82 33.8 33.8 33.8
Rated Capacity 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1 88719.1
Sumber : Pengolahan Data
106

Grafik Load Profile Kerja Bangku


100000
90000
80000
70000
60000
50000
Kebutuhan Aktual
40000
Rated Capacity
30000
20000
10000
0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.11
Grafik Load Profile Kerja Bangku
Sumber : Pengolahan data

j. Kerja Bangku Sub- Sub Assembling 1


Tabel 4.138
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Kerja Bangku Sub- Sub Assembling 1
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 0 3870.05 3870.05 3833.74 3833.74 3833.74 3833.74 3894.25 3894.25 3894.25 3894.25 3833.74 3833.74 3833.74 3833.74 0 0 0 0
Rated Capacity 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72 5458.72
Sumber : Pengolahan Data

Grafik Load Profile Kerja Bangku Sub- Sub Assembling 1


6000

5000

4000

3000
Kebutuhan Aktual
2000 Rated Capacity

1000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.12
Grafik Load Profile Kerja Bangku Sub- Sub Assembling 1
Sumber : Pengolahan data

k. Kerja Bangku Sub- Sub Assembling 2


Tabel 4.139
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Kerja Bangku Sub- Sub Assembling 2
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 0 2821.47 2821.47 2795 2795 2795 2795 2839.11 2839.11 2839.11 2839.11 2795 2795 2795 2795 0 0 0 0
Rated Capacity 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7 3979.7
Sumber : Pengolahan Data

Grafik Load Profile Kerja Bangku Sub- Sub Assembling 2


4500
4000
3500
3000
2500
2000 Kebutuhan Aktual
1500 Rated Capacity
1000
500
0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.13
Grafik Load Profile Kerja Bangku Sub- Sub Assembling 2
Sumber : Pengolahan data

l. Kerja Bangku Sub Assembling 1


Tabel 4.140
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Kerja Bangku Sub Assembling 1
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 0 752.851 3134.74 3134.74 3105.33 3105.33 3105.33 3105.33 3154.34 3154.34 3154.34 3154.34 3105.33 3105.33 3105.33 3105.33 0 0 0
Rated Capacity 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56 4421.56
Sumber : Pengolahan Data

Grafik Load Profile Kerja Bangku Sub Assembling 1


5000
4500
4000
3500
3000
2500
Kebutuhan Aktual
2000
Rated Capacity
1500
1000
500
0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.14
Grafik Load Profile Kerja Bangku Sub Assembling 1
Sumber : Pengolahan data

m. Kerja Bangku Sub Assembling 2


Tabel 4.141
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Kerja Bangku Sub Assembling 2
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 0 818.572 3408.39 3408.39 3376.41 3376.41 3376.41 3376.41 3429.7 3429.7 3429.7 3429.7 3376.41 3376.41 3376.41 3376.41 0 0 0
Rated Capacity 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55
Sumber : Pengolahan Data
107

Grafik Load Profile Kerja Bangku Sub Assembling 2


6000

5000

4000

3000
Kebutuhan Aktual
2000 Rated Capacity

1000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.15
Grafik Load Profile Kerja Bangku Sub Assembling 2
Sumber : Pengolahan data

n. Kerja Bangku Assembling


Tabel 4.142
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Kerja Bangku Assembling
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 0 8262.94 14834.8 18959.8 19761.7 19761.7 19731.3 19803.9 19906.2 19906.2 19956.9 19905.6 19803.3 19803.3 19752.6 13070.6 6588.82 6588.82 3376.41
Rated Capacity 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02 4574.02
Sumber : Pengolahan Data

Grafik Load Profile Kerja Bangku Assembling


25000

20000

15000

Kebutuhan Aktual
10000
Rated Capacity
5000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.16
Grafik Load Profile Kerja Bangku Assembling
Sumber : Pengolahan data

o. Kerja Bangku Pengemasan


Tabel 4.143
Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity ) Kerja Bangku Pengemasan
Periode
Description Desember Januari Februari Maret April
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Kebutuhan Aktual 0 0 0 0 2545.12 3408.39 3408.39 3408.39 3376.41 3376.41 3376.41 3376.41 3429.7 3429.7 3429.7 3429.7 3376.41 3376.41 3376.41 3376.41
Rated Capacity 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55 4807.55
Sumber : Pengolahan Data

Grafik Load Profile Kerja Bangku Pengemasan


6000

5000

4000

3000
Kebutuhan Aktual
2000 Rated Capacity

1000

0
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Desember Januari Februari Maret April

Gambar 4.17
Grafik Load Profile Kerja Bangku Pengemasan
Sumber : Pengolahan data
108

