FINAL REPORT
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
TABLE OF CONTENTS
RINGKASAN EKSEKUTIF .......................................................................................................................... 1
1 PENGANTAR ..................................................................................................................................... 9
1.1 Deskripsi Proyek ....................................................................................................................... 9
1.2 Lokasi Proyek ........................................................................................................................... 9
1.3 Iklim ........................................................................................................................................ 11
1.4 Keadaan Sosial Masyarakat ................................................................................................... 11
1.5 Kepemilikan Kontrak Karya (KK) ............................................................................................ 11
1.6 Penggunaan Lahan ................................................................................................................ 12
1.7 Studi Sebelumnya dan Saat Ini .............................................................................................. 13
2 GEOLOGY REGIONAL ................................................................................................................... 15
2.1 Geologi dan Mineralisasi ........................................................................................................ 15
2.1.1 Deposit Awak Mas .............................................................................................................. 15
2.1.2 Deposit Salu Bulo ............................................................................................................... 15
3 ESTIMASI SUMBER DAYA MINERAL ........................................................................................... 17
3.1 Pengeboran dan Pengambilan Sampel .................................................................................. 17
3.2 Verifikasi Data......................................................................................................................... 17
3.3 Estimasi Sumber Daya Mineral .............................................................................................. 18
3.3.1 Estimasi Sumber Daya Mineral Awak Mas ........................................................................ 18
3.3.2 Estimasi Sumber Daya Mineral Salu Bulo .......................................................................... 18
3.3.3 Estimasi Sumber Daya Mineral Proyek Awak Mas ............................................................ 19
4 GEOTEKNIK DAN HIDROGEOLOGI.............................................................................................. 20
4.1 Pendahuluan........................................................................................................................... 20
4.2 Data Tersedia ......................................................................................................................... 20
4.3 Hasil Pekerjaan Geoteknik ..................................................................................................... 22
4.3.1 TSF Detailed Design - Factual Geotechnical Report (Dokumen 1) ................................... 22
4.3.1.1 Latar Belakang - Tes Geoteknik Sebelumnya ................................................................ 22
4.3.1.2 Ringkasan Pekerjaan Lapangan .................................................................................... 22
4.3.2 TSF Detailed Design - Geotechnical Interpretive Report (Dokumen 2) ............................. 22
4.3.2.1 Pengenalan..................................................................................................................... 22
4.3.2.2 Latar Belakang................................................................................................................ 22
4.3.2.3 Parameter Desain Geoteknik ......................................................................................... 23
4.3.3 Infrastructure - Geotechnical, Hydrology, and Civil Design Services Awak Mas FEED
(Dokumen 3) ..................................................................................................................................... 23
4.3.3.1 Pengenalan..................................................................................................................... 23
4.3.3.2 Lingkup Pekerjaan .......................................................................................................... 23
4.3.3.3 Informasi Terdahulu ........................................................................................................ 24
4.3.3.4 Penyelidikan Saat Ini ...................................................................................................... 24
4.3.3.5 Ringkasan Kegiatan Lapangan ...................................................................................... 24
4.3.4 Desain Detail TSF (Dokumen 4) ......................................................................................... 25
4.3.4.1 Pendahuluan................................................................................................................... 25
4.3.4.2 Ringkasan ....................................................................................................................... 25
4.3.5 Tinjauan Geoteknik Desain Pit Awak Mas dengan Data Investigasi Tambahan (Dokumen
5) 26
4.3.5.1 Hidrogeologi.................................................................................................................... 26
4.3.6 Pembaruan Perencanaan dan Desain Tambang Modifikasi Desain Geoteknik: Tempat
Pembuangan Batuan Limbah Awak Mas Utara dan Salu Bulo (Dokumen 6).................................. 28
4.4 Ringkasan dan Kesimpulan .................................................................................................... 31
P:\66021_M\66021_M_J1088_V3.docx
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
5 PENAMBANGAN ............................................................................................................................. 33
5.1 Laporan Area Estimasi Cadangan Bijih AMC ......................................................................... 33
5.1.1 Optimisasi Pit ...................................................................................................................... 33
5.1.1.1 Dilusi dan Kehilangan Penambangan (Ore Loss) .......................................................... 34
5.1.1.2 Parameter Optimisasi Pit ................................................................................................ 34
5.1.1.3 Hasil Optimisasi Pit ......................................................................................................... 35
5.1.2 Desain Pit ........................................................................................................................... 37
5.1.2.1 Awak Mas ....................................................................................................................... 37
5.1.2.2 Salu Bulo ........................................................................................................................ 38
5.1.2.3 Total Awak Mas dan Salu Bulo ....................................................................................... 39
5.1.3 Jadwal Penambangan ........................................................................................................ 42
5.2 Ulasan dan Komentar Mining One ......................................................................................... 46
5.2.1 Model Sumber Daya ........................................................................................................... 46
5.2.2 Biaya Penambangan .......................................................................................................... 47
5.2.3 Kadar Batas ........................................................................................................................ 47
5.2.4 Geoteknik ............................................................................................................................ 48
5.2.5 Optimisasi Pit ...................................................................................................................... 48
5.2.6 Metode Penambangan ....................................................................................................... 48
5.2.7 Pemilihan Peralatan Pertambangan ................................................................................... 48
5.2.8 Desain Penambangan ........................................................................................................ 49
5.2.9 Jadwal Penambangan ........................................................................................................ 49
5.2.10 Waste Dump ................................................................................................................... 49
5.2.11 Modal Biaya Penambangan ........................................................................................... 49
5.2.12 Kesimpulan Kajian Mining One ...................................................................................... 50
6 PABRIK PENGOLAHAN BIJIH ....................................................................................................... 51
6.1 Desain Pengolahan ................................................................................................................ 51
6.2 Recovery ................................................................................................................................. 53
6.3 Throughput ............................................................................................................................. 55
6.4 Biaya Operasi ......................................................................................................................... 56
6.5 Biaya Modal ............................................................................................................................ 57
6.6 Kesimpulan ............................................................................................................................. 58
7 INFRASTRUKTUR PENDUKUNG DAN FASILITAS NON-PENGOLAHAN .................................. 60
7.1 Infrastruktur Proyek ................................................................................................................ 60
7.1.1 Jalan Untuk Akses dan Logistik.......................................................................................... 61
7.1.2 Quarry ................................................................................................................................. 62
7.1.3 Listrik - Sementara, Konstruksi dan Operasi ...................................................................... 62
7.1.4 Sistem Komunikasi ............................................................................................................. 63
7.1.5 Sumber, Pengolahan dan Distribusi Air ............................................................................. 63
7.1.6 Pengolahan Limbah ............................................................................................................ 63
7.1.7 Pengendalian Debu ............................................................................................................ 63
7.1.8 Area Pencucian .................................................................................................................. 64
7.1.9 Kolam Sedimen .................................................................................................................. 64
7.1.10 Sistem Pemadam Kebakaran ......................................................................................... 64
7.2 Fasilitas Non-Pengolahan ...................................................................................................... 65
7.2.1 Mess ................................................................................................................................... 65
7.2.2 Fasilitas Kantor Utama Masmindo...................................................................................... 65
7.2.3 Fasilitas Bengkel dan Gudang............................................................................................ 65
7.2.4 Fasilitas Laboratorium Metalurgi ........................................................................................ 65
7.2.4.1 Fasilitas Laboratorium Metalurgi Tetap .......................................................................... 65
P:\66021_M\66021_M_J1088_V3.docx
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
INDEX TABLE
Table A Ringkasan Sumber Daya Mineral 2021 – Awak Mas, Salu Bulo and Tarra ....................... 2
Table B Estimasi Cadangan Bijih 30 Juni 2021 ......................................................................................... 8
Table 1.1 Ijin-Ijin Proyek Utama yang telah Diterbitkan .........................................................................12
Table 3.1 Ringkasan Sumberdaya Mineral 2021 – Awak Mas, Salu Bulo and Tarra ........................19
Table 4.1 Data Geoteknik yang Disediakan .............................................................................................21
Table 4.2 Investigasi Geoteknik – Lingkup Kerja (dari Dokumen 3) ...................................................24
Table 4.3 Tingkatan Upaya Geotecknik berdasarkan Tahapan Proyek (Guidelines for Open Pit
Slope Design, CSIRO 2008)....................................................................................................................32
Table 5.1 Parameter Optimisasi Pit ...........................................................................................................35
Table 5.2 Hasil Optimasi Untuk Awak Mas Berdasarkan Kategori Sumber Daya Terukur Dan
Tertunjuk, Dijalankan 6. Lubang Terpilih Dan Lubang Optimal Disorot Optimum ......................36
Table 5.3 Hasil Optimasi Untuk Salu Bulo Berdasarkan Kategori Sumber Daya Terukur Dan
Tertunjuk Jalankan 4. Lubang Yang Dipilih Disorot ..........................................................................37
Table 5.4 Inventarisasi Desain Pit Awak Mas Dibandingkan Dengan Pit Shells ...............................38
Table 5.5 Inventarisasi Desain Pit Salu Bulo Dibandingkan Dengan Pit Shells ................................39
Table 5.6 Inventaris Penambangan LOM..................................................................................................40
Table 5.7 Metrik Jadwal LOM......................................................................................................................46
Table 6.1 Parameter Kominusi ...................................................................................................................55
Table 6.2 Detil Biaya Reagen and Bahan Habis Pakai ...........................................................................57
Table 6.3 Rincian Biaya Modal ...................................................................................................................58
Table 8.1 Kapasitas Desain dan Laju Pengisian .....................................................................................73
Table 10.1 Ringkasan Biaya Modal, Operasi, dan Penerimaan selama Umur Tambang ...................89
Table 11.1 Estimasi Cadangan Bijih 30 Juni 2021 ....................................................................................91
INDEX GAMBAR
Gambar 1.1 Lokasi Awak Mas Gold Project, Sulawesi Selatan, Indonesia ........................................10
Gambar 1.2 Akses Lokasi Dan Hubungan Dengan Infrastruktur Daerah ...........................................10
Gambar 4.1 Lembah Awak Mas Utara Dilihat Dari Camp Masjid Dan Tempat Penyimpanan Core
(Dari Dokumen 6) .....................................................................................................................................29
Gambar 5.1 Desain Pit Awak Mas ..............................................................................................................38
Gambar 5.2 Desain Pit Salu Bulo ...............................................................................................................39
Gambar 5.3 Desain Waste dump Awak Mas ............................................................................................41
Gambar 5.4 Desain Waste Dump Salu Bulo .............................................................................................41
Gambar 5.5 Tata Letak Lokasi Site Penambangan .................................................................................42
Gambar 5.6 Ton Dan Kadar Yang Ditambang ..........................................................................................43
Gambar 5.7 Closing Stockpile Balance ....................................................................................................44
Gambar 5.8 Ore Tonnes And Grade Processed ......................................................................................44
Gambar 5.9 Bahan Ditambang Berdasarkan Tahap Penambangan ....................................................45
Gambar 5.10 Bijih Ditambang dan Diproses setiap Tahun .....................................................................45
Gambar 6.1 Diagram Pengolahan ..............................................................................................................52
Gambar 6.2 Ringkasan Tes yang Sudah Dilakukan ...............................................................................54
Gambar 6.3 Biaya Operasi DFS ..................................................................................................................57
P:\66021_M\66021_M_J1088_V3.docx
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
LAMPIRAN
A. Kode KCMI, Tabel 1
P:\66021_M\66021_M_J1088_V3.docx
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
RINGKASAN EKSEKUTIF
Latar Belakang
Proyek Emas Awak Mas (“Proyek”) terletak di Kabupaten Luwu Provinsi Sulawesi Selatan,
Indonesia. Proyek ini 100% dimiliki oleh PT Masmindo Dwi Area (“Masmindo”), anak perusahaan
yang saham mayoritasnya dimiliki oleh Nusantara Resources Limited (“Nusantara”), melalui
Kontrak Karya (“KK”) Generasi ke-7 dengan Pemerintah Indonesia Pada tahun 2017, Nusantara
menjadi pemilik Proyek dengan mengakuisisi One Asia Resources melalui Initial Public Offering
(“IPO”) di Bursa Saham Australia (“ASX”) dengan kode saham ASX: NUS. KK baru-baru ini telah
diamandemen dengan kesepakatan bersama untuk diselaraskan dengan undang-undang
terbaru. Kontrak Karya memungkinkan untuk masa konstruksi 2 tahun ditambah opsi
perpanjangan 1 tahun dan masa operasi 30 tahun.
