BAGIAN BAGIAN POKOK

SISTEM MANAJEMEN MUTU


(SMM)
dan
RENCANA MUTU KONTRAK
(RMK)
(Bagian 2)
SURAT EDARAN NOMOR:
22/SE/D/2015 TENTANG
PENYELENGGARAAN SISTEM
MANAJEMEN MUTU DI
LINGKUNGAN DIREKTORAT
JENDERAL SUMBER DAYA AIR.
MAKSUD DAN TUJUAN.
 DIMAKSUDKAN SEBAGAI PEDOMAN BAGI SELURUH
UNIT KERJA DILINGKUNGAN DIREKTORAT JENDERAL
SUMBER DAYA AIR DALAM PENERAPAN SISTEM
MANAJEMEN MUTU SEBAGAIMAN DIPERSYARATKAN
DALAM PERATURAN MENTERI PEKERJAAN UMUM NO.:
01/PRT/M/2009 TENTANG SISTEM MANJEMEN MUTU

 DITUJUKAN UNTUK MENGARAHKAN DAN


MENGENDALIKAN PENYELENGGARAKAN PEKERJAAN
KONSTRUKSI DAN NONKONSTRUKSI DI SETIAP UNIT
KERJA, UNIT PELAKSANA KEGIATAN DAN PENYEDIA JASA
DALAM PENCAPAIAN MUTU DI LINGKUNGAN
DIREKTORAT JENDERAL SUMBER DAYA AIR.
RUANG LINGKUP
1. MANUAL MUTU DIREKTORAT JENDERAL SDA

2. PROSEDUR WAJIB DAN REKAMAN TERDOKUMENTASI


 PROSEDUR PENGENDALIAN DOKUMEN
 PROSEDUR PENGENDALIAN REKAMAN
 PROSEDUR AUDIT INTERNAL
 PROSEDUR PENGENDALIAN HASIL PEKERJAAN TIDAK SESUAI
 PROSEDUR TINDAKAN KOREKTIF
 PROSEDUR TINDAKAN PENCEGAHAN

3. PETUNJUK PELAKSANAAN DAN INSTRUKSI KERJA


YAITU:
 PETUNJUK PELAKSANAAN KAJI ULANG MANAJEMEN;
 INSTRUKSI KERJA PENYUSUNAN DOKUMEN SISTEM MUTU.
RENCANA MUTU DEFINISI :

 Dokumen yang berisi prosedur dan sumber


daya yang diperlukan harus diterapkan
oleh siapa dan kapan pada suatu proyek,
produk, proses atau kontrak tertentu

 Merupakan bagian dari Sistem


Manajemen Mutu yang difokuskan untuk
memenuhi maksud Penjaminnan Mutu,
Pengendalian Mutu dan Perencanaan
Mutu
Rencana Mutu :
1. Rencana Mutu Pelaksanaan (RMP),
merupakan dokumen SMM Pelaksanaan
yang disusun oleh Kepala Satker, SNVT,
SKS, dan PPK dan Tim Swakelola dalam
rangka menjamin mutu.
2. Rencana Mutu Kontrak (RMK),
merupakan dokumen SMM yang
disusun oleh Penyedia Barang/Jasa
untuk setiap kontrak pekerjaan dalam
rangka menjamin mutu
PERAN RENCANA MUTU
RMP
DALAM PELAKSANAAN
PENGGUNA
KEGIATAN KONSTRUKSI
JASA

KONTRAK
KONTRAK

RMK

KONTRAKTOR KONSULTAN

RMK RMK
KONTRAKTOR KONSULTAN
PENGAWAS
Satuan Kerja dan Unit Pelaksana Kegiatan (Satker/PPK)

