BAGIAN BAGIAN POKOK

SISTEM MANAJEMEN MUTU


(SMM)
dan
RENCANA MUTU KONTRAK
(RMK)
SURAT EDARAN NOMOR: 22/SE/D/2015
TENTANG PENYELENGGARAAN SISTEM
MANAJEMEN MUTU DI LINGKUNGAN
KEMENTERIAN PEKERJAAN UMUM &
PERUMAHAN RAKYAT
MAKSUD DAN TUJUAN.
❑DIMAKSUD SEBAGAI PEDOMAN BAGI SELURUH UNIT
KERJA DILINGKUNGAN PUPR DALAM PENERAPAN SISTEM
MANAJEMEN MUTU SEBAGAIMANA DIPERSYARATKAN
DALAM PERATURAN MENTERI PEKERJAAN UMUM NO.:
01/PRT/M/2009 TENTANG SISTEM MANJEMEN MUTU

❑DITUJUKAN UNTUK MENGARAHKAN DAN


MENGENDALIKAN PENYELENGGARAKAN PEKERJAAN
KONSTRUKSI DAN NON KONSTRUKSI DI SETIAP UNIT
KERJA, UNIT PELAKSANA KEGIATAN DAN PENYEDIA JASA
DALAM PENCAPAIAN MUTU.
RUANG LINGKUP
1. MANUAL MUTU DIREKTORAT JENDERAL SDA

2. PROSEDUR WAJIB DAN REKAMAN TERDOKUMENTASI


➢PROSEDUR PENGENDALIAN DOKUMEN
➢PROSEDUR PENGENDALIAN REKAMAN
➢PROSEDUR AUDIT INTERNAL
➢PROSEDUR PENGENDALIAN HASIL PEKERJAAN TIDAK SESUAI
➢PROSEDUR TINDAKAN KOREKTIF
➢PROSEDUR TINDAKAN PENCEGAHAN

3. PETUNJUK PELAKSANAAN DAN INSTRUKSI KERJA YAITU:


➢PETUNJUK PELAKSANAAN KAJI ULANG MANAJEMEN;
➢INSTRUKSI KERJA PENYUSUNAN DOKUMEN SISTEM MUTU.
RENCANA MUTU DEFINISI :

❑ Dokumen yang berisi prosedur dan sumber


daya yang diperlukan harus diterapkan
oleh siapa dan kapan pada suatu proyek,
produk, proses atau kontrak tertentu

❑ Merupakan bagian dari Sistem


Manajemen Mutu yang difokuskan untuk
memenuhi maksud Penjaminnan Mutu,
Pengendalian Mutu dan Perencanaan
Mutu
Rencana Mutu :
1. Rencana Mutu Pelaksanaan (RMP),
merupakan dokumen SMM Pelaksanaan
yang disusun oleh Kepala Satker, SNVT,
SKS, dan PPK dan Tim Swakelola dalam
rangka menjamin mutu.
2. Rencana Mutu Kontrak (RMK), merupakan
dokumen SMM yang disusun oleh
Penyedia Barang/Jasa untuk setiap kontrak
pekerjaan dalam rangka menjamin mutu.
PERAN RENCANA MUTU
RMP
DALAM PELAKSANAAN
PENGGUNA
KEGIATAN KONSTRUKSI
JASA

KONTRAK
KONTRAK

RMK

KONTRAKTOR KONSULTAN

RMK RMK
KONTRAKTOR KONSULTAN
PENGAWAS
Satuan Kerja dan Unit Pelaksana Kegiatan (Satker/PPK)