C. Pembahasan dan Analisis


1. Pengumpulan Data

Pengumpulan dan penelitian ini bersifat kuantitatif. Data ini bersumber

dari Master Modul 1 MRP dan membuat Company Profile PT. SE

WOODEN TOYS yang merupakan perusahaan industri manufaktur dan

bergerak di bagian penjualan mainan kereta api.

a. Bill Of Material Chart

Membuat Bill Of Material Chart yang di isi data dari

komponen epsk yaitu untuk level 0 Produk mainan kereta api kayu,

Untuk level 1, Rakitan mainan, Kemasan, Untuk level 2 Bagian atas,

Bagian bawah, Bagian belakang, Untuk level 3 Cerobong, Badan

lokomotif, Pasak, Roda samping kiri, As roda depan, Badan bawah,

As roda belakang, Roda samping kanan, Pasak, Badan atas, Atap,

Untuk level 4 Pengunci roda belakang kiri, Pengunci roda depan

kiri, Perangkai roda kiri, Roda belakang, Roda depan kiri, Pengunci

roda belakan kanan, Pengunci roda depan kanan, Perangkai roda

kanan, Roda belakang kanan, Roda depan kanan, dengan tujuan

lebih spesifik lagi dan membuat lampiran OPC dengan sofwere

autocad/dwg.

b. Bill Of Material Table

1) Direct Material Mainan Kereta Api Kayu

Dari data tersebut di dapatkan rincian mulai dari gambar

part, nama part, q/u, produk awal mm dan ukuran produk jadi,
109

Dengan ketentuan yang ada di master modul 1 mrp, dan membuat

sebanyak 19 komponen.

2) Indirect Material Mainan Kereta Api Kayu

Membuat komponen material pendukung yang terdiri dari

Cat Kayu Warna Abu, Cat Kayu Warna Pink, Cat Kayu Warna Biru,

Mika, Kardus, Data tersebut di dapatkan dari master modul yang

sudah di tentukan.

2. Pengolahan Data

Setelah data sudah didapatkan maka masuk ke proses pengolahan data

dimana data tersebut diggunakan untuk mencari nilai forecasting, waktu

operasional, mps-rccp, mrp, crp dengan rincian sebagai berikut:

a. Forecasting

1) Forecasting

Pada Forecasting ini membuat table yang terdiri dari 27 part

data yang di dapatkan dari BOM Chart pengumpulan data dan di

urutkan dari level yang terendah hingga level tertinggi, untuk q/u di isi

saja 1.

2) Metode Weighted Moving Average (WMA)

Pada WMA ini membuat metode peramalan permintaan yang

terdiri 2 tahun dengan total sebanyak 24 bulan, untuk nilai data

peramalan permintaan di dapatkan dari master modul yang sudah di

tentukan, membuat Grafik Peramalan Forecasting dengan aplikasi


110

POMQM untuk membuat grafik tersebut menggunakan data peramalan

permintaan di input kedalam aplikasi POMQM dan membuat lampiran

forecasting pada file terpisah.

b. Waktu Operasi Unit for Capacity Requirement Planning (CRP)

1. Pembuatan Komponen Badan Bawah

Pada Pembuatan Komponen Badan Bawah Ada 8 unit

mesin yang di gunakan mulai dari mesin alat ukur sampai mesin

kerja bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan badan bawah dan

nilai data Operating Kode yang di ambil dari OPC, untuk nilai

set-up mesin didapatkan dari asumsi hanya tidak boleh melebihi

dari 10 detik, Untuk nilai waktu siklus di ambil dari OPC yang

sudah di buat dengan total 37 detik, Untuk mendapatkan nilai

waktu normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 46 detik dan waktu baku dengan total 53 detik.

2. Komponen As Roda Depan

Pada Pembuatan Komponen As Roda Depan Ada 6 unit

mesin yang di gunakan mulai dari mesin alat ukur sampai mesin

kerja bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan as roda depan dan

nilai data Operating Kode yang di ambil dari OPC, untuk nilai

set-up mesin didapatkan dari asumsi hanya tidak boleh melebihi


111

dari 10 detik, Untuk nilai waktu siklus di ambil dari OPC yang

sudah di buat dengan total 31 detik, Untuk mendapatkan nilai

waktu normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 40 detik dan waktu baku dengan total 52 detik.