1. Menyusun dan menerapkan Rencana Mutu Pelaksanaan


Kegiatan (RMP).
2. Melakukan tinjauan pada Rencana Mutu Pelaksanaan (RMP)
apabila terjadi perubahan persyaratan pekerjaan, agar tetap
memenuhi mutu yang dipersyaratkan.
3. Melakukan pengesahan ulang apabila terjadi perubahan
RMP.
4. Mengesahkan Rencana Mutu Kontrak (RMK) Penyedia
Barang/Jasa setelah disepakati dalam rapat pra
pelaksanaan (pre construction meeting)/rapat
pendahuluan.
Satuan Kerja dan Unit Pelaksana Kegiatan
(Satker/PPK)
5. Memonitor dan mengendalikan pelaksanaan kegiatan
sesuai RMK.
6. Melakukan pembinaan dan menerapkan SMM secara
konsisten di lingkungan kerjanya.
7. Mengusulkan perubahan yang diperlukan dalam
penerapan SMM.
8. Mengusulkan penyusunan Prosedur/Petunjuk
Pelaksanaan/Instruksi Kerja kepada atasan
langsungnya.
Penyedia Barang/Jasa wajib :
1. Membuat Rencana Mutu Kontrak (RMK) sebagai penjaminan
mutu pelaksanaan kepada Unit Pelaksana Kegiatan pada rapat
pra pelaksanaan kegiatan (pre construction meeting)/rapat
pendahuluan untuk mendapat pengesahan dari Kepala Unit
Pelaksana Kegiatan.
2. Menerapkan dan mengendalikan pelaksanaan RMK secara
konsisten untuk mencapai mutu yang dipersyaratkan pada
pelaksanaan kegiatannya.
3. Melakukan tinjauan pada RMK apabila terjadi perubahan dalam
pelaksanaan pekerjaan yang meliputi
persyaratan/ketentuan/organisasi, agar tetap memenuhi mutu
yang dipersyaratkan.
4. Mengajukan usulan pengesahan ulang apabila terjadi perubahan
RMK .
1. Umum
2. Informasi Kegiatan
3. Sasaran Mutu Kegiatan
4. Persyaratan teknis dan administrasi
5. Struktur Organisasi
6. Tugas, tanggung jawab dan wewenang
7. Kebutuhan sumber daya manusia dan
sumber daya lainnya
8. Bagan Alir Pelaksanaan Kegiatan
9. Jadwal Pelaksanaan Kegiatan
10. Jadwal Keterlibatan Personil
11. Jadwal Penggunaan Prasarana dan sarana
12. Rencana & metoda verifikasi, validasi,
monitoring, evaluasi, inspeksi dan
pengujian yang diperlukan
13. Daftar Kriteria Penerimaan
14. Daftar dokumen SMM
15. Daftar Induk Rekaman
16. Lampiran.
1. Umum.
2. Informasi Kegiatan;
3. Sasaran Mutu Kegiatan
4. Persyaratan Teknis dan Administrasi
5. Struktur Organisasi
6. Tugas, tanggungjawab dan wewenang
7. Bagan alir pelaksanaan Kegiatan;
8. Jadwal pelaksanaan kegiatan
9. Jadwal Peralatan
10. Jadwal Material
11. Jadwal Personil
12. Jadwal Arus Kas.
13. Rencana dan metoda verifikasi, validasi,
monitoring, evaluasi, inspeksi dan pengujian
14. Daftar Kriteria Penerimaan .
15. Daftar Induk Dokumen
16. Daftar Induk Rekaman/Bukti Kerja
17. Lampiran.
BAB III, SASARAN MUTU KEGIATAN

Sasaran Mutu merupakan target yang terukur dan


pencapaiannya dimonitor dan dievaluasi secara
periodik (Permen PU No.04/PRT/M/2009, BAB IV,
Pasal 4.2.4 butir 3).

Sasaran Mutu dalam pekerjaan ini adalah


melaksanakan pekerjaan tersebut sesuai dengan
persyaratan yang telah ditetapkan dalam Spesifikasi
Teknik dengan tepat waktu, tepat biaya dan tepat
mutu.
BAB IV, PERSYARATAN TEKNIS DAN
ADMINISTRASI

4.1 Persyaratan Teknis


Persyaratan teknis untuk pelaksanaan pekerjaan
ini adalah Spesifikasi Teknik yang melekat pada
Kontrak. Jika terdapat ketentuan atau standar yang
menyangkut pelaksanaan pekerjaan namun tidak
disebutkan dalam Spesifikasi Teknik maka bisa
mengacu pada ketentuan atau standar yang berlaku
secara umum untuk kegiatan atau bahan yang terkait,
dengan persetujuan Direksi Pekerjaan.
4.1. PERSYARATAN TEKNIS