Nusantara telah melakukan pengeboran definisi sumber daya mineral lebih lanjut, evaluasi
metalurgi, studi pertambangan untuk mendukung penyelesaian Definitive Feasbility Study
(“DFS”) / Front End Engineering Design (“FEED”) untuk Proyek Awak Mas. DFS bersama dengan
informasi terbaru lainnya, termasuk FEED yang baru saja diselesaikan merupakan dasar untuk
pelaporan Estimasi Cadangan Bijih sesuai dengan Kode Komite Cadangan Mineral Indonesia
(“KCMI”). PT Mining One Indonesia (“Mining One”) ditugaskan untuk mempersiapkan dan
menandatangani Laporan Cadangan Bijih KCMI ini dengan menggunakan informasi dan studi
yang dilakukan hingga saat ini. Peninjauan terhadap semua faktor pengubah (modifying factors)
yang memperhitungkan estimasi Estimasi Cadangan Bijih dilakukan oleh Mining One dan
diringkas dalam laporan ini sebagai Laporan Estimasi Cadangan Bijih KCMI untuk Proyek Awak
Mas. Dasar dari pelaporan KCMI ini adalah verifikasi yang dilakukan terhadap estimasi Cadangan
Bijih yang dilakukan oleh AMC Pty Ltd (“AMC”) pada awal tahun 2021, yang mengacu kepada
the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves
(JORC Code, 2012). Laporan ini adalah laporan Cadangan Bijih KCMI perdana untuk Proyek
Emas Awak Mas.
P:\ 66021_M\66021_M_J1088_V3.docx 1
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
menggunakan perangkat lunak Whittle, dengan parameter biaya lengkap dan harga emas dasar
1.450 USD/oz untuk Awak Mas dan 1.400 USD/oz untuk Salu Bulo.
Table A Ringkasan Sumber Daya Mineral 2021 – Awak Mas, Salu Bulo and Tarra
Rencana Penambangan
Mining One telah meninjau bagian Penambangan dari Estimasi Cadangan Bijih 2021 untuk PT
Masmindo yang diselesaikan oleh AMC. AMC telah ditugaskan oleh Masmindo untuk
menghasilkan Perhitungan Cadangan Bijih 2021 untuk Proyek Awak Mas yang dilaporkan
berdasarkan kode JORC. AMC juga menghasilkan bagian penambangan dari pembaruan DFS
2018 dan pelaporan Cadangan Bijih JORC di tahun 2020.
P:\ 66021_M\66021_M_J1088_V3.docx 2
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Proses optimisasi pit dijalankan menggunakan perangkat lunak Geovia Whittle berdasarkan
masukan seperti berikut ini:
➢ Faktor Dilusi dan Kehilangan Bijih saat penambangan diestimasi berdasarkan blok model
yang sudah diregularisasi.
➢ Optimisasi pit hanya berdasarkan untuk Sumber Daya Mineral Terukur dan Tertunjuk saja.
Sumber Daya Mineral Tereka diperlakukan sebagai waste dalam proses optimasi pit.
➢ Biaya penambangan untik optimisasi diestimasi dari perhitungan prinsipal pertama
berdasarkan DFS dan Desain Pit Cadangan sebelumnya.
➢ Kadar batas yang digunakan adalah 0,5 g/t Au.
➢ Sudut kemiringan dinding dan parameter geoteknik ini telah digunakan dalam optimasi Pit.
Rekomendasi lereng pit juga telah memperhitungkan masukan dari studi Hidrogeologi.
Input parameter yang digunakan untuk proses optimasi pit konsisten dan sesuai dengan jenis
operasi serupa di Indonesia. Perbandingan ini diperoleh melalui perbandingan langsung dengan
informasi dari tambang lain berdasarkan pengalaman Mining One.
Optimasi shell dipilih berdasarkan penyesuaian Proyek dengan strategi perusahaan. Di Awak
Mas, shell yang dipilih sebagai dasar desain lebih kecil dari optimasi shells yang dihasilkan pada
harga emas dasar dan didasarkan pada faktor pendapatan 0,92 (shell 27). Salu Bulo adalah
deposit yang lebih kecil dan shell yang sesuai dengan faktor pendapatan 1,0 dipilih sebagai dasar
desain untuk mengembangkan dasar desain pit yang praktis.
Desain pit Awak Mas dibagi menjadi empat tahap: Starter pit (AM1), Ridge cutback (AM2),
Southern Extension (AM3) dan Western Extension dibagi dalam dua tahap: Starter Pit (SB2) dan
Main Pit (SB1). Perbandingan tonase dan kadar emas antara pit shell hasil optimasi pit yang
dipilih dan desain yang dibuat dilakukan dan perbedaannya dianggap masih dalam batas
toleransi dan tidak akan mengubah nilai ekonomis pit secara signifikan atau membuat NPV
menjadi negatif. Inventaris penambangan sebesar 36,2 juta t bijih memiliki nilai Life of Mine (LOM)
stripping ratio sebesar 5,2:1. Inventaris bijih ini termasuk 3,2 juta t Sumber Daya Mineral Tereka
(9% dari total).
Waste dump diposisikan untuk meminimalkan risiko sterilisasi sumber daya potensial dan
perluasan pit, untuk mencapai stabilitas geoteknik dan untuk meminimalkan jarak angkut.
Tata letak site secara keseluruhan disajikan pada Gambar A. Tata letak tersebut mencakup lokasi
untuk infrastruktur pemrosesan, penyimpanan tailing, pembuangan limbah, stockpile untuk bijih
marginal, kadar rendah dan tinggi, penyimpanan tanah lapisan atas, bengkel tambang, fasilitas
bahan peledak dan majalah serta jalan angkut.
P:\ 66021_M\66021_M_J1088_V3.docx 3
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 4
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 5
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 6
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 7
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Semua biaya lain yang digunakan dalam Penilaian Ekonomis konsisten dengan modal dan biaya
operasional yang telah dikembangkan melalui proses DFS dan pembaruan studi lainnya hingga
saat ini.
Studi yang dilakukan dan laporan-laporan yang disediakan untuk Mining One menguraikan
proses dan informasi yang diperlukan untuk mengestimasi baik biaya operasi dan modal. Mining
One telah meninjau dokumen-dokumen yang disediakan termasuk informasi yang terkandung
dalam laporan. Laporan dilakukan pada tingkat Studi Kelayakan (DFS) yang dianggap memiliki
rincian yang cukup detil untuk pelaporan Cadangan Bijih menurut kode KCMI. Asumsi yang
digunakan cukup logis dan sesuai dengan standar yang dipakai di industri pertambangan. Mining
One menemukan tidak ada kesalahan fatal dalam proses estimasi biaya dan evaluasi ekonomi
Proyek yang telah dilakukan. Karena itu, Estimasi Cadangan Bijih yang dilaporkan dianggap valid
dan dapat dilaporkan sesuai dengan Kode KCMI.
Site Klasifikasi Tonnes (Juta Tonnes) Kadar Emas (g/t) Kandungan Emas (juta oz)
Terbukti 0 0 0
Awak Mas
Terkira 31,0 1,33 1,33
Terbukti 0,6 1,92 0,04
Salu Bulo
Terkira 1,4 1,93 0,09
Terbukti 0,6 1,92 0,04
Total Terkira 32,4 1,36 1,42
Total 33,0 1,37 1,45
Catatan: Kadar batas 0.5 g/t; kesalahan pembulatan mungkin terjadi
P:\ 66021_M\66021_M_J1088_V3.docx 8
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
1 PENGANTAR
P:\ 66021_M\66021_M_J1088_V3.docx 9
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Gambar 1.1 Lokasi Awak Mas Gold Project, Sulawesi Selatan, Indonesia
1.3 Iklim
Keadaan iklim di lokasi proyek sesuai dengan letak dan posisi di khatulistiwa pada ketinggian 900
m sampai dengan 1.400 m di atas permukaan laut rata-rata:
➢ Suhu maksimum berkisar antara 25˚C sampai 27˚C, dan suhu minimum 18˚C sampai 20˚C;
➢ Kelembaban tertinggi relatif terjadi pada bulan Mei (~98%) dan terendah pada bulan
September (~88%); dan
➢ Curah hujan rata-rata tahunan 3.000 mm dengan curah hujan bulanan tertinggi, 490 mm,
terjadi pada bulan April. Periode curah hujan yang lebih tinggi adalah Maret hingga April dan
November hingga Desember. Agustus hingga September merupakan periode curah hujan
rendah dengan rata-rata bulanan 120 mm.
P:\ 66021_M\66021_M_J1088_V3.docx 11
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Pada tahun 2020, Perusahaan telah menyerahkan dokumen utama yang diperlukan untuk
kepatuhan lisensi dan persyaratan impor yang diperlukan untuk pelaksanaan Proyek Emas Awak
Mas. Ijin yang diperlukan untuk kegiatan konstruksi tertentu tertentu seperti Fasilitas
Penyimpanan Tailing (“TSF”) sedang berlangsung. Rencana Reklamasi dan Penutupan
Tambang 5 Tahun telah disusun dan diserahkan kepada pemerintah pada Maret 2021.
P:\ 66021_M\66021_M_J1088_V3.docx 12
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Menurut hukum Indonesia, kepemilikan hak permukaan, kepemilikan tanah, tidak memberikan
kepemilikan mineral di dalam tanah dan juga tidak secara otomatis memberikan izin kepada
pemilik hak permukaan untuk melakukan kegiatan penambangan.
Sebelum konstruksi, Masmindo akan membebaskan lahan untuk pengembangan area Proyek.
Sekitar 1.409 ha tanah yang terdiri dari 477 plot perlu dibebaskan melalui program kompensasi
tanah. Survei tanah akan dilakukan sebelum dimulainya program kompensasi tanah. Sejumlah
kuburan (sekitar 21) dan rumah tangga (sekitar 36) ada di area Proyek dan akan direlokasi.
Kerangka waktu yang diperkirakan untuk program kompensasi tanah adalah 4-6 bulan dengan
mengasumsikan pendanaan untuk program tersebut telah tersedia.
P:\ 66021_M\66021_M_J1088_V3.docx 13
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
ke Sumber Daya Mineral Tertunjuk dan untuk alasan ini tidak masuk dalam studi DFS. DFS ini
telah mengkaji aspek finansial dan non finansial dari Awak Mas Gold.
Konsultan independen yang telah melakukan studi DFS adalah sebagai berikut:
➢ Cube Consulting — Estimasi Sumberdaya Mineral;
➢ AMC Consultants — Cadangan Bijih, optimalisasi pit dan perencanaan tambang, geoteknik
pertambangan;
➢ Minnovo — Pengolahan Metalurgi dan Mineral;
➢ Golder Associates (PT Geotechnical and Environmental Services Indonesia) — Tailing
Storage, geoteknik infrastruktur dan studi hidrologi;
➢ PT Resindo — Konsultan teknik dan utama;
➢ PT Lorax Indonesia — Komponen lingkungan dan sosial;
➢ Layanan Penjaga Independen Sdn. Bhd — Akses dan Keamanan Situs; dan
➢ Modal dan biaya operasional — Konsultan AMC, Minnovo, dan Resindo, dengan biaya
penambangan diverifikasi dengan membandingkan dengan informasi yang diberikan oleh
kontraktor penambangan spesialis.
DFS bersama dengan informasi terbaru lainnya, termasuk FEED yang baru saja diselesaikan
merupakan dasar untuk pelaporan Estimasi Cadangan Bijih sesuai dengan Kode KCMI. PT
Mining One Indonesia (“Mining One”) ditugaskan untuk mempersiapkan dan menandatangani
Laporan Cadangan Bijih KCMI ini dengan menggunakan informasi dan studi yang dilakukan
hingga saat ini. Peninjauan terhadap semua faktor pengubah (modifying factors) yang
memperhitungkan estimasi Estimasi Cadangan Bijih dilakukan oleh Mining One dan diringkas
dalam laporan ini sebagai Laporan Estimasi Cadangan Bijih KCMI untuk Proyek Awak Mas.