3. Komponen As Roda Belakang

Pada Pembuatan Komponen As Roda Belakang Ada 6

unit mesin yang di gunakan mulai dari mesin alat ukur sampai

mesin kerja bangku pemeriksaan, di lanjutkan dengan process

masing-masing mesin yang di lalui untuk pembuatan as roda

belakang dan nilai data Operating Kode yang di ambil dari OPC,

untuk nilai set-up mesin didapatkan dari asumsi hanya tidak

boleh melebihi dari 10 detik, Untuk nilai waktu siklus di ambil

dari OPC yang sudah di buat dengan total 31 detik, Untuk

mendapatkan nilai waktu normal dan waktu baku harus

membuat perhitungan penyesuaian dan kelonggaran, untuk nilai

waktu normal dengan total 9 detik dan waktu baku dengan total

12 detik.

4. Komponen Roda Depan Kanan

Pada Pembuatan Komponen Roda Depan Kanan Ada 7

unit mesin yang di gunakan mulai dari mesin alat ukur sampai

mesin kerja bangku pemeriksaan, di lanjutkan dengan process

masing-masing mesin yang di lalui untuk pembuatan roda depan


112

kanan dan nilai data Operating Kode yang di ambil dari OPC,

untuk nilai set-up mesin didapatkan dari asumsi hanya tidak

boleh melebihi dari 10 detik, Untuk nilai waktu siklus di ambil

dari OPC yang sudah di buat dengan total 34 detik, Untuk

mendapatkan nilai waktu normal dan waktu baku harus

membuat perhitungan penyesuaian dan kelonggaran, untuk nilai

waktu normal dengan total 39 detik dan waktu baku dengan total

46 detik.

5. Komponen Roda Depan Kiri

Pada Pembuatan Komponen Roda Depan Kiri Ada 7 unit

mesin yang di gunakan mulai dari mesin alat ukur sampai mesin

kerja bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan rodan depan kiri

dan nilai data Operating Kode yang di ambil dari OPC, untuk

nilai set-up mesin didapatkan dari asumsi hanya tidak boleh

melebihi dari 10 detik, Untuk nilai waktu siklus di ambil dari

OPC yang sudah di buat dengan total 34 detik, Untuk

mendapatkan nilai waktu normal dan waktu baku harus

membuat perhitungan penyesuaian dan kelonggaran, untuk nilai

waktu normal dengan total 47 detik dan waktu baku dengan total

64 detik.

6. Komponen Roda Belakang Kanan


113

Pada Pembuatan Komponen Roda Belakang Kanan Ada

7 unit mesin yang di gunakan mulai dari mesin alat ukur sampai

mesin kerja bangku pemeriksaan, di lanjutkan dengan process

masing-masing mesin yang di lalui untuk pembuatan roda

belakang kanan dan nilai data Operating Kode yang di ambil

dari OPC, untuk nilai set-up mesin didapatkan dari asumsi

hanya tidak boleh melebihi dari 10 detik, Untuk nilai waktu

siklus di ambil dari OPC yang sudah di buat dengan total 34

detik, Untuk mendapatkan nilai waktu normal dan waktu baku

harus membuat perhitungan penyesuaian dan kelonggaran,

untuk nilai waktu normal dengan total 37 detik dan waktu baku

dengan total 40 detik.

7. Komponen Roda Belakang Kiri

Pada Pembuatan Komponen Roda Belakang Kanan Ada

7 unit mesin yang di gunakan mulai dari mesin alat ukur sampai

mesin kerja bangku pemeriksaan, di lanjutkan dengan process

masing-masing mesin yang di lalui untuk pembuatan roda

belakang kiri dan nilai data Operating Kode yang di ambil dari

OPC, untuk nilai set-up mesin didapatkan dari asumsi hanya

tidak boleh melebihi dari 10 detik, Untuk nilai waktu siklus di

ambil dari OPC yang sudah di buat dengan total 34 detik, Untuk

mendapatkan nilai waktu normal dan waktu baku harus

membuat perhitungan penyesuaian dan kelonggaran, untuk nilai


114

waktu normal dengan total 38 detik dan waktu baku dengan total

43 detik.

8. Komponen Perangkai Roda Kanan

Pada Pembuatan Komponen Perangkai Roda Kanan Ada

8 unit mesin yang di gunakan mulai dari mesin alat ukur sampai

mesin kerja bangku pemeriksaan, di lanjutkan dengan process

masing-masing mesin yang di lalui untuk pembuatan perangkai

roda kanan dan nilai data Operating Kode yang di ambil dari

OPC, untuk nilai set-up mesin didapatkan dari asumsi hanya

tidak boleh melebihi dari 10 detik, Untuk nilai waktu siklus di

ambil dari OPC yang sudah di buat dengan total 36 detik, Untuk

mendapatkan nilai waktu normal dan waktu baku harus

membuat perhitungan penyesuaian dan kelonggaran, untuk nilai

waktu normal dengan total 46 detik dan waktu baku dengan total

60 detik.