No.: Judul Legislasi Nomor Legislasi

Uji Kepadatan dengan Metode


1. USBR 7221
Penggantian Air
2. Test Beton
2.1 Sample Beton ASTM C172 & ASTM C42
2.2 Kuat Tekan Beton ASTM C39 & ASTM C192
2.3 Slump ASTM C143
2.4 Kadar Air ASTM C231
2.5 Berat Volume ASTM C138
3. Persyaratan Curing dg Senyawa Beton ASTMC309
4. Standar Baja Tulangan ASTM A615 Kelas 60
5. Kepadatan Timbunan USBR Earth Manual No 5525

6. Test Kepadatan Lapangan ASTM D2.216


7. Dst ….
4.2 Persyaratan Administrasi
Persyaratan Administrasi yang terkait dengan pelaksanaan
pekerjaan ini adalah sebagai berikut :
1. DIPA Tahun Anggaran 2015, DIPA TA 2016, dst
2. Spesikisasi Umum yang tercantum pada Kontrak No.
xxx
3. Peraturan Presiden No.4 tahun 2015, tentang Perubahan
Keempat atas Peraturan Presiden No.54 tahun 2010,
tentang pengadaan Barang/Jasa Pemerintah
4. Peraturan Pemerintah No.4 tahun 2015 tentang
Organisasi dan Tata Kerja Kementerian Pekerjaan Umum
dan Perumahan Rakyat
5. Undang-undang Republik Indonesia No.18 tahun 1999
tentang Jasa Konstruksi
6. Permen PU No.04/PRT/M/2009, tanggal 16 Maret 2009,
tentang Sistem Manajemen Mutu (SMM) Departemen
Pekerjaan Umum
BAB VII
BAGAN ALIR
PELAKSANAAN
KEGIATAN
BAGAN ALIR
Bagan Alir merupakan gambar atau bagan yang
memperlihatkan urutan dan hubungan antar proses
beserta instruksinya atas suatu Kegiatan.
Bagan dinyatakan dengan Simbol. Setiap simbol
menggambarkan proses. Hubungan antar proses
digambarkan dengan garis penghubung.
Dalam pembuatan Bagan Alir tidak ada patokan yang
bersifat mutlak.
Bagan Alir ini merupakan hasil pemikiran untuk
menentukan urutan melaksanakan kegiatan.
Bagan Alir yang dibuat dapat bervariasi antara satu
penyusun Bagan Alir yang satu dengan yang lainnya.
MULAI BAGAN ALIR
PELAKSANAAN KEGIATAN
PERSIAPAN

SELESAI
MOBILISASI ALAT,
BAHAN/MATERIAL,
SDM
FHO

PELAKSANAAN YA
PEKERJAAN
(TAHAP KONSTRUKSI)
CEK
TIDAK
TIDAK
CEK
PEMELIHARAAN
YA

DEMOBILISASI PHO
ALAT & SDM
MULAI
BAGAN ALIR
SPMK TERBIT
PEKERJAAN PERSIAPAN

PERSIAPAN KANTOR,
SARANA ALAT UKUR,
GAMBAR FPELAKSANAAN
KONSTRUKSI

PENDATAAN KEPELIKAN YA
LAHAN DAN BATAS
PEKERJAAN
TIDAK
CEK
TIDAK
CEK

YA PENGUKURAN DAN
PENGGAMBARAN
MULAI
BAGAN ALIR
MENETAPKAN
MC 0%
PENGECEKAN
BM YANG
ALAT
DISEPAKATI

TIDAK TIDAK
CEK CEK
YA

PENGUKURAN MC DIREKSI
0% DAN
DOKUMENTASI

PENGGAMBARAN & KONSULTAN


PERHITUNGAN PENGAWAS
VOLULME

TIDAK YA
CEK PELAKSANAA FISIK SELESAI
BAGAN ALIR
DATA
MULAI PENGUKURAN PENGAJUAN SHOP
DRAWING

PERHITUNGAN DRAFT SHOP


DATA UKUR DRAWING

TIDAK

SELESAI DIPERIKSA
TEKNIK

YA
SHOP DRAWING
DIDISTRIBUSI GAMBAR
DICETAK

TIDAK
SHOP DRAWING YA ASISTENSI
DIPERBANYAK KE DIREKSI
MULAI
BAGAN ALIR
PEKERJAAN
PEKERJAAN BENDUNG
KANTONG LUMPUR

TIDAK YA TIDAK
CEK PEKERJAAN JALAN
CEK
INSPEKSI
YA
PEKERJAAN
PEKERJAAN
RETAINING WALL
HULU
KANTOR OP
YA
TIDAK TIDAK
CEK CEK