Laporan ini adalah laporan Cadangan Bijih KCMI perdana untuk Proyek Emas Awak Mas.
P:\ 66021_M\66021_M_J1088_V3.docx 14
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
2 GEOLOGY REGIONAL
P:\ 66021_M\66021_M_J1088_V3.docx 15
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Gaya mineralisasi di Salu Bulo dianggap analog dengan deposit Awak Mas, tetapi dengan kontrol
struktural sub-vertikal yang lebih dominan. Kedua endapan tersebut secara struktural terletak di
dalam batulempung berfoliasi dan batupasir di atas sekis berbatang kuat dari urutan ruang bawah
tanah. Gaya mineralisasi di Salu Bulo paling mirip dengan di Tanjung/Rante yaitu daerah dengan
struktur sub-vertikal dominan. Mineralisasi yang diinangi secara struktural sub-vertikal sangat
dominan di bagian selatan Biwa. Di bagian utara, struktur sub-vertikal melintasi zona breksiasi
dengan cekungan dangkal yang sesuai dengan perlapisan dan foliasi lokal.
Domain mineralisasi berorientasi utara-selatan, memiliki panjang strike gabungan keseluruhan
sekitar 800 m, kemiringan curam ke timur dan sub-vertikal. Zona mineralisasi yang dimodelkan
secara individu memiliki panjang strike antara 150 m sampai 500 m. Zona mineralisasi sub-
vertikal dapat bervariasi dalam ketebalan dari 1,5 m sampai 20 m tetapi lebih umum antara 3 m
sampai 10 m ketebalan. Zona mineralisasi yang lebih luas dan dangkal bervariasi dalam
ketebalan rata-rata dari 20 m hingga 60 m. Mineralisasi meluas dari permukaan hingga 200 m di
bawah permukaan dan puncak mineralisasi ditutup oleh selubung coluvium.
Sistem Ladder stockwork vein di Salu Bulo sebanding dengan yang ada di deposit Awak Mas,
yang menunjukkan orientasi mineralisasi yang serupa, dan kontinuitas kadar skala pendek pada
umumnya kurang dari jarak lubang bor (15 m hingga 50 m pusat kerah bor). Struktur breksi urat
kuarsa yang termineralisasi di Salu Bulo memiliki kontrol struktur sub-vertikal yang lebih dominan.
Zona mineralisasi dapat dengan mudah diidentifikasi secara visual dengan adanya albitisasi-
silisifikasi yang kuat, kalsifikasi dan antara 1-5% pirit yang menentukan zona berwarna pucat atau
memutih di inti.
Mineralisasi emas multi-fase dicirikan oleh breksi giling dan kresek, pengisi kuarsa vuggy, dan
urat kuarsa stockwork dengan struktur pengumpan sub-vertikal yang berbeda. Ada hubungan
spasial yang erat antara mineralisasi emas dan pirit yang berada di dalam urat kuarsa sub-
vertikal, breksi dan zona stockwork.
Mineralogi dan deformasi getas menunjukkan mineralisasi emas telah terbentuk pada tingkat
epitermal yang lebih rendah dari pengoksidasi, cairan hidrotermal salin dalam kondisi tidak
mendidih.
P:\ 66021_M\66021_M_J1088_V3.docx 16
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
reproduktifitas pengujian. Kunjungan tindak lanjut pada bulan September 2017 dilakukan untuk
meninjau dan memeriksa pengeboran Nusantara yang sedang berlangsung.
Analisis QAQC telah mengidentifikasi kesalahan presisi yang terkait dengan data uji historis dan
Nusantara, tetapi ini tidak dianggap material untuk estimasi Sumber Daya Mineral. Dalam hal ini,
Sumber Daya Mineral telah diklasifikasikan ke tingkat kepercayaan Terindikasi dan Terkira yang
cukup mencerminkan ketidakpastian yang terkait dengan integritas data informasi.
Ketepatan dan akurasi dari total dataset uji primer untuk Awak Mas dan Salu Bulo adalah standar
yang dapat diterima, tidak bias dan mewakili mineralisasi emas yang telah dibor. Kebenaran data
assay primer telah ditetapkan ke tingkat yang sesuai untuk tujuan estimasi Sumberdaya Mineral
P:\ 66021_M\66021_M_J1088_V3.docx 18
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Catatan:
1. Dilaporkan pada 0,5g/t Au cut-off dalam pit shell Sumber Daya Mineral US$1.600 ("am_run_c_shell_39_1600_usd1450
_2020_topo.dtm") untuk deposit Awak Mas.
2. Dilaporkan pada 0,5g/t Au cut-off dalam pit shell Sumber Daya Mineral ("sb5_ps38_rf114_$1600_v2.dxf") untuk deposit
Salu Bulo.
3. Kadar bawah (Cut-off grade) ditentukan dengan menggunakan harga emas dasar sebesar US$1450/oz (Awak Mas) dan
US$1,400 (Salu Bulo), perolehan metalurgi yang didukung oleh pengujian dan berdasarkan semua material yang diproses
melalui flowsheet Whole of Ore CIL.
4. Sumber Daya Mineral bukan Cadangan Bijih dan tidak menunjukkan kelayakan ekonomi.
5. Semua tonase, kadar dan ounces telah dibulatkan dan perbedaan kecil dalam total mungkin terjadi.
P:\ 66021_M\66021_M_J1088_V3.docx 19
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
4.1 Pendahuluan
Mining One telah menyelesaikan kajian atas aspek geoteknik dan hidrogeologi yang dilakukan
oleh konsultan sebelumnya untuk tambang terbuka Awak Mas dan infrastruktur terkait.
Infrastruktur terkait termasuk tempat pembuangan limbah yang diusulkan, fasilitas penyimpanan
tailing (“TSF”) dan berbagai infrastruktur permukaan yang terkait dengan pengolahan mineral.
Peninjauan dilakukan oleh Kevin Dugan, Principal Geotechnical Engineer dari Mining One.
Tujuan utama dari tinjauan geoteknik adalah untuk mengkonfirmasi bahwa pekerjaan geoteknik
sampai saat ini minimum telah berada pada tingkat Pra-Kelayakan (PFS) atau lebih tinggi. Hal
tersebut merupakan persyaratan untuk pelaporan Estimasi Cadangan Bijih berdasarkan kode
KCMI. Tinjauan geoteknik hanya berbasis desktop yaitu tidak ada kunjungan lapangan yang
dilakukan.
Tinjauan geoteknik juga dilakukan pada tingkat tinggi, mengingat ruang lingkupnya, dan bukan
tinjauan teknis yang terperinci.
P:\ 66021_M\66021_M_J1088_V3.docx 20
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Tipe
Judul Dialamat- No. Hala-
No. Doku- Tanggal Penulis Perusahaan
Dokumen kan Ke Dokumen man
men
TSF Detailed
754-
Design 26 Feb Coffey PT
Paul PERGE226
1 Factual PDF Geotechnics Masmindo 2429
2021 Petropulos 862-RD
Geotechnical Pty Ltd Dwi Area
Rev 0
Report
TSF Detailed
Coffey 754-
Design 26 Feb PT
Paul Services PERGE226
2 Geotechnical PDF Masmindo 122
2021 Petropulos Australia Pty 862-RE
Interpretive Dwi Area
Ltd Rev 0
Report
Geotechnical,
Hydrology, Indah Fivi
and Civil 05 Apr Kristianti, PT. 208712008
Golder
3 Design PDF Petrosea -GEO-018- 710
2021 Philip R. Associates
Services Tbk. R-Rev 1
Awak Mas Woodmansey
FEED
Geotechnical
Review of the
Awak Mas Pit AMC PT AMC22002
18 May
5 Designs with PDF Asoka Herath Consultants Masmindo 9/ 197
Additional 2021 Pty Ltd Dwi Area 210518
Investigation
Data
Updated
Mine
Planning and
Design
Modified AMC22002
01 Jun AMC PT
Geotechnical 9/
6 PDF Asoka Herath Consultants Masmindo 57
Designs: 2021 Pty Ltd Dwi Area 210601
Awak Mas
North and
Salu Bulo
Waste Rock
Dumps
P:\ 66021_M\66021_M_J1088_V3.docx 21
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Dokumen 1, 2 dan 4 berkaitan dengan tahap desain terbaru untuk Fasilitas Penyimpanan Tailing
(TSF). Dokumen 3 merinci semua pekerjaan terbaru yang berkaitan dengan infrastruktur
permukaan. Dua laporan sisanya, yaitu Dokumen 5 dan 6 meliputi pekerjaan desain untuk
tambang terbuka (Dokumen 5) dan waste dumps (Dokumen 6).
4.3.2.1 Pengenalan
Laporan ini mewakili Geotechnical Interpretive Report (GIR), disiapkan berdasarkan pelaporan
geoteknik yang disiapkan selama DFS dan penyelidikan faktual yang dilakukan sebagai bagian
dari desain geoteknik ini (lihat Bab 4.3.1).
P:\ 66021_M\66021_M_J1088_V3.docx 22
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Laporan faktual historis tambahan diberikan dalam laporan Golder "Awak Mas Historical
Boreholes and Laboratory Test Data for TSF Area", memorandum 178712033-006-TM-Rev0
tertanggal 17 Juni 2020.
Setelah catatan geoteknik yang relevan dengan DFS untuk desain rinci termasuk pengujian
karakteristik partikel (ukuran, density dan plastisitas), undrained settling column test dan slurry
consolidation test pada sampel tailing. Hasil pengujian dilaporkan dalam Golder “Tailings
Laboratory Testing Report Awak Mas Gold Project”, tertanggal 20 Maret 2020.
4.3.3 Infrastructure - Geotechnical, Hydrology, and Civil Design Services Awak Mas
FEED (Dokumen 3)
4.3.3.1 Pengenalan
Golder ditugaskan oleh PT Petrosea Tbk. (Petrosea) untuk menyediakan Jasa Geoteknik,
Hidrologi dan Desain Sipil untuk studi Front-End-Engineering-Design (FEED) untuk Proyek
Tambang Emas Awak Mas.
Laporan ini menyajikan penilaian geoteknik untuk Area Pabrik Pengolahan, Gardu Induk dan
Fasilitas Tambang.
Tata letak site berikut digunakan sebagai referensi gambar untuk persiapan laporan:
➢ Pabrik Pengolahan: nama file "P4283-300-SKT-GN-001_B.DWG", 14 July 2020.
➢ Gardu Induk : nama file "PETROSEA LAYOUT GI.DWG", 11 September 2020.
➢ Fasilitas Tambang: nama file ·20210115 MIA exercise 5C - Layout.dwg·, 16 Januari 2021.
P:\ 66021_M\66021_M_J1088_V3.docx 23
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 24
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
4.3.4.1 Pendahuluan
Coffey ditugaskan oleh MDA untuk menyiapkan desain TSF terperinci untuk proyek tersebut.
Laporan Desain ini disusun berdasarkan pelaporan geoteknik selama DFS dan investigasi faktual
(Dokumen 1) dan pelaporan interpretatif (Dokumen 2) yang dilakukan sebagai bagian dari desain
geoteknik ini.
4.3.4.2 Ringkasan
Studi desain terperinci ini disiapkan mengikuti DFS, dan program pengujian geoteknik Lapangan
dan Laboratorium yang ekstensif.
Sebuah model geologi untuk TSF embankment envelope terdiri dari voIkanik era Oligosen (basal
dan batupasir dan batulanau) diterobos oleh gabro era Pliosen. Satu sesar telah ditemukan
sekitar 1 km jarak hulu dari kaki tanggul ubin dan tidak berdampak pada amplop tanggul TSF.
Pemilihan lokasi mempertimbangkan berbagi alternatif site. Lokasi yang dipilih memerlukan
fasilitas penyimpanan tipe lembah dengan tanggul yang akan dinaikkan ke ketinggian akhir
hampir 150 m di atas ujung kaki terakhirnya, ditinggikan selama ~16 tahun dan menyimpan ~30
juta m3 tailing.
Persiapan pondasi untuk mengurangi risiko likuifaksi seismik dan deformasi puncak
membutuhkan pengupasan tanah lapisan atas, tanah yang sangat lunak hingga tanah keras dan
juga akan melibatkan pengupasan tanah kaku (undrained shear strength kurang dari 100kPa,
dan SPT N < 12).