9. Komponen Perangkai Roda Kiri

Pada Pembuatan Komponen Perangkai Roda Kiri Ada 8

unit mesin yang di gunakan mulai dari mesin alat ukur sampai

mesin kerja bangku pemeriksaan, di lanjutkan dengan process

masing-masing mesin yang di lalui untuk pembuatan perangkai

roda kiri dan nilai data Operating Kode yang di ambil dari OPC,

untuk nilai set-up mesin didapatkan dari asumsi hanya tidak

boleh melebihi dari 10 detik, Untuk nilai waktu siklus di ambil


115

dari OPC yang sudah di buat dengan total 36 detik, Untuk

mendapatkan nilai waktu normal dan waktu baku harus

membuat perhitungan penyesuaian dan kelonggaran, untuk nilai

waktu normal dengan total 47 detik dan waktu baku dengan total

61 detik.

10. Komponen Pengunci Roda Depan Kanan

Pada Pembuatan Komponen Pengunci Roda Depan

Kanan Ada 7 unit mesin yang di gunakan mulai dari mesin alat

ukur sampai mesin kerja bangku pemeriksaan, di lanjutkan

dengan process masing-masing mesin yang di lalui untuk

pembuatan pengunci roda depan kanan dan nilai data Operating

Kode yang di ambil dari OPC, untuk nilai set-up mesin

didapatkan dari asumsi hanya tidak boleh melebihi dari 10 detik,

Untuk nilai waktu siklus di ambil dari OPC yang sudah di buat

dengan total 34 detik, Untuk mendapatkan nilai waktu normal

dan waktu baku harus membuat perhitungan penyesuaian dan

kelonggaran, untuk nilai waktu normal dengan total 46 detik dan

waktu baku dengan total 61 detik.

11. Komponen Pengunci Roda Depan Kiri

Pada Pembuatan Komponen Pengunci Roda Depan Kiri

Ada 7 unit mesin yang di gunakan mulai dari mesin alat ukur

sampai mesin kerja bangku pemeriksaan, di lanjutkan dengan

process masing-masing mesin yang di lalui untuk pembuatan


116

pengunci roda depan kiri dan nilai data Operating Kode yang di

ambil dari OPC, untuk nilai set-up mesin didapatkan dari asumsi

hanya tidak boleh melebihi dari 10 detik, Untuk nilai waktu

siklus di ambil dari OPC yang sudah di buat dengan total 34

detik, Untuk mendapatkan nilai waktu normal dan waktu baku

harus membuat perhitungan penyesuaian dan kelonggaran,

untuk nilai waktu normal dengan total 42 detik dan waktu baku

dengan total 51 detik.

12. Komponen Pengunci Roda Belakang Kanan

Pada Pembuatan Komponen Pengunci Roda Belakang

Kanan Ada 7 unit mesin yang di gunakan mulai dari mesin alat

ukur sampai mesin kerja bangku pemeriksaan, di lanjutkan

dengan process masing-masing mesin yang di lalui untuk

pembuatan pengunci roda belakang kanan dan nilai data

Operating Kode yang di ambil dari OPC, untuk nilai set-up

mesin didapatkan dari asumsi hanya tidak boleh melebihi dari

10 detik, Untuk nilai waktu siklus di ambil dari OPC yang sudah

di buat dengan total 34 detik, Untuk mendapatkan nilai waktu

normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 40 detik dan waktu baku dengan total 47 detik.

13. Komponen Pengunci Roda Belakang Kiri


117

Pada Pembuatan Komponen Pengunci Roda Belakang

Kiri Ada 7 unit mesin yang di gunakan mulai dari mesin alat

ukur sampai mesin kerja bangku pemeriksaan, di lanjutkan

dengan process masing-masing mesin yang di lalui untuk

pembuatan pengunci roda belakang kiri dan nilai data Operating

Kode yang di ambil dari OPC, untuk nilai set-up mesin

didapatkan dari asumsi hanya tidak boleh melebihi dari 10 detik,

Untuk nilai waktu siklus di ambil dari OPC yang sudah di buat

dengan total 34 detik, Untuk mendapatkan nilai waktu normal

dan waktu baku harus membuat perhitungan penyesuaian dan

kelonggaran, untuk nilai waktu normal dengan total 39 detik dan

waktu baku dengan total 46 detik.

14. Komponen Badan Atas

Pada Pembuatan Komponen Badan Atas Ada 7 unit

mesin yang di gunakan mulai dari mesin alat ukur sampai mesin

kerja bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan badan atas dan

nilai data Operating Kode yang di ambil dari OPC, untuk nilai

set-up mesin didapatkan dari asumsi hanya tidak boleh melebihi

dari 10 detik, Untuk nilai waktu siklus di ambil dari OPC yang

sudah di buat dengan total 33 detik, Untuk mendapatkan nilai

waktu normal dan waktu baku harus membuat perhitungan


118

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 39 detik dan waktu baku dengan total 47 detik.