YA
PEKERJAAN
PEKERJAAN
RETAINING WALL CEK
HILIR YA
TUBUH BENDUNG
TIDAK
MULAI
BAGAN ALIR
PEKERJAAN GALIAN
SHOP DRAWING

REQUEST / IJIN
KERJA

PENGUKURAN:
1. VOLUME SELESAI
PEKERJAAN
2. ELEVASI, PATOK, DLL Y
A
TIDAK TIDAK
CEK CEK

Y
PERSIAPAN
A
PERALATAN, AREA,
CEK PENGGALIAN
JALAN KERJA DAN Y
BUANGAN TIDAK A
MULAI BAGAN ALIR
PEKERJAAN TIMBUNAN

SHOP TRIAL TEST MATERIAL


DRAWING EMBANKMENT BORROW AREA

TIDAK TIDAK TIDAK


CEK CEK CEK
YA YA YA

REQUEST / IJIN
YA
KERJA
A
PENGUKURAN : TIDAK
1. VOLUME PEKERJAAN CEK
2. ELEVASI, PATOK, DLL

TIDAK YA PERSIAPAN PERALATAN


CEK AREA, JALAN KERJA DAN
STOCKPILE
A BAGAN ALIR
PEKERJAAN
TIMBUNAN DAN
TIMBUNAN
PEMADATAN (LANJUTAN)

TIDAK
CEK

YA

TEST LAB
Permeability, SELESAI
Density, dll

TIDAK YA
CEK DOKUMENTASI
MULAI
REQUEST/ BAGAN ALIR
IJIN KERJA
PEKERJAAN BETON

SHOP
TRIAL MIX
DRAWING

TIDAK TIDAK
CEK CEK
YA YA

REQUEST / IJIN
KERJA PEKERJAAN PAS.BEKESTING,
PEMBESIAN WATERSTP, DLL

PENGUKURAN :
1. VOLUME PEKERJAAN TIDAK TIDAK
2. ELEVASI, PATOK, DLL CEK CEK
YA
YA YA
TIDAK
CEK A
A BAGAN ALIR
PEKERJAAN BETON
(LANJUTAN)
SAMPLING
BETON

TIDAK TIDAK
CEK TEST LAB
(STRENGTH CEK
YA TEST)
YA YA

PENGECORAN
CEK
TIDAK SELESAI

YA BONGKAR
TIDAK Y
CEK BEKESTING DAN
A
CURING BETON
BAB XIII
RENCANA, METODA
VERIFIKASI, VALIDASI,
MONITORING, EVALUASI,
INSPEKSI DAN PENGUJIAN &
KRITERIA PENERIMAANNYA
8. RENCANA, METODA VERIFIKASI, VALIDASI, MONITORING,
EVALUASI, INSPEKSI DAN PENGUJIAN & KRITERIA
PENERIMAANNYA
Kriteria
No. Pemeriksaan Metode Waktu
Penerimaan
1. Mobilisasi  Melakukan pengecekan Sesuai jenis dan Setiap
Peralatan secara visual jumlah alat dalam Pengirima
daftar yang tercantum n
dalam dokumen
kontrak
2. Mobilisasi  Melakukan pengecekan Sesuai jenis dan Setiap
bahan secara visual . jumlah bahan dalam pengirima
daftar yang tercantum n
dalam dokumen
kontrak
3. Mutual  Melakukan pengecekan Hasil pengecekan Setiap
Check terhadap hasil kegiatan dapat dipertanggung pengeceka
 Melakukan pengecekan jawabkan n progres
dengan menggunakan fisik
alat ukur meteran 50m, pekerjaan
alat Waterpass,
Theodolite
Lanjutan 8. RENCANA, METODA VERIFIKASI, …