Potensi likuifaksi telah dinilai dan disimpulkan bahwa tanah di 3 m atas profil tanah umumnya
rentan terhadap likuifaksi, dan beberapa tanah pada kedalaman yang lebih dalam dapat secara
lokal rentan terhadap likuifaksi.
Parameter geoteknik yang cocok untuk studi pembebanan seismik diturunkan setelah pengujian
laboratorium spesialis untuk masukan ke studi deformasi dan stabilitas tanggul. Laporan desain
menganalisis stabilitas tanggul utama dan menyimpulkan bahwa Faktor Keamanan yang
memadai ada di bawah semua desain beban. Deformasi akibat gempa telah dianalisis
menggunakan metode empiris dan numerik.
Hidrologi daerah tangkapan dianalisis dan Surface Water Management Plan (SWMP) disusun.
Analisis jebolnya bendungan selesai dan populasi berisiko (PAR) diidentifikasi, luasan banjir dan
kedalaman genangan dari jebolnya TSF dihitung. Kategori konsekuensi dinilai sebagai "Ekstrim"
jika terjadi bencana jebolnya bendungan TSF di bawah skenario "hari hujan".
Desain juga menetapkan persyaratan untuk instrumentasi dan menyoroti pertimbangan
konstruksi utama termasuk prosedur operasi dan perencanaan Tindakan Darurat.
Perencanaan penutupan juga dipertimbangkan.
P:\ 66021_M\66021_M_J1088_V3.docx 25
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
4.3.5 Tinjauan Geoteknik Desain Pit Awak Mas dengan Data Investigasi Tambahan
(Dokumen 5)
Sebagai latar belakang, AMC Consultants Pty Ltd (AMC) sebelumnya telah menyelesaikan DFS
geoteknik untuk Awak Mas pada tahun 2018. Untuk DFS, AMC mengumpulkan semua data
geoteknik sebelumnya, mengawasi pemboran geoteknik terbatas (2 lubang bor di Awak Mas dan
1 lubang bor di Salu Bulo) dan melakukan logging geoteknik tambahan dari beberapa lubang bor
hidrogeologi. Data yang dianalisis digunakan untuk mengkarakterisasi dan mengklasifikasikan
massa batuan dan mengembangkan model domain geoteknik tiga dimensi (3D) untuk kedua
proyek tersebut. Parameter kekuatan ditentukan berdasarkan klasifikasi massa batuan dan data
kekuatan batuan. Analisis stabilitas lereng dilakukan dan parameter desain lereng pit diturunkan
untuk setiap sektor pit dari desain tambang.
Untuk meningkatkan kepercayaan model geoteknik, pengeboran geoteknik tambahan dan
logging dan pengujian kekuatan laboratorium dilakukan selama tahun 2020 dan awal 2021.
Pemboran geoteknik dilakukan di bagian barat daya (Rante selatan) area pit Awak Mas untuk
mengatasi keterbatasan data yang ada di area ini. Pencatatan geoteknik dari beberapa sumber
daya dan lubang piezometer juga dilakukan selama waktu ini ketika tersedia. Site Geologist
melakukan logging geoteknik di bawah panduan AMC.
Basis data geoteknik ditambah dengan data baru, yang meningkatkan basis data dari 3.000
catatan menjadi lebih dari 5.000 catatan, yang secara signifikan meningkatkan tingkat
kepercayaan karakterisasi massa batuan dan perkiraan kekuatan batuan.
Tinjauan AMC terdiri dari:
➢ Meningkatkan karakterisasi massa batuan dan klasifikasi kekuatan batuan menggunakan
data tambahan dan melakukan penilaian stabilitas dari tahap pit yang direncanakan.
➢ Memutuskan apakah desain pit saat ini memenuhi kriteria keamanan yang dipakai industri,
dan jika tidak, modifikasi desain apa yang diperlukan.
➢ Penilaian potensi kegagalan dari zona overburden/pelapukan di atas puncak pit.
➢ Menilai dampak air tanah pada stabilitas lereng dan apakah rekomendasi depressurisasi saat
ini memadai.
Penilaian stabilitas lereng keseluruhan ditinjau kembali menggunakan parameter kekuatan baru
yang berasal dari karakterisasi massa batuan yang direvisi dan klasifikasi kekuatan batuan.
4.3.5.1 Hidrogeologi
Penyelidikan hidrogeologi sebelumnya di Awak Mas mengidentifikasi profil batuan dasar yang
sangat lapuk dangkal dengan massa batuan dasar yang kurang lapuk dan permeabel. Sifat
akuifer sebagian besar tergantung pada fitur struktural lokal, tingkat rekahan, dan pelapukan
(RPS 2018).
Pada tahun 2020 dan 2021, jaringan titik pemantauan, menggunakan multi-depth grouted
vibrating wire piezometers (VWP) dan data-logger dipasang di lubang bor yang ada di Awak Mas
dan Salu Bulo. Tujuannya adalah untuk memungkinkan analisis distribusi tekanan dan untuk
menyoroti area di mana tekanan pori yang berlebihan dapat mengganggu stabilitas dinding.
Dua belas lubang dipilih di Awak Mas, dan tiga lubang di Salu Bulo, untuk memberikan distribusi
spasial yang wajar, dengan kedalaman VWP menargetkan litologi yang berpotensi permeabel
menurut log bor. Delapan VWP di empat lubang bor yang dipasang selama penyelidikan
sebelumnya terus memberikan data.
P:\ 66021_M\66021_M_J1088_V3.docx 26
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
AMC melakukan tinjauan desain pit saat ini menggunakan data massa dan kekuatan batuan yang
ditingkatkan. Tinjauan ini tidak mencakup penilaian stabilitas kinematik untuk desain adonan,
hanya penilaian stabilitas keseluruhan. Namun demikian, masalah stabilitas potensial di lapisan
penutup yang lapuk di atas adonan paling atas diselidiki. Kesimpulan dan rekomendasi berikut
ditentukan.
Kesimpulan utama dari studi yang dilakukan AMC adalah:
➢ Desain pit saat ini stabil terhadap kegagalan massa batuan pada skala lereng keseluruhan
dengan FOS melebihi kriteria penerimaan untuk kondisi keseimbangan statis dan pseudo
statis.
➢ Beberapa bagian kuasi stabil terhadap kegagalan struktural pada foliasi di mana-mana.
Namun kontinuitas yang besar (>50 m) di sepanjang bidang foliasi diasumsikan, yang
mungkin merupakan kondisi aktual yang dilebih-lebihkan (terlalu pesimistis). Selanjutnya,
metode analisis konservatif (analisis linierisotropik) digunakan. Karena alasan ini, ambang
batas FOS ditetapkan pada 1,0.
➢ Bagian-bagian dengan nilai FOS sedikit kurang dari 1,0 meningkat di atas ambang batas
yang diperlukan dengan depresurisasi yang sesuai.
➢ Ada potensi terjadinya pelapukan lapisan penutup / deposit colluvial jika kemiringan alami di
atas bench pertama adalah 35°.
➢ Kemampugalian batuan dinilai. Batuan dikategorikan cukup kuat hingga kuat. Umumnya,
mereka dapat di-ripping tetapi akan membutuhkan peledakan untuk merenggangkan.
➢ Trafficability lapisan penutup dievaluasi menggunakan nilai CBR yang diturunkan dari hasil
uji DCP. Pelapisan di atas tanah dasar akan diperlukan untuk jalan angkut tambang.
Rekomendasi utama AMC adalah:
➢ Berdasarkan hasil pemantauan piezometer yang baru dipasang, AMC merekomendasikan
sekitar 1000 m HDH dangkal (40 m) untuk mencapai depressurisasi untuk lereng tunggal
(AMC 2021), yang berbeda dengan rekomendasi studi 2018.
➢ Untuk mencapai stabilitas terhadap longsoran struktural, drainase horizontal dalam akan
diperlukan. HDH sedalam 150 m direkomendasikan (lebih pendek dari rekomendasi AMC
2018 untuk HDH sedalam 200 m). Efektivitas pengurangan tekanan pori harus dinilai
menggunakan jaringan piezometer yang ada dan jaringan HDH yang dimodifikasi. AMC
memperkirakan akan dibutuhkan 7.500 m pengeboran.
➢ Direkomendasikan sebuah berm selebar 10 m di bawah lereng tambang pertama di bawah
lereng alami, dengan maksud untuk memudahkan melakukan perbaikan jika terjadi
ketidakstabilan minor. Ini adalah satu-satunya perubahan desain yang direkomendasikan
dan hanya akan mempengaruhi konstruksi Tahap 1.
➢ AMC merekomendasikan bahwa 150 mm lapisan tanah atas yang terdiri dari bahan organik
yang berlebihan harus dihilangkan dan lapisan tanah atas di-ripping dan dipadatkan kembali.
Lapisan subbase nominal setebal 1 m dengan batuan dari pit (terdiri dari batuan waste)
direkomendasikan untuk jalan angkut tambang.
P:\ 66021_M\66021_M_J1088_V3.docx 27
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 28
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Gambar 4.1 Lembah Awak Mas Utara Dilihat Dari Camp Masjid Dan Tempat
Penyimpanan Core (Dari Dokumen 6)
Ringkasan utama, Kesimpulan dan Rekomendasi dari AMC adalah sebagai berikut:
Awak Mas NWRD
Menurut jadwal penambangan, desain dump Awak Mas NWRD Tahap 1 memenuhi persyaratan
volume untuk delapan tahun pertama penambangan. Pembangunan dump Tahap 1 akan
memberikan pengalaman berharga di beberapa bidang:
➢ Tanah lapisan atas yang terdiri dari bahan organik perlu dikupas dan ditimbun untuk
digunakan untuk rehabilitasi WRD.
➢ Lereng pembuangan dirancang pada sudut kemiringan keseluruhan 20°. Ini dianggap
sebagai sudut kemiringan yang sangat rendah. Biasanya, timbunan batuan akan diprofil
ulang untuk rehabilitasi hingga 20°.
➢ Analisis menunjukkan bahwa baik Tahap 1 dan tahap akhir lereng stabil terhadap mobilisasi
coluvium sebagai lapisan tunggal pada antarmuka batuan dasar yang sangat lapuk. Analisis
juga menegaskan bahwa desain yang dimodifikasi stabil tanpa perawatan pondasi, termasuk
terhadap beban gempa.
➢ Terlepas dari longsoran besar, yang merupakan masalah desain, longsoran skala kecil harus
dikelola dengan rencana pengelolaan WRD (misalnya dumping short, penggunaan spotter,
dll.).
➢ Jika lereng Tahap 1 stabil, kemiringan keseluruhan dapat ditingkatkan dan menghindari
pengisian lembah yang jauh lebih besar, yang secara signifikan meningkatkan kebutuhan
P:\ 66021_M\66021_M_J1088_V3.docx 29
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
drainase. Analisis menunjukkan bahwa kemiringan Tahap 1 saat ini dapat ditingkatkan
sebesar 5° dalam kriteria desain target.
➢ Jika tanah lemah terdistribusi lebih luas daripada yang diasumsikan dalam analisis, peristiwa
seismik dapat mengganggu kestabilan lereng. Ini akan menjadi risiko besar yang sulit untuk
dimitigasi. Namun, dengan sudut kemiringan keseluruhan yang sangat rendah, AMC
menganggap bahwa keruntuhan lereng seperti itu tidak akan berkembang menjadi run.
➢ Ada banyak aliran air kecil hingga sedang di dalam area pembuangan. AMC mengusulkan
bahwa drainase yang dirancang dengan baik dapat menghindari perkembangan permukaan
freatik di dalam timbunan. Sebuah timbunan batu yang lebih bersih yang terdiri dari bahan
batuan yang cukup segar harus ditempatkan di atas pondasi, terutama di daerah yang
dicirikan dengan tanah liat permukaan.
➢ AMC merekomendasikan agar program test pit jarak dekat (~100 m grid) dilakukan, atau
serangkaian radial trenches dibangun pada batas area terganggu WRD di luar area
pembuangan Tahap 1, untuk penyelidikan rinci lapisan tanah permukaan.
Salu Bulo WRD
Modifikasi desain berikut diterapkan oleh AMC:
➢ Kurangi ketinggian lereng utama dari desain saat ini sebesar 10 m (900 mRL menjadi 890
mRL).