15. Komponen Atap

Pada Pembuatan Komponen Atap Ada 6 unit mesin yang

di gunakan mulai dari mesin alat ukur sampai mesin kerja

bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan atap dan nilai data

Operating Kode yang di ambil dari OPC, untuk nilai set-up

mesin didapatkan dari asumsi hanya tidak boleh melebihi dari

10 detik, Untuk nilai waktu siklus di ambil dari OPC yang sudah

di buat dengan total 31 detik, Untuk mendapatkan nilai waktu

normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 38 detik dan waktu baku dengan total 47 detik.

16. Komponen Pasak Belakang

Pada Pembuatan Komponen Pasak Belakang Ada 6 unit

mesin yang di gunakan mulai dari mesin alat ukur sampai mesin

kerja bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan pasak belakang

dan nilai data Operating Kode yang di ambil dari OPC, untuk

nilai set-up mesin didapatkan dari asumsi hanya tidak boleh

melebihi dari 10 detik, Untuk nilai waktu siklus di ambil dari

OPC yang sudah di buat dengan total 31 detik, Untuk


119

mendapatkan nilai waktu normal dan waktu baku harus

membuat perhitungan penyesuaian dan kelonggaran, untuk nilai

waktu normal dengan total 36 detik dan waktu baku dengan total

41 detik.

17. Komponen Badan Lokomotif

Pada Pembuatan Komponen Badan Lokomotif Ada 7

unit mesin yang di gunakan mulai dari mesin alat ukur sampai

mesin kerja bangku pemeriksaan, di lanjutkan dengan process

masing-masing mesin yang di lalui untuk pembuatan atap dan

nilai data Operating Kode yang di ambil dari OPC, untuk nilai

set-up mesin didapatkan dari asumsi hanya tidak boleh melebihi

dari 10 detik, Untuk nilai waktu siklus di ambil dari OPC yang

sudah di buat dengan total 39 detik, Untuk mendapatkan nilai

waktu normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 44 detik dan waktu baku dengan total 51 detik.

18. Komponen Cerobong

Pada Pembuatan Komponen Cerobong Ada 6 unit mesin

yang di gunakan mulai dari mesin alat ukur sampai mesin kerja

bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan cerobong dan nilai

data Operating Kode yang di ambil dari OPC, untuk nilai set-up

mesin didapatkan dari asumsi hanya tidak boleh melebihi dari


120

10 detik, Untuk nilai waktu siklus di ambil dari OPC yang sudah

di buat dengan total 30 detik, Untuk mendapatkan nilai waktu

normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 38 detik dan waktu baku dengan total 48 detik.

19. Komponen Pasak Depan

Pada Pembuatan Komponen Pasak Depan Ada 6 unit

mesin yang di gunakan mulai dari mesin alat ukur sampai mesin

kerja bangku pemeriksaan, di lanjutkan dengan process masing-

masing mesin yang di lalui untuk pembuatan pasak depan dan

nilai data Operating Kode yang di ambil dari OPC, untuk nilai

set-up mesin didapatkan dari asumsi hanya tidak boleh melebihi

dari 10 detik, Untuk nilai waktu siklus di ambil dari OPC yang

sudah di buat dengan total 31 detik, Untuk mendapatkan nilai

waktu normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 41 detik dan waktu baku dengan total 55 detik.

20. Sub-Sub Assembling 1

Pada Sub-Sub Assembling 1 Ada 2 unit mesin yang di

gunakan mulai dari mesin meja assembling sampai mesin meja

pemeriksaan, di lanjutkan dengan process masing-masing mesin

yang di lalui untuk sub-sub assembling 1 dan nilai data

Operating Kode yang di ambil dari OPC, untuk nilai set-up


121

mesin didapatkan dari asumsi hanya tidak boleh melebihi dari

10 detik, Untuk nilai waktu siklus di ambil dari OPC yang sudah

di buat dengan total 10 detik, Untuk mendapatkan nilai waktu

normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 13 detik dan waktu baku dengan total 17 detik.

