JADWAL PEKERJAAN

INSTALASI PENGOLAHAN AIR LIMBAH


RUMAH SAKIT UNISMU KOTA PALU

No Uraian Pelaksanaan Pekerjaan Minggu - I Minggu - II Minggu - III Minggu - IV Minggu - V Minggu - VI Minggu -VII Minggu - VIII Minggu - IX Minggu - X Minggu - XI Minggu -XII

I PEKERJAAN SIPIL
1 Galian dan pasang pipa :
- Panjang pemipaan 200-250 meter
2 Galian dan pasang tabung pre treatment
-1 unit oil & fat trap
-1 unit antyfoam
-1 unti screen
-4 unit bio tank
-2 unit collecting tank
II PEKERJAAN PABRIKASI
1 Pembuatan tabung IPAL fiberglass :
-2 unit AnBIO tank
-1 unit ArBIO tank
-1 unit Clarifier tank
-2 unit sirkular filter
-3 unit bak kontrol monitoring
2 Kirim tabung dan peralatan IPAL
3 Pasang dan instalasi tabung IPAL :
-4 unit tabung IPAL : AnBIO-ArBIO-Clarifier
-2 unit sirkular filter
-3 unit bak kontrol monitoring
-2 unit pompa air limbah (submersible)
-1 unit pompa aerator inevn
-1 unit flowmeter
-1 unit panel operating
4 Uji fungsi peralatan IPAL

Keterangan : Surabaya, 2021


* Jadwal pekerjaan/time schedule diatas dapat berubah jika terjadi kondisi bencana alam. CV. KURMA JAYA
* Terutama pada faktor perubahan cuaca/alam yang mendadak (force majeur).

Djafar
Direktur