➢ Tambahkan bobot di toe, pada saat yang sama menopang dump dan mengambil benefit dari
topografi (membangun kaki terhadap punggungan).
➢ Sekitar 40 m x 150 m area membutuhkan pengupasan tanah permukaan pada pondasi
hingga kedalaman 3 m, pada 810 mRL di lereng timur laut akan diperlukan.
o Pengupasan tanah mengubah topografi lereng pondasi yang sebelumnya seperti
lompatan ski yang mana mengurangi FOS di bawah beban seismik.
o Penggalian harus dilakukan di bawah pengawasan seorang geotechnical engineer
dengan evaluasi kondisi tanah diikuti dengan evaluasi stabilitas.
➢ Material lapuk (material overburden dari galian pondasi TSF) yang direncanakan untuk
bagian kaki timbunan harus dipindahkan ke atas timbunan.
Fondasi untuk timbunan batuan sisa Awak Mas (utara) dan Salu Bulo akan dibangun di atas
fondasi yang terdiri dari material yang lebih lemah yang dapat mempengaruhi stabilitas.
Pemindahan vegetasi dan tanah permukaan
Langkah ini sebagian besar terbatas pada area toe WRD Tahap 1 Awak Mas tetapi harus
diperluas lebih jauh ke bagian lereng jika diperlukan:
➢ Pindahkan vegetasi dan lapisan topsoil. Ini harus diputuskan oleh Geotechnical Engineer.
Topsoil harus ditimbun untuk rehabilitasi tempat pembuangan di masa depan.
➢ Geotechnical Engineer harus memeriksa daerah tersebut untuk tanah yang lebih lemah.
Direkomendasikan untuk melakukan penilaian kekuatan lapangan, tes pentrometer dan tes
dynamic cone penetration (DCP) di daerah tersebut untuk menilai kekuatan tanah.
o Tergantung pada asumsi desain, pengupasan tanah yang lebih lemah mungkin
diperlukan. Hal ini sangat relevan dengan TPA Salu Bulo yang membutuhkan pengupasan
tanah seluas 40 m x 150 m x 3 m.
P:\ 66021_M\66021_M_J1088_V3.docx 30
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 31
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Table 4.3 Tingkatan Upaya Geotecknik berdasarkan Tahapan Proyek (Guidelines for
Open Pit Slope Design, CSIRO 2008)
P:\ 66021_M\66021_M_J1088_V3.docx 32
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
5 PENAMBANGAN
P:\ 66021_M\66021_M_J1088_V3.docx 33
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
AMC telah merancang lubang untuk pemasangan VWP dan Masmindo baru saja menyelesaikan
pemasangan 12 lubang di Awak Mas dan 3 di Salu Bulo. Data yang diambil dari VWP akan
digunakan untuk mengonfirmasi parameter desain, memandu rencana depressurisasi
operasional, dan dapat memberikan peluang untuk mempertajam sudut dinding.
P:\ 66021_M\66021_M_J1088_V3.docx 34
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
USD/t bijih untuk Pit Awak Mas dan 4,73 USD/t bijih untuk Salu Bulo, karena jarak angkut
tambahan ke pabrik pengolahan dari Salu Bulo.
Perolehan metalurgi tetap sama seperti pekerjaan tahun 2020, di mana nilai ini sudah didukung
oleh pengujian baru-baru ini.
Table 5.1 Parameter Optimisasi Pit
Deskripsi Unit Nilai
Harga Emas USD/oz 1.400
Royalti % 4,00
Biaya Transportasi Emas $/oz 1,00
Biaya Refining Emas $/oz 1,93
Payable Emas % 99,75
Revenue Emas Bersih $/oz 1,338
Revenue Emas Bersih $/g 43,01
Biaya Penambangan (AM) $/t tertambang 2,85
Biaya Penambangan (SB) $/t tertambang 2,89
Biaya Pengolahan $/t bijih terproses 10,03
General dan Admin $/t tertambang 3,64
Rehandle & Crusher Feed $/t tertambang 0,41
Biaya Ore Grade Control $/t bijih tertambang 0,35
Biaya Angkut Bijih ke Pabrik (AM) $/t bijih tertambang 0,67
Biaya Angkut Bijih ke Pabrik (SB) $/t bijih tertambang 1,69
Biaya Sustaining TSF $/t bijih tertambang 1,57
% Rante, tanjong, Lematik 93,2
Perolehan Pabrik % Mapacing Ongan 92,2
% Salu Bulo 94,8
Proses optimisasi pit diiterasi berdasarkan model yang sudah didilusi dan hanya dilakukan
terhadap Sumber Daya Mineral Terukur dan Tertunjuk untuk Awak Mas dan Salu Bulo. Sumber
Daya Terkira dianggap sebagai waste dalam proses optimasi pit.
P:\ 66021_M\66021_M_J1088_V3.docx 35
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Tabel output optimasi pit ditunjukkan pada Table 5.2 dan Table 5.3.
Table 5.2 Hasil Optimasi Untuk Awak Mas Berdasarkan Kategori Sumber Daya Terukur
Dan Tertunjuk, Dijalankan 6. Lubang Terpilih Dan Lubang Optimal Disorot
Optimum
Base Shell Data (2021 Model, 2021 BoD Opt2, Diluted model 5mx5mx5m) Value
Pit Shell Revenue Final Ore Tonnes Waste Total Strip Mining Cost Processing Au grade in- Au metal in-situ Produced Au Processing Mining Revenue Undiscounted Discounted Discounted Cost per Ounce
Factor Bench Tonnes Rock Ratio Per Total Cost Per Tonne situ Metal Cost Cost Cash Flow Best Worst
Tonnes Tonne Mined of Ore Cash Flow Cash Flow
No. No. (mRL) (Mt) (Mt) (Mt) W:O ($/t) ($/t) (g/t) (koz) (koz) ($M) ($M) ($M) ($M) ($M) ($M) (A$/oz)
1 0.40 975 4.0 5.2 9.2 1.3 -2.85 -16.67 1.70 219 203 67 26 272 179 168 168
2 0.42 975 4.5 6.0 10.5 1.4 -2.85 -16.67 1.67 240 222 74 30 298 194 181 181 578
3 0.44 975 5.2 7.7 12.9 1.5 -2.85 -16.67 1.63 274 254 87 37 341 217 202 201 603
4 0.46 975 5.6 8.5 14.1 1.5 -2.85 -16.67 1.62 291 270 93 40 362 228 212 211 636
5 0.48 975 7.8 13.8 21.6 1.8 -2.85 -16.67 1.54 384 357 129 61 478 287 262 259 659
6 0.50 975 9.0 16.8 25.8 1.9 -2.85 -16.67 1.51 435 403 150 74 541 318 288 282 689
7 0.52 975 9.4 17.9 27.2 1.9 -2.85 -16.67 1.50 451 419 156 78 562 328 295 290 708
8 0.54 975 10.1 20.7 30.8 2.0 -2.85 -16.67 1.49 484 449 168 88 602 346 310 303 729
9 0.56 970 10.8 23.0 33.8 2.1 -2.85 -16.67 1.48 512 475 179 96 637 361 322 314 757
10 0.58 970 11.2 24.7 35.9 2.2 -2.85 -16.67 1.47 530 492 186 102 660 371 330 321 778
11 0.60 965 11.4 25.3 36.7 2.2 -2.85 -16.67 1.47 538 499 190 105 669 375 333 324 806
12 0.62 965 11.9 27.6 39.5 2.3 -2.85 -16.67 1.46 560 520 199 113 697 385 341 331 831
13 0.64 960 12.1 28.1 40.3 2.3 -2.85 -16.67 1.45 567 526 202 115 705 388 343 332 858
14 0.66 960 12.4 29.4 41.8 2.4 -2.85 -16.67 1.45 578 536 207 119 719 393 347 335 876
15 0.68 960 15.2 40.5 55.7 2.7 -2.85 -16.67 1.39 679 630 253 159 845 434 377 358 910
16 0.70 950 15.7 43.0 58.6 2.7 -2.85 -16.67 1.39 698 648 261 167 869 441 382 362 932
17 0.72 950 16.4 46.1 62.5 2.8 -2.85 -16.67 1.37 724 672 273 178 901 450 388 366 959
18 0.74 950 17.1 49.6 66.7 2.9 -2.85 -16.67 1.37 750 696 284 190 933 459 394 370 978
19 0.76 925 19.8 65.4 85.2 3.3 -2.85 -16.67 1.34 853 792 330 243 1,062 490 415 384 1,015
20 0.78 925 20.4 69.0 89.5 3.4 -2.85 -16.67 1.34 877 814 340 255 1,092 497 420 386 1,033
21 0.80 925 21.2 74.3 95.4 3.5 -2.85 -16.67 1.33 908 843 353 272 1,130 505 425 388 1,064
22 0.82 925 21.6 76.5 98.1 3.5 -2.85 -16.68 1.33 923 856 361 280 1,149 508 427 389 1,089
23 0.84 925 22.6 82.4 104.9 3.7 -2.85 -16.68 1.32 957 888 376 299 1,191 515 432 389 1,109
24 0.86 925 23.3 87.9 111.2 3.8 -2.85 -16.68 1.31 986 915 389 317 1,227 521 435 388 1,134
25 0.88 925 23.5 88.4 111.9 3.8 -2.85 -16.68 1.31 989 919 391 319 1,232 522 435 389 1,161
26 0.90 910 24.1 91.9 116.0 3.8 -2.85 -16.68 1.30 1,009 937 401 331 1,256 524 437 389 1,192
27 0.92 895 33.3 192.4 225.7 5.8 -2.85 -16.68 1.33 1,423 1,321 555 643 1,772 574 451 329 1,211
28 0.94 895 33.5 194.7 228.2 5.8 -2.85 -16.68 1.33 1,433 1,331 559 650 1,785 575 452 328 1,252
29 0.96 895 33.7 196.7 230.5 5.8 -2.85 -16.68 1.33 1,441 1,339 563 657 1,795 576 452 326 1,279
30 0.98 895 34.0 198.5 232.5 5.8 -2.85 -16.68 1.33 1,449 1,346 566 663 1,805 576 452 325 1,300
31 1.00 890 34.1 199.8 234.0 5.9 -2.85 -16.68 1.33 1,455 1,351 569 667 1,812 576 452 324 1,327
32 1.02 890 34.7 205.0 239.7 5.9 -2.85 -16.68 1.32 1,475 1,370 579 683 1,837 576 452 319 1,356
33 1.04 890 34.8 205.5 240.2 5.9 -2.85 -16.68 1.32 1,477 1,372 580 685 1,840 576 452 319 1,379
34 1.06 890 35.9 218.5 254.4 6.1 -2.85 -16.68 1.32 1,522 1,414 598 725 1,896 573 450 305 1,403
35 1.08 890 36.2 222.4 258.6 6.1 -2.85 -16.68 1.32 1,536 1,427 604 737 1,913 572 449 301 1,431
36 1.10 890 36.5 225.4 262.0 6.2 -2.85 -16.68 1.32 1,547 1,437 609 747 1,927 571 449 298 1,461
37 1.12 890 36.8 228.8 265.7 6.2 -2.85 -16.68 1.32 1,558 1,447 614 757 1,941 569 448 294 1,483
38 1.14 890 36.9 230.1 267.0 6.2 -2.85 -16.68 1.32 1,562 1,451 616 761 1,946 569 448 293 1,516
39 1.16 890 38.0 245.2 283.3 6.5 -2.85 -16.68 1.31 1,607 1,493 634 807 2,002 560 444 273 1,539
40 1.18 890 38.1 246.4 284.5 6.5 -2.85 -16.68 1.31 1,611 1,496 636 811 2,006 560 443 272 1,566
41 1.20 890 38.2 247.0 285.1 6.5 -2.85 -16.68 1.31 1,613 1,498 637 813 2,008 559 443 271 1,598