Kriteria
No. Pemeriksaan Metode Waktu
Penerimaan
4. Pengetesan  Melakukan pengetesan Hasil uji laboratorium Sebelum
Material material yang akan atau sertifikasi material
digunakan untuk material digunaka
masing2 benda uji n
5. Galian  Penggalian tanah biasa, Hasil sesuai dengan Setelah
batu lapuk, batu dengan yang disajikan dalam pelaksana
alat berat, peledakan shop drawing baik an
sesuai kebutuhan. elevasi, ukuran pekerjaan
clearing &
Grubbing
6. Timbunan  Timbunan dilakukan Hasil sesuai Pada
untuk berbagai tipe: pengujian timbunan waktu
1. Timbunan Kedap Air melaksan
2. Timbunan semi kedap akan
air pekerjaan
3. Timbunan Filter
4. Timbunan drainasi
horizontal
Lanjutan 8. RENCANA, METODA VERIFIKASI, …

Kriteria
No. Pemeriksaan Metode Waktu
Penerimaan
7. Shotcrete  Menempatkan satu lapis Terowongan Pada saat
atau lebih spesi (mortar) terproteksi dari pembuatan
beton yang dialirkan longsoran terowongan
melalui selang dan
ditembakkan dengan
kecepatan tinggi
menggunakan tekanan
udara
8. Semen  Pembelian semen curah Sesuai Pada saat
harus dilakukan spesifikasi mendatangk
penimbangan terlebih teknik an semen
dahulu, dan dengan
persetujuan direksi
9. Dokumenta  Pengambilan dokumentasi Sudut Setiap
si foto maupun video pengambilan, bagian
sebelum pekerjaan dimulai ukuran foto, pekerjaan
(0), saat pelaksanaan dan durasi video
selesai pekerjaan (100%).
9. DAFTAR KRITERIA PENERIMAAN
Pemeri
No. Kriteria Penerimaan Referensi Keterangan
ksaan
1. SP.1  Sosialisasi kepada warga SSUK ….. Proyek akan dimulai

2. SD.1  Kesepakatan SSUK …. Proyek akan dimulai


 Berita Acara Sosialisasi
 Dokumentasi
3. SP.2  MC 0% Joint 1 Bulan diawal
 Data Survey Inspection pekerjaan
SpekTek ….
4. SD.2  Shop Drawing SpekTek Harus sudah ada
…… sebelum pekerjaan
dimulai
5. SP.3  Membangun, melengkapi Spesifikasi
dan memberikan kantor Teknik
direksi dan perumahan
untuk staf Direksi selama
masa konstruksi
6. SD.3  Shop Drawing Spesifikasi
Teknik
9. DAFTAR KRITERIA PENERIMAAN
Pemeri
No. Kriteria Penerimaan Referensi Keterangan
ksaan
7. SP.4  Menyediakan dan Spek.Tek Proyek akan dimulai
memelihara fasilitas …..
kontraktor yang sudah
ditentukan
8. SD.4  Shop Drawing Spek.Tek Proyek akan dimulai
.….
9. SP.5  Memasang kelengkapan Spek.Tek
Hidromechanikal dan Sub Bab
Electrical 16.14
10. SD.5  Shop Drawing SpekTek
……
11. SP.6  Membangun akses jalan Spek.Tek …
permanen, sementara, Halaman
jembatan, gorong2 TS 11
12. SD.6  Shop Drawing Spek.Tek
……
9. DAFTAR KRITERIA PENERIMAAN
Pemeri
No. Kriteria Penerimaan Referensi Keterangan
ksaan
13. SP.7  Pengerjaan Cofferdam hulu dan Spek.Tek
hilir dilakukan pada kondisi aliran Bab.2.14,
minimum di musim kemarau. Halaman TS2-3
14. SD.7  Shop Drawing Spek.Tek .….
 Cofferdam hulu dibangun dihulu
bendungan utama didekat mulut
terowongan
15. SP.8  Pengerjaan tahapan galian dan Spek.Tek …….
timbunan Bendungan Pelana

16. SD.8  Shop Drawing SpekTek ……

17. SP.9  Pembetonan terowongan Spek.Tek Sub


didasarkan pada program Bab. 7.4
pengalihan sungai. Halaman TS 7-4
18. SD.9  Shop Drawing Spek.Tek Sub
 Beton pada Plug Terowongan Bab 7.4 TS 7-5
menggunakan sistem
pendinginan
RENCANA INSPEKSI DAN TEST