21. Sub-Sub Assembling 2

Pada Sub-Sub Assembling 2 Ada 2 unit mesin yang di

gunakan mulai dari mesin meja assembling sampai mesin meja

pemeriksaan, di lanjutkan dengan process masing-masing mesin

yang di lalui untuk sub-sub assembling 2 dan nilai data

Operating Kode yang di ambil dari OPC, untuk nilai set-up

mesin didapatkan dari asumsi hanya tidak boleh melebihi dari

10 detik, Untuk nilai waktu siklus di ambil dari OPC yang sudah

di buat dengan total 10 detik, Untuk mendapatkan nilai waktu

normal dan waktu baku harus membuat perhitungan

penyesuaian dan kelonggaran, untuk nilai waktu normal dengan

total 11 detik dan waktu baku dengan total 12 detik.

22. Sub Assembling 1

Pada Sub Assembling 1 Ada 2 unit mesin yang di

gunakan mulai dari mesin meja assembling sampai mesin meja

pemeriksaan, di lanjutkan dengan process masing-masing mesin

yang di lalui untuk sub assembling 1 dan nilai data Operating


122

Kode yang di ambil dari OPC, untuk nilai set-up mesin

didapatkan dari asumsi hanya tidak boleh melebihi dari 10 detik,

Untuk nilai waktu siklus di ambil dari OPC yang sudah di buat

dengan total 10 detik, Untuk mendapatkan nilai waktu normal

dan waktu baku harus membuat perhitungan penyesuaian dan

kelonggaran, untuk nilai waktu normal dengan total 12 detik dan

waktu baku dengan total 14 detik.

23. Sub Assembling 2

Pada Sub Assembling 2 Ada 2 unit mesin yang di

gunakan mulai dari mesin meja assembling sampai mesin meja

pemeriksaan, di lanjutkan dengan process masing-masing mesin

yang di lalui untuk sub assembling 2 dan nilai data Operating

Kode yang di ambil dari OPC, untuk nilai set-up mesin

didapatkan dari asumsi hanya tidak boleh melebihi dari 10 detik,

Untuk nilai waktu siklus di ambil dari OPC yang sudah di buat

dengan total 10 detik, Untuk mendapatkan nilai waktu normal

dan waktu baku harus membuat perhitungan penyesuaian dan

kelonggaran, untuk nilai waktu normal dengan total 12 detik dan

waktu baku dengan total 15 detik.

24. Assembling

Pada Assembling Ada 2 unit mesin yang di gunakan

mulai dari mesin meja assembling sampai mesin meja

pemeriksaan, di lanjutkan dengan process masing-masing mesin


123

yang di lalui untuk assembling dan nilai data Operating Kode

yang di ambil dari OPC, untuk nilai set-up mesin didapatkan

dari asumsi hanya tidak boleh melebihi dari 10 detik, Untuk

nilai waktu siklus di ambil dari OPC yang sudah di buat dengan

total 10 detik, Untuk mendapatkan nilai waktu normal dan

waktu baku harus membuat perhitungan penyesuaian dan

kelonggaran, untuk nilai waktu normal dengan total 12 detik dan

waktu baku dengan total 14 detik.

25. Pengemasan Mika

Pada Pengemasan Mika Ada 2 unit mesin yang di

gunakan mulai dari mesin meja assembling sampai mesin meja

pemeriksaan, di lanjutkan dengan process masing-masing mesin

yang di lalui untuk pengemasan mika dan nilai data Operating

Kode yang di ambil dari OPC, untuk nilai set-up mesin

didapatkan dari asumsi hanya tidak boleh melebihi dari 10 detik,

Untuk nilai waktu siklus di ambil dari OPC yang sudah di buat

dengan total 5 detik, Untuk mendapatkan nilai waktu normal

dan waktu baku harus membuat perhitungan penyesuaian dan

kelonggaran, untuk nilai waktu normal dengan total 6 detik dan

waktu baku dengan total 7 detik.

26. Pengemasan Kardus

Pada Pengemasan Kardus Ada 2 unit mesin yang di

gunakan mulai dari mesin meja assembling sampai mesin meja


124

pemeriksaan, di lanjutkan dengan process masing-masing mesin

yang di lalui untuk pengemasan kardus dan nilai data Operating

Kode yang di ambil dari OPC, untuk nilai set-up mesin

didapatkan dari asumsi hanya tidak boleh melebihi dari 10 detik,

Untuk nilai waktu siklus di ambil dari OPC yang sudah di buat

dengan total 5 detik, Untuk mendapatkan nilai waktu normal

dan waktu baku harus membuat perhitungan penyesuaian dan

kelonggaran, untuk nilai waktu normal dengan total 6 detik dan

waktu baku dengan total 7 detik.