42 1.22 890 38.4 249.3 287.7 6.5 -2.85 -16.68 1.31 1,620 1,504 640 820 2,017 557 442 269 1,621
43 1.24 890 38.8 254.5 293.2 6.6 -2.85 -16.68 1.31 1,634 1,518 647 836 2,035 553 440 262 1,653
44 1.26 890 38.9 255.3 294.2 6.6 -2.85 -16.68 1.31 1,637 1,520 648 838 2,039 552 440 261 1,677
1,710
45 1.28 885 39.1 258.4 297.4 6.6 -2.85 -16.68 1.31 1,645 1,528 651 848 2,049 550 438 257
P:\ 66021_M\66021_M_J1088_V3.docx 36
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Table 5.3 Hasil Optimasi Untuk Salu Bulo Berdasarkan Kategori Sumber Daya
Terukur Dan Tertunjuk Jalankan 4. Lubang Yang Dipilih Disorot
Base Shell Data (Run4, 2021 Model, Diluted model 5mx5mx5m) Value
Pit Shell Revenue Final Ore Tonnes Waste Total Strip Mining Cost Processing Au grade in- Au metal in-situ Produced Au Processing Mining Revenue Undiscounted Discounted Discounted Cost per Ounce
Factor Bench Tonnes Rock Ratio Per Total Cost Per Tonne situ Metal Cost Cost Cash Flow Best Worst
Tonnes Tonne Mined of Ore Cash Flow Cash Flow
No. No. (mRL) (Mt) (Mt) (Mt) W:O ($/t) ($/t) (g/t) (koz) (koz) ($M) ($M) ($M) ($M) ($M) ($M) (A$/oz)
1 0.40 980 0.3 1.6 1.9 4.9 -2.69 -17.67 2.42 25.26 23.89 5.7 5.1 32.0 21.2 21.1 21.1
2 0.42 940 0.4 2.0 2.4 4.8 -2.69 -17.68 2.31 31.01 29.32 7.4 6.5 39.3 25.4 25.2 25.2 558
3 0.44 940 0.5 2.5 3.0 5.0 -2.69 -17.67 2.26 37.09 35.07 9.0 8.2 47.0 29.9 29.6 29.6 573
4 0.46 940 0.6 2.9 3.5 5.2 -2.69 -17.67 2.25 41.13 38.89 10.1 9.4 52.2 32.7 32.3 32.3 607
5 0.48 935 0.6 3.4 4.1 5.3 -2.69 -17.67 2.21 45.88 43.39 11.4 10.9 58.2 35.8 35.4 35.4 636
6 0.50 935 0.7 3.5 4.1 5.3 -2.69 -17.67 2.20 46.37 43.85 11.6 11.1 58.8 36.1 35.7 35.7 657
7 0.52 935 0.8 4.4 5.2 5.7 -2.69 -17.67 2.16 54.49 51.53 13.9 14.1 69.1 41.2 40.6 40.6 685
8 0.54 935 0.9 5.0 5.9 5.9 -2.69 -17.67 2.15 58.90 55.69 15.1 15.8 74.7 43.8 43.1 43.1 714
9 0.56 935 0.9 5.4 6.3 6.1 -2.69 -17.67 2.14 61.76 58.40 15.9 17.0 78.3 45.4 44.6 44.6 738
10 0.58 935 1.0 6.1 7.0 6.3 -2.69 -17.67 2.14 65.79 62.21 16.9 18.9 83.4 47.6 46.7 46.7 769
11 0.60 930 1.3 9.1 10.4 7.0 -2.69 -17.67 2.06 86.07 81.39 22.9 28.0 109.2 58.2 56.7 56.7 789
12 0.62 930 1.3 9.2 10.5 7.1 -2.69 -17.67 2.06 86.44 81.74 23.0 28.2 109.6 58.4 56.9 56.9 823
13 0.64 930 1.3 9.4 10.8 7.1 -2.69 -17.67 2.06 87.85 83.07 23.5 28.9 111.4 59.0 57.5 57.5 853
14 0.66 925 1.4 10.3 11.8 7.2 -2.69 -17.67 2.03 93.43 88.35 25.4 31.6 118.5 61.5 59.8 59.8 872
15 0.68 920 1.5 11.2 12.7 7.4 -2.69 -17.67 2.01 98.35 93.00 26.9 34.3 124.7 63.5 61.7 61.7 904
16 0.70 920 1.5 11.4 12.9 7.4 -2.69 -17.67 2.01 99.15 93.76 27.1 34.8 125.7 63.8 62.0 62.0 932
17 0.72 920 1.6 11.7 13.3 7.5 -2.69 -17.67 2.00 100.68 95.21 27.6 35.7 127.7 64.4 62.5 62.5 955
18 0.74 920 1.6 12.1 13.7 7.6 -2.69 -17.67 2.00 102.81 97.22 28.3 36.9 130.4 65.1 63.1 63.1 977
19 0.76 920 1.8 14.0 15.8 8.0 -2.69 -17.67 1.98 111.49 105.43 31.0 42.5 141.4 67.9 65.7 65.7 1,000
20 0.78 920 1.8 14.1 15.9 8.0 -2.69 -17.67 1.97 112.02 105.93 31.2 42.8 142.1 68.1 65.8 65.8 1,029
21 0.80 915 1.8 14.5 16.3 8.1 -2.69 -17.67 1.97 113.79 107.60 31.8 44.0 144.3 68.6 66.2 66.2 1,052
22 0.82 915 1.8 14.6 16.4 8.1 -2.69 -17.67 1.96 114.22 108.01 32.0 44.2 144.9 68.7 66.3 66.3 1,081
23 0.84 915 1.9 15.6 17.4 8.3 -2.69 -17.67 1.96 117.92 111.51 33.1 46.9 149.5 69.5 67.0 67.0 1,111
24 0.86 915 1.9 15.8 17.7 8.4 -2.69 -17.67 1.95 118.75 112.29 33.4 47.5 150.6 69.6 67.1 67.1 1,146
25 0.88 915 1.9 15.9 17.9 8.4 -2.69 -17.67 1.95 119.44 112.95 33.7 48.0 151.5 69.8 67.2 67.2 1,163
26 0.90 915 1.9 16.2 18.1 8.4 -2.69 -17.67 1.94 120.41 113.87 34.0 48.8 152.7 69.9 67.3 67.3 1,206
27 0.92 915 1.9 16.5 18.5 8.5 -2.69 -17.67 1.94 121.47 114.86 34.3 49.7 154.0 70.0 67.4 67.4 1,212
28 0.94 915 1.9 16.5 18.5 8.5 -2.69 -17.67 1.94 121.53 114.92 34.4 49.7 154.1 70.0 67.4 67.4 1,248
29 0.96 915 2.0 16.7 18.7 8.5 -2.69 -17.67 1.94 122.21 115.57 34.7 50.3 155.0 70.1 67.4 67.4 1,274
30 0.98 910 2.0 17.3 19.3 8.6 -2.69 -17.67 1.93 124.03 117.29 35.3 51.9 157.3 70.1 67.4 67.4 1,311
31 1.00 910 2.0 17.5 19.6 8.7 -2.69 -17.67 1.93 124.84 118.06 35.6 52.6 158.3 70.1 67.4 67.4 1,327
32 1.02 910 2.0 17.6 19.7 8.8 -2.69 -17.67 1.93 125.10 118.30 35.6 52.9 158.6 70.1 67.4 67.4 1,344
33 1.04 910 2.0 17.7 19.7 8.8 -2.69 -17.67 1.93 125.19 118.38 35.7 53.0 158.8 70.1 67.4 67.4 1,386
34 1.06 910 2.0 18.1 20.1 8.8 -2.69 -17.67 1.92 126.42 119.54 36.2 54.1 160.3 70.0 67.3 67.3 1,413
35 1.08 905 2.1 18.4 20.4 8.9 -2.69 -17.67 1.92 127.34 120.42 36.5 55.0 161.5 70.0 67.2 67.2 1,436
36 1.10 905 2.1 18.4 20.5 8.9 -2.69 -17.67 1.91 127.43 120.50 36.6 55.1 161.6 69.9 67.2 67.2 1,466
37 1.12 905 2.1 18.5 20.6 8.9 -2.69 -17.67 1.91 127.85 120.90 36.8 55.5 162.1 69.9 67.1 67.1 1,487
38 1.14 905 2.1 18.8 20.9 9.0 -2.69 -17.67 1.91 128.46 121.47 37.0 56.2 162.9 69.8 67.0 67.0 1,530
39 1.16 900 2.1 19.1 21.2 9.1 -2.69 -17.67 1.91 129.17 122.14 37.2 57.0 163.8 69.6 66.8 66.8 1,556
40 1.18 900 2.1 19.1 21.2 9.1 -2.69 -17.67 1.91 129.34 122.30 37.3 57.1 164.0 69.6 66.8 66.8 1,572
41 1.20 900 2.1 19.2 21.3 9.1 -2.69 -17.67 1.91 129.40 122.36 37.3 57.2 164.1 69.6 66.8 66.8 1,596
42 1.22 900 2.1 19.2 21.3 9.1 -2.69 -17.67 1.90 129.46 122.42 37.4 57.2 164.2 69.6 66.7 66.7 1,620
43 1.24 900 2.1 19.2 21.3 9.1 -2.69 -17.67 1.90 129.55 122.51 37.4 57.3 164.3 69.5 66.7 66.7 1,647
44 1.26 900 2.1 19.6 21.7 9.2 -2.69 -17.67 1.90 130.40 123.31 37.7 58.4 165.4 69.3 66.4 66.4 1,678
1,708
45 1.28 900 2.2 20.0 22.2 9.3 -2.69 -17.67 1.89 131.56 124.41 38.2 59.7 166.8 68.9 66.0 66.0
P:\ 66021_M\66021_M_J1088_V3.docx 37
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 38
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 39
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Catatan: kadar batas 0,5 g/t untuk bijih, kadar bahan marjinal adalah 0,4 hingga 0,5 g/t. sedikit perbedaan dapat dilaporkan antar
tabel karena metode penghitungan persediaan yang berbeda.
Waste dump diposisikan untuk meminimalkan risiko sterilisasi sumber daya potensial dan
perluasan pit, untuk mencapai stabilitas geoteknik dan untuk meminimalkan jarak angkut.
Penyelidikan geokimia menunjukkan bahwa waste tidak berpotensi menghasilkan asam (PAF),
namun, jika ada waste dengan volume kecil memerlukan encasement ada area kecil di dalam
waste dump yang didesain untuk membuang material ini. Desain tempat pembuangan waste
Awak Mas dan Salu Bulo ditunjukkan pada Gambar 5.3 dan Gambar 5.4.
P:\ 66021_M\66021_M_J1088_V3.docx 40
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 41
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Tata letak site secara keseluruhan disajikan pada Gambar 5.5. Tata letak tersebut mencakup
lokasi untuk infrastruktur pemrosesan, penyimpanan tailing, pembuangan limbah, stockpile untuk
bijih marginal, kadar rendah dan tinggi, penyimpanan tanah lapisan atas, bengkel tambang,
fasilitas bahan peledak dan majalah serta jalan angkut.
P:\ 66021_M\66021_M_J1088_V3.docx 42
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 43
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\ 66021_M\66021_M_J1088_V3.docx 44
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 45
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Catatan:
➢ Batas kadar 0.5 g/t untuk bijih, kadar material marjinal 0.4 sampai 0.5 g/t .
➢ Nisbah kupas 5.2:1.
➢ Material tereka yang dimasukkan ke pengolahan 3.240 kt (9% dari total yang diolah).
P:\66021_M\66021_M_J1088_V3.docx 46
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
penambangan ini. Ukuran SMU 5m x 5m x 5m memberikan tingkat dilusi dan kehilangan bijih
yang dapat diterima.
Faktor Dilusi and Kehilangan Bijih
Estimasi Dilusi dan Kehilangan Bijih telah dilakukan melalui proses regularisasi model
Sumberdaya menjadi model Perencanaan Tambang dengan ukuran SMU 5m x 5m x 5m. Proses
ini secara efektif mempertimbangkan blok bijih dan waste kadar rendah yang lebih sempit di
dalam badan bijih dan menetapkannya ke blok yang lebih besar yang lebih mewakili
penambangan badan bijih yang sebenarnya.
Proses ini menghasilkan perkiraan dilusi penambangan dan kehilangan bijih dibandingkan
dengan model sumber daya sebagai berikut:
➢ Model Awak Mas menunjukkan peningkatan dilusi sebesar 5% dalam ton dan penurunan
kadar emas sebesar 7% untuk menghasilkan 97% emas yang terkandung (nilai batas 0,5 g/t).