1. Menyusun dan menerapkan Rencana Mutu Pelaksanaan


Kegiatan (RMP).
2. Melakukan tinjauan pada Rencana Mutu Pelaksanaan (RMP)
apabila terjadi perubahan persyaratan pekerjaan, agar tetap
memenuhi mutu yang dipersyaratkan.
3. Melakukan pengesahan ulang apabila terjadi perubahan
RMP.
4. Mengesahkan Rencana Mutu Kontrak (RMK) Penyedia
Barang/Jasa setelah disepakati dalam rapat pra
pelaksanaan (pre construction meeting)/rapat
pendahuluan.
Satuan Kerja dan Unit Pelaksana Kegiatan
(Satker/PPK)
5. Memonitor dan mengendalikan pelaksanaan kegiatan
sesuai RMK.
6. Melakukan pembinaan dan menerapkan SMM secara
konsisten di lingkungan kerjanya.
7. Mengusulkan perubahan yang diperlukan dalam
penerapan SMM.
8. Mengusulkan penyusunan Prosedur/Petunjuk
Pelaksanaan/Instruksi Kerja kepada atasan
langsungnya.
Penyedia Barang/Jasa wajib :
1. Membuat Rencana Mutu Kontrak (RMK) sebagai penjaminan
mutu pelaksanaan kepada Unit Pelaksana Kegiatan pada rapat
pra pelaksanaan kegiatan (pre construction meeting)/rapat
pendahuluan untuk mendapat pengesahan dari Kepala Unit
Pelaksana Kegiatan.
2. Menerapkan dan mengendalikan pelaksanaan RMK secara
konsisten untuk mencapai mutu yang dipersyaratkan pada
pelaksanaan kegiatannya.
3. Melakukan tinjauan pada RMK apabila terjadi perubahan dalam
pelaksanaan pekerjaan yang meliputi
persyaratan/ketentuan/organisasi, agar tetap memenuhi mutu
yang dipersyaratkan.
4. Mengajukan usulan pengesahan ulang apabila terjadi perubahan
RMK .
Rencana Mutu Pelaksanaan Kegiatan (RMP) terdiri
dari 16 bab :
1. Umum
2. Informasi Kegiatan
3. Sasaran Mutu Kegiatan
4. Persyaratan teknis dan administrasi
5. Struktur Organisasi
6. Tugas, tanggung jawab dan wewenang
7. Kebutuhan sumber daya manusia dan
sumber daya lainnya
8. Bagan Alir Pelaksanaan Kegiatan
9. Jadwal Pelaksanaan Kegiatan
Rencana Mutu Pelaksanaan Kegiatan (RMP) terdiri
dari 16 bab :
10. Jadwal Keterlibatan Personil
11. Jadwal Penggunaan Prasarana dan sarana
12. Rencana & metoda verifikasi, validasi,
monitoring, evaluasi, inspeksi dan pengujian
yang diperlukan
13. Daftar Kriteria Penerimaan
14. Daftar dokumen SMM
15. Daftar Induk Rekaman
16. Lampiran.
Rencana Mutu Kontrak (RMK)
terdiri dari 17 BAB :
1. Umum.
2. Informasi Kegiatan;
3. Sasaran Mutu Kegiatan
4. Persyaratan Teknis dan Administrasi
5. Struktur Organisasi
6. Tugas, tanggungjawab dan wewenang
7. Bagan alir pelaksanaan Kegiatan;
8. Jadwal pelaksanaan kegiatan
9. Jadwal Peralatan
Rencana Mutu Kontrak
terdiri dari 17 BAB :

10. Jadwal Material


11. Jadwal Personil
12. Jadwal Arus Kas.
13. Rencana dan metoda verifikasi, validasi,
monitoring, evaluasi, inspeksi dan pengujian
14. Daftar Kriteria Penerimaan .
15. Daftar Induk Dokumen
16. Daftar Induk Rekaman/Bukti Kerja
17. Lampiran.
BAB III, SASARAN MUTU KEGIATAN

Sasaran Mutu merupakan target yang terukur dan


pencapaiannya dimonitor dan dievaluasi secara periodik
(Permen PU No.04/PRT/M/2009, BAB IV, Pasal 4.2.4
butir 3).

Sasaran Mutu dalam pekerjaan ini adalah


melaksanakan pekerjaan tersebut sesuai dengan
persyaratan yang telah ditetapkan dalam spesifikasi
teknik dengan tepat waktu, tepat biaya dan tepat mutu.
BAB IV, PERSYARATAN TEKNIS DAN ADMINISTRASI

4.1 Persyaratan Teknis


Persyaratan teknis untuk pelaksanaan pekerjaan ini
adalah Spesifikasi Teknik yang melekat pada Kontrak.
Jika terdapat ketentuan atau standar yang menyangkut
pelaksanaan pekerjaan namun tidak disebutkan dalam
Spesifikasi Teknik maka bisa mengacu pada ketentuan
atau standar yang berlaku secara umum untuk kegiatan
atau bahan yang terkait, dengan persetujuan Pemilik
Proyek, bisa melalui Konsultan Pengawas.
4.1. PERSYARATAN TEKNIS