Dari hasil perhitungan tersebut didapatkan kesimpulan bahwa Hasil

dari Waktu Operasi Unit for Capacity Requirement Planning (CRP) untuk

Total Waktu Siklus adalah 89 detik dan Total Waktu Keseluruhan adalah

698 detik.

c. Master Production Schedule (MPS)

Pada table Master Production Schedule (MPS) dengan

priode pengolahan data di tahun ke 2 atau 2022 nilai peramalan

permintaan dari bulan januari sampai desember di ambil dari

lampiran pomqm, Untuk nilai permintaan aktual di dapatkan dari

perhitungan peramalan permintaan dikali 0,5% sesuai dengan

ketentuan, Untuk nilai lost di dapatkan dari perhitungan permintaan

aktual dikali LM 12% di tambah LP 2% sesuai dengan ketentuan,

Untuk nilai mps di dapatkan dari nilai permintaan aktul ditambah

nilai lost.
125

d. Rough Cut Capacity Planning (RCCP)

1) Perhitungan RCCP

Pada tabel Rough Cut Capacity Planning (RCCP)

dengan priode pengolahan data di tahun 2022 ada 26 komponen

perhitungan rccp mulai dari komponen badan bawah sampai

pengemasan kardus, dimana masing-masing mempunyai alat

mesin yang digunakan untuk pembuatan komponen di hitung

dari bulan januari sampai desember setiap mesin mempunyai

nilai data yang di dapatkan dari perhitungan mps pada bulan

dikali wb pada mesin komponen, dari hasil perhitungan

didapatkan nilai di setiap alat mesin tersebut sampai dengan

nilai pemeriksaan.

2) Resume Jumlah Kapasitas Yang Dibutuhkan

Pada tabel Resume Jumlah Kapasitas Yang Dibutuhkan dengan

priode pengolahan data di tahun 2022 dari bulan januari sampai

desember semua alat mesin dan alat kerja bangku di masukan

pada tabel dan di sesuaikan, untuk nilai alat mesin dan alat

bangku didapatkan dari perhitungan setiap periode alat mesin

atau alat kerja bangku ditambah dengan komponen yang

menggunakan alat tersebut dibagi dengan 3600, Dari hasil

perhitungan tersebut didapatkan kesimpulan bahwa total mesin

Alat Ukur 953, Jig Saw 832, Drilling Ø6mm 264, Drilling

Ø8mm 90, Bubut 147, Pneudrem Sender 660, Spray Gun 1168,
126

Oven Dryer 837, Pemeriksaan 945, Sub- Sub Assembling I 51,

Sub-Sub Assembling II 38, Sub Assembling I 42, Sub

Assembling II 45, Sub Assembling III 0, Assembling 43,

Pengemasan 45.

3) Kapasitas Perusahaan

Pada Kapasitas Perusahaan keterangan Jam Kerja 8 jam

per shift, Shift Kerja 3 shift per hari dan Hari Kerja 20 hari per

bulan didapatkan dari company profile yang sudah di buat,

Untuk nilai alat mesin dan alat kerja bangku kapasitas

perusahaan didapatkan dari hasil perhitungan jumlah mesin

yang ada di tabel resume jumlah kapasitas yang dibutuhkan,

Untuk nilai kapasitas yang tersedia alat mesin dan alat kerja

bangku didapatkan dari perhitungan jam kerja dikali shift kerja

dikali hari kerja dikali jumlah mesin yang ada di kapasitas

perusahaan.

e. Material Requirement Planning (MRP)

1) Perhitungan MRP

Pada tabel Perhitungan MRP dibutuhkan Penentuan

Safety Stock dengan menggunakan Metode Konservatif dengan

nilai Pemakaian Rata-Rata U 91 unit per hari, Lead Time Rata-

Rata L 7 hari, Pemakaian Terbesar U max 92 unit per hari, Lead

Time Terlama L max 7 hari, On Hand 121, Perhitungan mrp ada

27 nama komponen terdiri dari Produk mainan sampai Roda


127

belakang kanan dimulai level 0 sampai level 4 dengan periode

bulan desember sampai bulan april, Untuk nilai Gross

Requirement (mps dibagi 4), Projected Hand (on hand dikurang

safety stock), Net Requirement (gr dikurang project hand),

Planned Order Receipt (net requirement), Planned Order

Release (gr dikurang project hand) perhitungan ini seterus nya

digunakan sampai 27 nama komponen.