AMC menggunakan model ini untuk desain tambang dan estimasi Cadangan Bijih. Pelaporan
dampak dari dilusi dan kehilangan bijih di atas menggunakan nilai batas 0,5 g/t dan dibatasi
oleh optimasi shell 1.600 USD/oz yang disediakan oleh Cube.
➢ Model Salu Bulo menunjukkan peningkatan dilusi sebesar 1% dalam ton, di atas kadar batas
dilusi dan pengurangan kadar emas sebesar 11% untuk hasil 90% emas yang terkandung
(nilai batas 0,5 g/t) setara dengan faktor dilusi 11%. AMC menggunakan model ini untuk
desain tambang dan estimasi Cadangan Bijih. Pelaporan dampak dilusi dan kehilangan bijih
yang disebutkan di atas menggunakan kadar batas 0,5 g/t dan dibatasi oleh pengoptimalan
shell 1.600 USD/oz yang dihasilkan oleh AMC.
Proses dan estimasi dilusi dan kehilangan bijih di atas berada dalam ekspektasi untuk jenis
deposit dan metode penambangan ini. Hal ini tidak dapat dikonfirmasi sampai setelah
penambangan dan pemrosesan bijih mencapai kondisi produksi yang stabil yang memungkinkan
rekonsiliasi model sumber daya yang ditambang bijih untuk dilakukan.
Tidak ada faktor dilusi atau kehilangan bijih tambahan yang digunakan dalam proses lebih lanjut
untuk mengestimasi Cadangan Bijih.
P:\66021_M\66021_M_J1088_V3.docx 47
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Sumber Daya Mineral dan Cadangan Bijih sudah sesuai. Hasil dari penggunaan kadar batas yang
lebih tinggi bersifat konservatif dan membatasi risiko terhadap penurunan harga logam.
5.2.4 Geoteknik
Sebagai bagian dari DFS, studi Geoteknik telah dilakukan oleh AMC dengan masukan lain dari
Golder. Hal tersebut memberikan rekomendasi untuk digunakan dalam desain tambang.
Mining One telah meninjau rekomendasi Geoteknik dan menganggapnya sudah sesuai untuk
pelaporan KCMI seperti yang didiskusikan di Bab 4.
Sudut kemiringan dinding dan parameter geoteknik ini telah digunakan dalam optimasi Pit dan
proses desain tambang. Rekomendasi lereng pit juga telah memperhitungkan masukan dari studi
Hidrogeologi.
P:\66021_M\66021_M_J1088_V3.docx 48
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
digunakan di Indonesia dan dianggap sesuai dengan metode penambangan dan tingkat produksi
tambang. Ukuran eksavator cocok untuk penambangan bijih selektif standar industri dengan
kemampuan kontrol pengenceran dan perolehan bijih yang baik.
ADT cocok untuk daerah dengan curah hujan tinggi di mana kondisi jalan angkut bisa memburuk
dengan cepat jika hujan.
Jumlah armada didasarkan pada jadwal penambangan dan faktor ketersediaan, efisiensi, dan
pemanfaatan yang berlaku.
Armada produksi didukung oleh peralatan bantu dengan jumlah dan ukuran yang sesuai.
Armada pengeboran ditentukan untuk memenuhi jadwal pengeboran berdasarkan usulan pola
pengeboran dan peledakan di setiap jenjang tambang.
P:\66021_M\66021_M_J1088_V3.docx 49
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
peralatan penambangan. Biaya peralatan pertambangan dimasukkan sebagai bagian dari biaya
operasi pertambangan di bawah struktur kontraktor.
P:\66021_M\66021_M_J1088_V3.docx 50
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 51
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Pencucian emas terjadi dari luapan siklon dalam satu tangki resapan dan 5 tangki CIL, di mana
sianida, kapur dan oksigen ditambahkan. Karbon bergerak berlawanan arah dengan ore slurry
untuk menyerap emas yang terlindi.
Karbon yang dimuat dikumpulkan dan diolah dalam kolom elusi, menggunakan metode Anglo
Amerian Research Laboratories (AARL) split. Karbon diregenerasi melalui tungku karbon dan
eluat memberi EW ke pelat emas. Emas berlapis dikumpulkan dan dilebur untuk menghasilkan
doré emas.
Tailing dari CIL dikentalkan dan dipompa ke hopper tailing melalui 2 tangki penghancur sianida.
Penghancuran sianida terjadi menggunakan proses INCO SO2/udara. Persyaratan pembuangan
sianida WAD yang ditargetkan adalah maksimum 0,5 ppm CNWAD.
Tailing dipompa sekitar 4 km ke TSF. Diagram alir pengolahan dapat dilihat pada Gambar 6 1.
P:\66021_M\66021_M_J1088_V3.docx 52
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Air yang digunakan untuk pemrosesan emas disuplai dari air baku dan tailing thickener overflow.
Air baku bersumber dari Sungai Songgong dekat lokasi Proyek dan dipompa melalui pipa ke
pabrik pengolahan.
Desain pengolahan yang digunakan adalah proses pengolahan emas konvensional dengan
konfigurasi berisiko rendah. Utilisasi pabrik diasumsikan 91,3% dan dianggap cukup masuk akal
dan sesuai dengan standar yang dipakai di industri tambang. Sementara itu, utilisasi crushing
circuit juga diasumsikan 91,3% dan dianggap cukup tinggi, tetapi stockpile darurat 12 jam
digunakan untuk membantu mengurangi risiko waktu henti crusher. Pengaturan ini bukan desain
terbaik, tetapi dianggap cukup memadai.
Ukuran penggilingan P80 75 µm umumnya digunakan dalam industri pengolahan emas. Waktu
pelindian 24 jam CIL juga merupakan nilai standar industri.
6.2 Recovery
Deposit Awak Mas terdiri dari lima domain termineralisasi:
➢ Rante
➢ Tanjung
➢ Lematik
➢ Mapacing
➢ Ongan
Selain itu, ada dua deposit satelit yaitu Salu Bulo dan Tarra.
Uji coba yang signifikan telah dilakukan pada proyek Awak Mas sejak tahun 1994. Uji coba
sebagian besar telah dilakukan oleh Ammtec / ALS Ammtec / ALS Metalurgi. Testwork telah
difokuskan pada tiga pilihan proses:
➢ Flotasi dan CIL.
➢ Gravitasi dan pelindian bijih.
➢ Pelindian bijih dengan gravity sulphide regrind.
Gravitasi dan pelindian bijih utuh dipilih sebagai opsi yang direkomendasikan setelah Studi Opsi
Pemrosesan Minnovo dilakukan tahun 2017. Opsi ini dianggap paling optimum oleh tim studi inti
dari Nusantara, Minnovo dan Cube Consulting.
Program pengujian komprehensif yang diselesaikan untuk Awak Mas dirangkum dalam Gambar
6.2. Selain itu, pengujian detoksifikasi telah diselesaikan, serta pengujian vendor untuk
pengentalan, pencucian intensif konsentrat gravitasi, filtrasi dan reologi tailing juga telah
diselesaikan.
P:\66021_M\66021_M_J1088_V3.docx 53
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 54
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Pelindian 24 jam diidentifikasi sebagai waktu pelindian yang tepat, karena pelindian lebih lanjut
setelah waktu itu minimal.
Mineralisasi emas biasanya berasosiasi dengan pirit, dengan beberapa emas diskrit. Bahan
karbon umumnya tidak diamati, tetapi penambahan karbon aktif mengurangi preg-robbing dan
CIL dipilih sebagai rute proses.
Mineralogi sampel didominasi oleh silikat (albit dan kuarsa). Mineralisasi major sekunder adalah
karbonat (ankerit).
Gravitasi total desain dan leach extraction digunakan sebesar 91,1%. Perolehan emas untuk
gravity adalah 40%.
DFS fase 2 melakukan pengujian tambahan untuk menghasilkan parameter desain dan
melakukan uji variabilitas pada 18 sampel yang baru dibor. Dua sampel bulk composite juga diuji
untuk mendapatkan sampel yang cukup untuk karakterisasi TUNRA bulk material, uji
pengentalan tailing dan filtrasi, uji reologi, dan uji detoksifikasi sianida curah.
Uji coba fase 2 berhasil menunjukkan kelayakan flowsheet. Tidak ada perubahan yang dibuat
pada asumsi perolehan. Namun, oksigen sparging diganti dengan udara bertekanan rendah,
karena oksigen sparging ditemukan menurunkan kinerja dibandingkan dengan udara (dilaporkan
sebagai tidak ada perbedaan material). Hal tersebut merupakan hasil yang tidak biasa yang harus
diselidiki lebih lanjut. Ini mungkin lebih menarik secara akademis, karena variabilitas dan sampel
massal diuji dengan udara, sehingga ada kepercayaan pada hasil yang diperoleh. Khususnya,
perolehan emas lebih besar dari 90% untuk semua pengujian menggunakan udara dan P80 75
µm.
Perolehan rata-rata di seluruh sampel variabilitas dan komposit adalah 95,2%. Perolehan
minimum adalah 88,8% di mana hanya 2 dari 32 sampel yang kurang dari 90%. Hasilnya
mendukung perolehan keseluruhan sebesar 91,1% dengan perolehan emas gravitasi 40%.
Faktanya, uji coba Tahap 2 menunjukkan hasil ini konservatif dengan beberapa sisi positif,
terutama dalam perolehan emas gravitasi.
Mining One menyatakan tingkat tes dan kesimpulan yang ditarik sesuai dengan tingkat ketelitian
kajian.
6.3 Throughput
Ukuran penggilingan P80 75 µm dipilih berdasarkan pertukaran antara ekstraksi emas yang
ditingkatkan pada ukuran penggilingan yang lebih halus dan biaya pengoperasian sirkuit
penggilingan. Uji kominusi yang signifikan telah diselesaikan di berbagai sampel dan endapan.
Parameter kominusi yang digunakan untuk desain dirangkum dalam Tabel 6.1. Rentang
pengujian yang diselesaikan dan pemilihan parameter desain dianggap tepat oleh Mining One
dan mendukung throughput yang diharapkan.
Table 6.1 Parameter Kominusi
Test Unit Design Basis
Crushing work index CWi kWh/t 17.2 Max
Unconfined compressive strength UCS Mpa 118.2 75th percentile
Axb Axb 60.8 75th percentile
Drop weight index Dwi kWh/m3 4.25 75th percentile
P:\66021_M\66021_M_J1088_V3.docx 55
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Risiko utama untuk throughput tampaknya adalah umpan langsung dari bijih yang hancur, yang
sebagian dimitigasi dengan stickpile darurat bijih hancur (12 jam). Penimbunan ini akan
membantu menjaga ketersediaan untuk waktu henti yang singkat dan perawatan crusher.
P:\66021_M\66021_M_J1088_V3.docx 56
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 57
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Perlu dicatat bahwa daya listrik pabrik di DFS berbeda dengan yang diestimasi dalam studi FEED,
sehingga biaya modal telah berubah sejak DFS, tetapi tidak ditinjau seperti disebutkan di atas.
Rincian biaya modal keseluruhan dari DFS disajikan pada Tabel 6 3.
Table 6.3 Rincian Biaya Modal
WBS Description $US million
100 Mining 18
300 Process plant 49.6
400 TSF 13
500 Infrastructure 13.9
600 Site support facilities 10.7
700 Other 0.3
800 Owners costs
Land acquisition costs 7.2
Construction management 7.9
Other owners costs 12.3
Contingency 12.6
Total Capital cost 145.5
Pre-production mining cost 15.8
LOM sustaining capital cost 28.9
6.6 Kesimpulan
Tidak ditemukan kesalahan fatal dalam proses kajian metalurgi dan pengolahan sehingga
modifying factor untuk aspek ini dalam Estimasi Cadangan Bijih yang dilaporkan dianggap valid
dan dapat dilaporkan sesuai dengan KCMI Code.
Catatan tambahan:
➢ Desain proses adalah sirkuit emas / CIL gravitasi konvensional berisiko rendah.
➢ Asumsi perolehan pabrik dan throughput didukung dengan baik oleh uji tes dan cukup
konservatif untuk memberikan keyakinan bahwa kinerja akan tercapai.
➢ Gravity gold recovery tinggi, dengan desain perolehan sebesar 40%. Keseluruhan perolehan
emas adalah 91,1%.
➢ Beberapa material preg-robbing terdapat dalam bijih, mendukung pemilihan CIL.