No.: Judul Legislasi Nomor Legislasi

Uji Kepadatan dengan Metode


1. USBR 7221
Penggantian Air
2. Test Beton
2.1 Sample Beton ASTM C172 & ASTM C42
2.2 Kuat Tekan Beton ASTM C39 & ASTM C192
2.3 Slump ASTM C143
2.4 Kadar Air ASTM C231
2.5 Berat Volume ASTM C138
3. Persyaratan Curing dg Senyawa Beton ASTMC309
4. Standar Baja Tulangan ASTM A615 Kelas 60
5. Kepadatan Timbunan USBR Earth Manual No 5525

6. Test Kepadatan Lapangan ASTM D2.216


7. Dst ….
4.2 Persyaratan Administrasi
Persyaratan Administrasi yang terkait dengan pelaksanaan
pekerjaan ini adalah sebagai berikut :
1. DIPA Tahun Anggaran 2019, DIPA TA 2020, dst
2. Spesifikasi Umum yang tercantum pada Kontrak No. xxx
3. Peraturan Presiden No. 16 tahun 2018, tentang Perubahan
atas Peraturan Presiden No.54 tahun 2010, tentang
Pengadaan Barang/Jasa Pemerintah
4. Peraturan Pemerintah tentang Organisasi dan Tata Kerja
Kementerian Pekerjaan Umum dan Perumahan Rakyat
5. Undang-undang Republik Indonesia No.2 tahun 2017 tentang
Jasa Konstruksi
6. Permen PUPR, tentang Sistem Manajemen Mutu (SMM)
Kementerian PUPR
BAGAN ALIR
PELAKSANAAN KEGIATAN
BAGAN ALIR
❑Bagan Alir merupakan gambar atau bagan yang
memperlihatkan urutan dan hubungan antar proses
beserta instruksinya atas suatu Kegiatan.
❑Bagan dinyatakan dengan Simbol. Setiap simbol
menggambarkan proses. Hubungan antar proses
digambarkan dengan garis penghubung.
❑Dalam pembuatan Bagan Alir tidak ada patokan yang
bersifat mutlak.
❑Bagan Alir ini merupakan hasil pemikiran untuk
menentukan urutan melaksanakan kegiatan.
❑Bagan Alir yang dibuat dapat bervariasi antara satu
penyusun Bagan Alir yang satu dengan yang lainnya.
MULAI BAGAN ALIR
PELAKSANAAN KEGIATAN
PERSIAPAN

SELESAI
MOBILISASI ALAT,
BAHAN/MATERIAL,
SDM
FHO

PELAKSANAAN PEKERJAAN YA
(TAHAP KONSTRUKSI)
CEK
TIDAK
TIDAK
CEK
PEMELIHARAAN
YA

DEMOBILISASI ALAT PHO


& SDM
MULAI
BAGAN ALIR
SPMK TERBIT
PEKERJAAN PERSIAPAN

PERSIAPAN KANTOR,
SARANA ALAT UKUR,
GAMBAR FPELAKSANAAN
KONSTRUKSI

PENDATAAN KEPELIKAN YA
LAHAN DAN BATAS PEKERJAAN

TIDAK
CEK
TIDAK
CEK

YA PENGUKURAN DAN
PENGGAMBARAN
MULAI
BAGAN ALIR
MENETAPKAN
MC 0%
PENGECEKAN
BM YANG
ALAT
DISEPAKATI

TIDAK TIDAK
CEK CEK
YA

DIREKSI
PENGUKURAN MC 0%
DAN DOKUMENTASI

PENGGAMBARAN & KONSULTAN


PERHITUNGAN PENGAWAS
VOLUME

TIDAK YA
CEK PELAKSANAAN FISIK SELESAI
BAGAN ALIR
MULAI DATA PENGUKURAN PENGAJUAN SHOP DRAWING

PERHITUNGAN DATA DRAFT SHOP


UKUR DRAWING

TIDAK

SELESAI DIPERIKSA
TEKNIK

YA
SHOP DRAWING
DIDISTRIBUSI GAMBAR DICETAK

TIDAK
SHOP DRAWING YA ASISTENSI
DIPERBANYAK KE DIREKSI
MULAI
BAGAN ALIR
PEKERJAAN
PEKERJAAN BENDUNG
KANTONG LUMPUR

TIDAK YA TIDAK
CEK PEKERJAAN JALAN
CEK
INSPEKSI
YA
PEKERJAAN RETAINING PEKERJAAN
WALL HULU KANTOR OP
YA
TIDAK TIDAK
CEK CEK