RINCIAN
JENIS Inspeksi dan Test
ITEM PENGE
DOKUMEN
PEKERJA NDALIA PERSETUJU
PENAN
No.: PERSYARATA
AN N
AN
N MUTU JENIS WAKTU KODE PENGGUNA. GGUNG
MUTU (1) (2) (3) JASA JAWAB
(4) (5)

1. Penguk Shop Inspek Vis, Kal Sbl, I,D Ya Surve


uran Drawing, si Slm, y
Spek., Tek. Ssd
4 Timbun Spek.Tek Inspek Vis., Sbl, I, W, Ya Tekni
an butir 4.1.5 si Kuantitas Slm, D k
Kedap dan 4.1.6 Ssd
Air
10 Beton Spek.Tek Inspek Visual, Sbl, I, W, Ya Tekni
K-300 Butir 5.6, si , Test Dimensi, Slm, D k
5.6.1 – 5.6.7 Curing, Ssd
Compresive,
Strength
Test

(1). TEST CAMPURAN, DIMENSI DLL; (2). SEBELUM, SELAMA, SESUDAH; (3). INSPEKSI, TEST,
MENYAKSIKAN, DOKUMENTASI; (4). YA/TIDAK; (5). PELAKSAN/QUALITY CONTROL, TEKNI
DAFTAR INDUK REKAMAN
No. Jenis Bukti Unit Masa Lokasi Penanggun
Rekama Kerja Kerja Simpan Penyimpana g Jawab
n n
ADM/BA Berita Acara Owner Periode Kantor Proyek Adkont
… Serah Terima Kontrak
Lapangan
ADM/BA Berita Acara Owner Periode Kantor Proyek Kapro
PCM … PCM Kontrak
ADM/LM Laporan Teknik Periode Kantor Proyek Teknik
,LB Mingguan, Kontrak
Bulanan
ADM/ Request for Teknik Periode Kantor Proyek Teknik
RFW Work Kontrak
ADM/ Request for Teknik Periode Kantor Proyek Teknik
RFC Checking Kontrak
ADM/JM Job Mix Teknik Periode Kantor Laboratoriu
F, JMD Formula, Job Kontrak Laboratorium m
Mix Design
JADWAL PELAKSANAAN KEGIATAN
Contoh :
JADWAL PERALATAN
Contoh :
Tahun 2012
Kondisi
No Jenis Peralatan Kapasitas Jumlah Jun Jul Agt Sept Okt Nop Ket.
(%)
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1Excavator 105 HP 90 1 bh
2Beton Molen 350 Lt 80 2 bh
3Pompa Air 16 PK 80 2 bh
4Dst
JADWAL MATERIAL

Tahun 2012
No Jenis Peralatan Kapasitas J un J ul Agt Sept Okt Nop Ket.
123412341234123412341234
1PC 2074
2Pasir Pasang 1550
3Dst
JAWAL PERSONIL

Tahun ……………
Pendidika
No. Jabatan Nama KKeterangan
n Jun Jul Ags
JADWAL ARUS KAS
Contoh :

TAHUN ………..
No. JENIS URAIAN
Jun Jul Ags Sep Okt Nop Total KETERANGAN
Penerimaan (cash in)
1 1. Uang Muka 20 %
2. Termyn 50 %
3. Termyn 30 %

Total penerimaan Jun - Okt

Pengeluaran (cash out)


2 1. Bayar Kisdam
2. Bayar galian tanah
3. Bayar timbunan tanah
4. Bayar pasang bt 1 : 4
5. Bayar Plesteran 1 : 3
6. Bayar siaran 1 : 2
7. Bayar beton K 75
8. Lain-lain

Total pengeluaran Jun - Okt


Saldo = Penerimaan -
Pengeluaran
TERIMA KASIH
(Bagian 2)
KOORDINATOR PELAKSANAAN
3. SASARAN MUTU

No Item Pekerjaan
Bobot Time Frame
(%)
2015 2016 2017 2018

I Pekerjaan Persiapan

II Pekerjaan Sementara
2.1 Saluran Pengelak
2.2 Dewatering
III Pekerjaan Tetap
3.1 Pekerjaan Tanah

3.2 Pekerjaan Pasangan Batu


3.3 Kantong Lumpur
IV Pekerjaan Pintu
4.1 Pintu Penguras Bendung

4.2 Pintu Intake Kanan