2) Resume Planned Order Receipt

Pada tabel Resume Planned Order Receipt MRP di

urutkan dari level 0 sampai level 4 di ikuti dengan komponen

dari Produk mainan kereta api kayu sampai roda belakang

kanan, nilai setiap periode bulan didapatkan dari perhitungan

mrp dengan sesuai pada setiap masing-masing komponen.

f. Capacity Requirement Planning (CRP)

1) Perhitungan CRP

Pada Perhitungan CRP ada 26 tabel nama komponen

terdiri dari Badan Bawah sampai Pengemasan Kardus masing-

masing komponen mempunyai alat mesin dan periode dari bulan

desember sampai april, Untuk nilai setiap mesin didapatkan dari

perhitungan waktu set up mesin dikali hari kerja perbulan dibagi

4 ditambah waktu total proses komponen wb dikali resume

planned order receipt, dari hasil perhitungan didapatkan nilai di

setiap alat mesin.


128

2) Resume Jumlah Kebutuhan Aktual

Pada tabel Resume Jumlah Kebutuhan Aktual untuk

mencari nilai setiap mesin didapatkan dari perhitungan tabel crp

dengan sesuai pada setiap masing-masing komponen.

g. Perbandingan Kebutuhan Aktual dengan Kapasitas yang Tersedia

Pada Perbandingan Kebutuhan Aktual dengan Kapasitas

yang Tersedia ada 15 tabel komponen terdiri dari alat ukur sampai

kerja bangku pengemasan untuk mencari nilai waktu yang tersedia

didapatkan dari perhitungan kapasitas tersedia di rccp dibagi 4,

untuk mencari nilai tingkat utilitas sudah di tentukan yaitu 93% dan

tingkat efisiensi 95%, mencari nilai rated capacity di dapatkan dari

perhitungan waktu yang tersedia dikali tingkat utilitas dikali tingkat

efisiensi, untuk mencari nilai kebutuhan aktual didapatkan dari

perhitungan resume jumlah kebutuhan aktual crp dan untuk mencari

nilai nilai over atau under didapatkan dari perhitungan rated

capacity dibagi kebutuhan aktual.

h. Grafik Load Profile Kebutuhan Aktual Kapasitas (Rated Capacity)

Dari hasil perhitungan Perbandingan Kebutuhan Aktual

dengan Kapasitas yang Tersedia didapatkan nilai kebutuhan aktual

dan rated capacity untuk membuat grafik di 15 komponen tersebut

yang terdiri dari alat ukur sampai kerja bangku pengemasan.


BAB V

KESIMPULAN DAN SARAN

A. Kesimpulan

Berdasarkan hasil penelitian menunjukkan bahwa:

1. Total waktu siklus keseluruhan CRP yang didapatkan pada modul ini

adalah 698 detik.

2. Jumlah kapasitas mesin yang dibutuhkan pada periode Januari sampai

Desember 2022 adalah kapasitas Mesin Jig Saw sebanyak 399.360 , Mesin

Drilling 6mm sebanyak 126.720 , Mesin Drilling 8 mm sebanyak 432.000

, Mesin Bubut sebanyak 70.560 , Mesin Pneudrem Sender sebanyak

316.800 , Mesin Spray Gun sebanyak 569.280 , dan Mesin Oven Dryer

sebanyak 401.760.

3. Jumlah kebutuhan aktual dengan Reated Capacity pada mainan kereta api

kayu adalah 19.242 unit.

B. Saran

Dengan melakukan analissi ini, kami berharap PR SE WOODEN

TOYS akan mulai merencakan semua proses komponrn-komponen yang akan

menjadi bagian dari kegatan produksi di dalam perusahaan, salah satunya yaitu

persediaan bahan baku. Dengan perencanaan yang baik proses akan berjalan

dengan lancar sesuai dengan yang diharapkan oleh perusahaan. Kami juga

berharap dengan persediaan yang cukup, perusahaan dapat menghemat baya,

khusus nya biaya persediaan tanpa mengganggu proses produksi yang

129
130

akan berdampak pada kelangsungan hidup perusahaan dan kepuasan

konsumen.
DAFTAR PUSTAKA

Angela, Peppy. 2022. Perencanaan Kebutuhan Material Menggunakan Metode Lot-

Sizing Dengan Penerapan Metode Forecasting Time Series Dalam

Perencanaan Produksi Di Konveksi XYZ. Journal of Industrial & Quality

Engineering, Vol. 10. No. P-ISSN : 2303-2715. E-ISSN : 2622-5816.

Indiyanto , Rus, 2008. Perencanaan dan Pengendalian Produksi. Klaten. Yayasan

Humaniora.

Sidiq, Muhammad Nasir. 2022. Perencanaan dan Penentuan Jadwal Induk

Produksi di P.T. Arwina Triguna Sejahtera. Jurnal Media Teknik & Sistem

Industri , Vol. 1(2017) hal.11-25. E-ISSN:2581-0561. P-ISSN:2581-0529.

Sinulingga, Sukaria, 2009. Perencanaan dan Pengendalian Produksi. Yogyakarta.

Graha Ilmu