YA
PEKERJAAN RETAINING PEKERJAAN TUBUH
WALL HILIR CEK BENDUNG
YA
TIDAK
MULAI
BAGAN ALIR
PEKERJAAN GALIAN
SHOP DRAWING

REQUEST / IJIN KERJA

PENGUKURAN: SELESAI
1. VOLUME PEKERJAAN
2. ELEVASI, PATOK, DLL
YA
TIDAK TIDAK
CEK CEK

YA
PERSIAPAN PERALATAN,
AREA, JALAN KERJA CEK PENGGALIAN
DAN BUANGAN YA
TIDAK
MULAI BAGAN ALIR
PEKERJAAN TIMBUNAN

TRIAL TEST MATERIAL


SHOP DRAWING
EMBANKMENT BORROW AREA

TIDAK TIDAK TIDAK


CEK CEK CEK
YA YA YA

REQUEST / IJIN KERJA YA


A
PENGUKURAN : TIDAK
1. VOLUME PEKERJAAN CEK
2. ELEVASI, PATOK, DLL

TIDAK YA PERSIAPAN PERALATAN AREA,


CEK JALAN KERJA DAN STOCKPILE
A BAGAN ALIR
PEKERJAAN TIMBUNAN
(LANJUTAN)
TIMBUNAN DAN
PEMADATAN

TIDAK
CEK

YA

TEST LAB
Permeability, SELESAI
Density, dll

TIDAK YA
CEK DOKUMENTASI
MULAI
REQUEST/ BAGAN ALIR
IJIN KERJA
PEKERJAAN BETON

SHOP DRAWING TRIAL MIX

TIDAK TIDAK
CEK CEK
YA YA

REQUEST / IJIN
KERJA PEKERJAAN PAS.BEKESTING,
PEMBESIAN WATERSTOP, DLL

PENGUKURAN :
1. VOLUME PEKERJAAN TIDAK TIDAK
2. ELEVASI, PATOK, DLL CEK CEK
YA
YA YA
TIDAK
CEK A
A BAGAN ALIR
PEKERJAAN BETON
(LANJUTAN)
SAMPLING
BETON

TIDAK TIDAK
CEK TEST LAB
CEK
(STRENGTH TEST)
YA
YA YA

PENGECORAN
CEK
TIDAK SELESAI

YA BONGKAR
TIDAK YA
CEK BEKESTING DAN
CURING BETON
RENCANA, METODA VERIFIKASI,
VALIDASI, MONITORING, EVALUASI,
INSPEKSI DAN PENGUJIAN &
KRITERIA PENERIMAANNYA
8. RENCANA, METODA VERIFIKASI, VALIDASI, MONITORING, EVALUASI,
INSPEKSI DAN PENGUJIAN & KRITERIA PENERIMAANNYA

No. Pemeriksaan Metode Kriteria Penerimaan Waktu

1. Mobilisasi ❖ Melakukan pengecekan Sesuai jenis dan jumlah Setiap


Peralatan secara visual alat dalam daftar yang Pengiriman
tercantum dalam
dokumen kontrak
2. Mobilisasi ❖ Melakukan pengecekan Sesuai jenis dan jumlah Setiap
bahan secara visual . bahan dalam daftar yang pengiriman
tercantum dalam
dokumen kontrak
3. Mutual Check ❖ Melakukan pengecekan Hasil pengecekan dapat Setiap
terhadap hasil kegiatan dipertanggung jawabkan pengecekan
❖ Melakukan pengecekan progres fisik
dengan menggunakan alat pekerjaan
ukur meteran 50m, alat
Waterpass, Theodolite
Lanjutan 8. RENCANA, METODA VERIFIKASI, …

No. Pemeriksaan Metode Kriteria Penerimaan Waktu

4. Pengetesan ❖ Melakukan pengetesan Hasil uji laboratorium Sebelum


Material material yang akan atau sertifikasi material material
digunakan untuk masing2 digunakan
benda uji
5. Galian ❖ Penggalian tanah biasa, batu Hasil sesuai dengan yang Setelah
lapuk, batu dengan alat disajikan dalam shop pelaksanaan
berat, peledakan sesuai drawing baik elevasi, pekerjaan
kebutuhan. ukuran clearing &
Grubbing
6. Timbunan ❖ Timbunan dilakukan untuk Hasil sesuai pengujian Pada waktu
berbagai tipe: timbunan melaksanak
1. Timbunan Kedap Air an
2. Timbunan semi kedap air pekerjaan
3. Timbunan Filter
4. Timbunan drainasi
horizontal
Lanjutan 8. RENCANA, METODA VERIFIKASI, …

Kriteria
No. Pemeriksaan Metode Waktu
Penerimaan
7. Shotcrete ❖ Menempatkan satu lapis atau Terowongan Pada saat
lebih spesi (mortar) beton yang terproteksi dari pembuatan
dialirkan melalui selang dan longsoran terowongan
ditembakkan dengan kecepatan
tinggi menggunakan tekanan
udara
8. Semen ❖ Pembelian semen curah harus Sesuai spesifikasi Pada saat
dilakukan penimbangan terlebih teknik mendatangkan
dahulu, dan dengan persetujuan semen
direksi
9. Dokumentasi ❖ Pengambilan dokumentasi foto Sudut pengambilan, Setiap bagian
maupun video sebelum ukuran foto, durasi pekerjaan
pekerjaan dimulai (0), saat video
pelaksanaan dan selesai
pekerjaan (100%).
9. DAFTAR KRITERIA PENERIMAAN
Pemeriksa
No. Kriteria Penerimaan Referensi Keterangan
an

1. SP.1 ❖ Sosialisasi kepada warga SSUK ….. Proyek akan dimulai

2. SD.1 ❖ Kesepakatan SSUK …. Proyek akan dimulai


❖ Berita Acara Sosialisasi
❖ Dokumentasi

3. SP.2 ❖ MC 0% Joint Inspection 1 Bulan diawal pekerjaan


❖ Data Survey SpekTek ….

4. SD.2 ❖ Shop Drawing SpekTek …… Harus sudah ada sebelum


pekerjaan dimulai

5. SP.3 ❖ Membangun, melengkapi dan Spesifikasi


memberikan kantor direksi dan Teknik
perumahan untuk staf Direksi selama
masa konstruksi
6. SD.3 ❖ Shop Drawing Spesifikasi
Teknik
9. DAFTAR KRITERIA PENERIMAAN
Pemeriksa
No. Kriteria Penerimaan Referensi Keterangan
an

7. SP.4 ❖ Menyediakan dan memelihara fasilitas Spek.Tek ….. Proyek akan dimulai
kontraktor yang sudah ditentukan
8. SD.4 ❖ Shop Drawing Spek.Tek .…. Proyek akan dimulai

9. SP.5 ❖ Memasang kelengkapan Spek.Tek Sub


Hidromechanikal dan Electrical Bab 16.14

10. SD.5 ❖ Shop Drawing SpekTek ……

11. SP.6 ❖ Membangun akses jalan permanen, Spek.Tek …


sementara, jembatan, gorong2 Halaman TS 11

12. SD.6 ❖ Shop Drawing Spek.Tek ……


9. DAFTAR KRITERIA PENERIMAAN
Pemeriksaa
No. Kriteria Penerimaan Referensi Keterangan
n

13. SP.7 ❖ Pengerjaan Cofferdam hulu dan hilir dilakukan Spek.Tek Bab.2.14,
pada kondisi aliran minimum di musim kemarau. Halaman TS2-3
14. SD.7 ❖ Shop Drawing Spek.Tek .….
❖ Cofferdam hulu dibangun dihulu bendungan
utama didekat mulut terowongan
15. SP.8 ❖ Pengerjaan tahapan galian dan timbunan Spek.Tek …….
Bendungan Pelana

16. SD.8 ❖ Shop Drawing SpekTek ……

17. SP.9 ❖ Pembetonan terowongan didasarkan pada Spek.Tek Sub Bab. 7.4
program pengalihan sungai. Halaman TS 7-4

18. SD.9 ❖ Shop Drawing Spek.Tek Sub Bab 7.4 TS


❖ Beton pada Plug Terowongan menggunakan 7-5
sistem pendinginan
RENCANA INSPEKSI DAN TEST

RINCIAN JENIS Inspeksi dan Test


ITEM
DOKUMEN PENGEN
PEKERJAA PERSETUJU
PENANG
No.: PERSYARATA DALIAN AN
N JENIS WAKTU KODE PENGGUNA. GUNG
N MUTU MUTU
(1) (2) (3) JASA JAWAB
(4) (5)

1. Pengukura Shop Drawing, Inspeksi Vis, Kal Sbl, Slm, I,D Ya Survey
n Spek., Tek. Ssd

4 Timbunan Spek.Tek butir Inspeksi Vis., Kuantitas Sbl, Slm, I, W, D Ya Teknik


Kedap Air 4.1.5 dan 4.1.6 Ssd

10 Beton K- Spek.Tek Butir Inspeksi , Visual, Dimensi, Sbl, Slm, I, W, D Ya Teknik


300 5.6, 5.6.1 – 5.6.7 Test Curing, Ssd
Compresive,
Strength Test

(1). TEST CAMPURAN, DIMENSI DLL; (2). SEBELUM, SELAMA, SESUDAH; (3). INSPEKSI, TEST, MENYAKSIKAN,
DOKUMENTASI; (4). YA/TIDAK; (5). PELAKSAN/QUALITY CONTROL, TEKNI
DAFTAR INDUK REKAMAN
No. Rekaman Jenis Bukti Kerja Unit Kerja Masa Simpan Lokasi Penanggung
Penyimpanan Jawab
ADM/BA … Berita Acara Serah Owner Periode Kontrak Kantor Proyek Adkont
Terima Lapangan
ADM/BA Berita Acara PCM Owner Periode Kontrak Kantor Proyek Kapro
PCM …
ADM/LM,LB Laporan Mingguan, Teknik Periode Kontrak Kantor Proyek Teknik
Bulanan
ADM/ Request for Work Teknik Periode Kontrak Kantor Proyek Teknik
RFW
ADM/ Request for Teknik Periode Kontrak Kantor Proyek Teknik
RFC Checking
ADM/JMF, Job Mix Formula, Teknik Periode Kontrak Kantor Laboratorium
JMD Job Mix Design Laboratorium
JADWAL PELAKSANAAN KEGIATAN
Contoh :

Tahun 2012 Tahun 2013


No Jenis Kegiatan Satuan Volume Bobot (%) Jun Jul Agt Sept Okt Nop Des Jan Peb Mar Apr Ket.
12341234123412341234123412341234123412341234
1Pengeringan - Ls 5
2Galian tanah m3 150 18
3Timbunan tanah dipadatkan m3 250 8
4Dst
masa pemelihara n 180 hari
JADWAL PERALATAN
Contoh :
Tahun 2012
Kondisi
No Jenis Peralatan Kapasitas Jumlah Jun Jul Agt Sept Okt Nop Ket.
(%)
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1Excavator 105 HP 90 1 bh
2Beton Molen 350 Lt 80 2 bh
3Pompa Air 16 PK 80 2 bh
4Dst
JADWAL MATERIAL

Tahun 2012
No Jenis Peralatan Kapasitas J un J ul Agt Sept Okt Nop Ket.
123412341234123412341234
1PC 2074
2Pasir Pasang 1550
3Dst
JAWAL PERSONIL

Tahun ……………
No. Jabatan Nama Pendidikan Jun Jul Ags
KKeterangan
JADWAL ARUS KAS
Contoh :

TAHUN ………..
No. JENIS URAIAN
Jun Jul Ags Sep Okt Nop Total KETERANGAN
Penerimaan (cash in)
1 1. Uang Muka 20 %
2. Termyn 50 %
3. Termyn 30 %

Total penerimaan Jun - Okt

Pengeluaran (cash out)


2 1. Bayar Kisdam
2. Bayar galian tanah
3. Bayar timbunan tanah
4. Bayar pasang bt 1 : 4
5. Bayar Plesteran 1 : 3
6. Bayar siaran 1 : 2
7. Bayar beton K 75
8. Lain-lain

Total pengeluaran Jun - Okt


Saldo = Penerimaan -
Pengeluaran
KOORDINATOR PELAKSANAAN
3. SASARAN MUTU

No Item Pekerjaan
Bobot Time Frame
(%)
2015 2016 2017 2018

I Pekerjaan Persiapan
II Pekerjaan Sementara
2.1 Saluran Pengelak
2.2 Dewatering
III Pekerjaan Tetap
3.1 Pekerjaan Tanah

3.2 Pekerjaan Pasangan Batu


3.3 Kantong Lumpur
IV Pekerjaan Pintu
4.1 Pintu Penguras Bendung

4.2 Pintu Intake Kanan