➢ Ukuran penggilingan P80 75 µm adalah tipikal untuk pemrosesan CIL.
➢ Pengujian variabilitas dan sampel mendukung asumsi perolehan pabrik yang dapat dicapai
di seluruh deposit. Pengujian variabilitas dan tes dalam skala besar telah dilakukan dengan
memadai untuk tingkat studi. Tes ini dilakukan tanpa penambahan oksigen, yang mendukung
P:\66021_M\66021_M_J1088_V3.docx 58
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
penggunaan blower udara. Namun penurunan kinerja dengan oksigen tidak biasa dan dapat
diselidiki lebih lanjut.
➢ Mineralogi deposit dikarakterisasi dengan baik.
➢ Tes telah dilakukan oleh vendor dan laboratorium yang bereputasi baik dan sesuai untuk
tingkat kajian ini.
➢ Metodologi yang digunakan untuk estimasi biaya operasional dan modal dianggap memadai.
Walaupun detail perhitungan untuk mengestimasi biaya ini tidak dikaji oleh Mining One,
Mining One menganggap estimasi biaya ini wajar dan berada dalam benchmark untuk jenis
operasi yang serupa.
P:\66021_M\66021_M_J1088_V3.docx 59
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 60
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 61
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Gambar 7.2 Rute Akses Utama Site Proyek Emas Awak Mas
Sementara itu, pembangunan jalan perintis telah dimasukkan dalam desain FEED Jalan Akses
Utama di Lokasi. Jalan perintis akan mengakomodasi pembangunan area TSF dan Pabrik
Pengolahan dan untuk konstruksi pekerjaan tanah awal untuk memulai pekerjaan pembukaan
lahan dan cut & fill.
7.1.2 Quarry
Pengembangan awal quarry terletak di barat laut lokasi berdekatan dengan jalan akses yang
menghubungkan pabrik pengolahan dan fasilitas mess permanen.
Awalnya, batuan yang cocok untuk pembuatan material agregat dasar jalan dan agregat beton
akan diambil dari lubang tambang Salu Bulo.
Pengembangan quarry akan dimulai pada tahap pekerjaan awal guna menyediakan dasar jalan
untuk pekerjaan jalan di lokasi. Crushing Plant quarry yang dijelaskan di sini akan menyediakan
bahan yang sesuai untuk digunakan sebagai lapisan dasar jalan, lapisan pondasi dan lapisan
lapisan aus sesuai kebutuhan. Batuan sungai di luar lokasi sesuai kebutuhan akan dibeli dalam
keadaan hancur atau hancur di fasilitas crusher yang menggunakan crushing plant yang sama.
Quarry ini akan digunakan sebagai alternatif jika material dari pekerjaan earthmoving perintis dan
atau dari prestrip pit tidak sesuai dengan tipe material yang diperlukan untuk konstruksi.
P:\66021_M\66021_M_J1088_V3.docx 62
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 63
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
akan dikelola melalui truk yang dilengkapi dengan sistem penyemprotan air. Tipe truk dapat dilihat
pada Gambar 7.3.
P:\66021_M\66021_M_J1088_V3.docx 64
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
7.2.1 Mess
Untuk mengakomodir tenaga kerja operasional telah dilengkapi fasilitas mess dan administrasi
yang dapat digunakan selama tahap konstruksi, jika dikembangkan sebagai bagian dari kegiatan
pekerjaan awal. Mess akan disediakan akomodasi untuk Masmindo dan personil kontraktor.
Mess akan tetap berada di bawah pengawasan dan manajemen Masmindo selama fase
konstruksi dan operasional proyek. Kontraktor pihak ketiga akan dilibatkan untuk berkontribusi
kamp dan lokasi tenaga kerja secara luas serta layanan pembersihan dan pemeliharaan mess.
P:\66021_M\66021_M_J1088_V3.docx 65
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 66
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 67
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 68
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 69
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 70
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Tanggul akhir TSF dan pelimpah permanen ditunjukkan pada Gambar 8.3. Pemilihan lokasi
mempertimbangkan beberapa lokasi alternatif dan lokasi yang dipilih adalah fasilitas
penyimpanan tipe lembah dengan tanggul yang akan dinaikkan ke ketinggian akhir hampir 150
m di atas kaki akhir . Kapasitas penyimpanan tailing adalah sekitar 30 juta m3.
P:\66021_M\66021_M_J1088_V3.docx 71
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Output tailing dari pabrik pengolahan adalah 2,5 juta tonnes kering per tahun dengan asumsi SG
2,7, dan densitas pengendapan kering 1,3 t/m3 (untuk desain). Kapasitas total 30 juta m3 adalah
penyimpanan yang cukup untuk umur tambang, berdasarkan umur 17 tahun, dan total kapasitas
penyimpanan 39 juta t. Elevasi puncak tanggul maksimum adalah 765 mRL.
Bendungan memiliki elevasi puncak tanggul starter 695 mRL (Gambar 8.5).
P:\66021_M\66021_M_J1088_V3.docx 72
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
TSF menggunakan metode konstruksi tanggul zona konvensional. Tidak ada pelapis lantai hulu
yang digunakan, karena terbukti memberikan manfaat yang dapat diabaikan untuk laju rembesan
yang rendah. Metode konstruksi hilir diusulkan untuk kenaikan berkelanjutan. Ketinggian angkat
kira-kira 10 m diantisipasi sampai tingkat maksimum. Karena persyaratan penyimpanan air,
tailing freeboard akan selalu lebih besar dari 2,5 m.
Sebagian besar tanggul dibangun dari batuan sisa tambang pembentuk non-asam, termasuk
zona pengisian curah dan zona filter (screened rock). Material ini bersumber dari lubang tambang
utama dan/atau area quarry. Material “inti” urugan diperkirakan bersumber dari tanah dekat
permukaan terpilih di dalam footpint TSF dan/atau dari lubang tambang atau penggalian tanah
penutup tanah penutup.
P:\66021_M\66021_M_J1088_V3.docx 73
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Penampang desain dapat dilihat pada Gambar 8.5. Lapisan lantai tidak diilustrasikan pada
gambar. Zona 1A adalah "inti timbunan tanah (atau tanah liat)", Zona 2 adalah lapisan filter dan
Zona 3A lapisan pengisi umum. Zona 3C adalah face protection.
P:\66021_M\66021_M_J1088_V3.docx 74
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 75
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 76
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
9.2.3 Iklim
Iklim di lokasi Proyek merupakan ciri khas wilayah Indonesia ini dengan musim hujan dan
kemarau yang cukup berbeda. Meskipun permulaan musim dapat bervariasi antar-tahunan,
biasanya, Juni hingga Oktober mewakili kondisi musim kemarau, Desember hingga April mewakili
kondisi musim hujan dan Mei dan November mewakili bulan peralihan antara musim kemarau
dan musim hujan. Suhu maksimum bulanan di lokasi berkisar antara 25°C hingga 27°C dan
minimum dari 18°C hingga 20°C. Kisaran suhu terutama mencerminkan variabilitas harian dan
umumnya konsisten sepanjang tahun.
Kelembaban relatif bulanan rata-rata tertinggi di Awak Mas terjadi pada bulan Mei (sekitar 98%)
dan terendah pada bulan September (sekitar 88%). Data kecepatan dan arah angin rata-rata
harian menunjukkan bahwa angin dominan adalah timur/timur laut dengan kecepatan rata-rata
berkisar antara 0-1 km/jam (15% waktu), 1-2 km/jam (7% waktu) dan 12-15 km/jam (12% dari
waktu). Selama bulan-bulan terkering Agustus dan September, penguapan melebihi curah hujan
dan oleh karena itu neraca air yang negatif diperkirakan terjadi di lokasi Awak Mas selama bulan-
bulan tersebut.
P:\66021_M\66021_M_J1088_V3.docx 77
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
antara 750 – 1.400 mdpl dengan kemiringan lereng yang bervariasi antara 25°– 60°, mewakili
medan terjal hingga sangat terjal. Dalam bagian timur wilayah proyek dimana aliran sungai dan
sungai sebagian besar mengalir ke arah timur menuju DAS Songgang/Sungai Ranteballa,
ketinggian bervariasi antara 400 hingga 750 mdpl dan kemiringan bervariasi antara 5o – 35o,
mewakili kisaran medan yang landai hingga curam.
9.2.5 Hidrologi
Lokasi Proyek dicirikan oleh medan berbukit yang dipisahkan oleh anak sungai kecil yang
mengalir umumnya ke arah utara dan timur ke sungai Songgang dan Ranteballa. Beberapa anak
sungai di lokasi Proyek mewakili sub-DAS dari DAS Songgang/Sungai Ranteballa, DAS utama
yang menerima limpasan dari lokasi Proyek. Ini termasuk Mapacing Creek, Kanan Creek, Tarra
Creek dan Tuara Creek. Sub-catchment Sungai Salu Bulo, yang menerima limpasan dari area
paling selatan dari lokasi Proyek, adalah sub-catchment dari catchment Sungai Kadundung.
Sungai Ranteballa dan Kadundung bergabung di sebelah tenggara situs membentuk Sungai
Suso yang mengalir ke arah timur. Tingkat debit lebih rendah selama musim kemarau
dibandingkan dengan musim hujan seperti yang diharapkan.
Penduduk setempat menggunakan air sungai terutama untuk keperluan sanitasi (mencuci,
mandi, dll.) serta, dalam kadar yang lebih rendah, sebagai air baku untuk memasak dan minum
(setelah direbus). Pengguna air tambahan di wilayah tersebut terdiri dari fasilitas pembangkit
listrik tenaga mikro hidro di Sungai Ranteballa di timur laut lokasi Proyek dan perusahaan air
minum negara (Perusahaan Daerah Air Minum - PDAM) pengambilan air di Sungai Suso, sekitar
9 km sebelah timur lokasi.
9.2.6 Geokimia
Studi drainase batuan asam/pelindian logam (ARD/ML) telah mengklasifikasikan 15-20% material
batuan sisa yang terganggu oleh Proyek sebagai berpotensi membentuk asam (PAF); namun,
sebagian besar batuan sisa adalah pembentuk non-asam (NAF), dan secara umum batuan sisa
memiliki kapasitas penetralan yang tinggi dan kandungan sulfida-S yang rendah. Uji kinetik pada
sampel limbah PAF menunjukkan pH drainase menjadi stabil pada pH 5, yang menunjukkan
material tersebut memiliki kapasitas PAF yang rendah dan tidak menghasilkan asam yang
berlebihan. Secara kolektif, hasil ini menunjukkan bahwa risiko ISPA/ML yang dihasilkan dari
batuan sisa Awak Mas adalah rendah. Sampel tailing diklasifikasikan sebagai PAF, namun,
karena kondisi penyimpanan jenuh yang diantisipasi untuk sebagian besar tailing, TSF
diharapkan tidak menjadi sumber ARD/ML yang signifikan.
P:\66021_M\66021_M_J1088_V3.docx 78
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
➢ Permintaan oksigen kimia (COD), kebutuhan oksigen biologis (BOD) dan mikrobiologis
parameter (fecal coliform, total coliform dan E. coli) di lokasi pengambilan sampel relatif tinggi
dan mendekati, atau dalam beberapa kasus melebihi standar Indonesia Kelas I dan Kelas II.
Lokasi-lokasi ini dekat dengan desa-desa yang ada dan ditinggikan. Parameter
BOD/COD/mikrobiologi dikaitkan dengan aktivitas manusia dan pembuangan limbah
domestik ke saluran air setempat.
9.2.10 Tanah
Data dasar kualitas tanah di wilayah Proyek diperoleh dari survei lapangan pada tahun 2012.
Berdasarkan peta tanah Wilayah Sulawesi Selatan, jenis tanah di lokasi Proyek didominasi oleh
tanah grumosol dan mediteran. Kedalaman solum sedang (60-120 cm) hingga dalam (>120 cm).
Tanah lapisan atas berwarna hitam dengan bahan organik dan humus yang membusuk.
Kedalaman tanah lapisan atas berkisar antara 20 sampai 40 cm dan meluas hingga lebih dari 40
cm di beberapa lokasi. Tekstur tanah didominasi oleh lempung, lempung berlumpur, dan lempung
liat.
P:\66021_M\66021_M_J1088_V3.docx 79
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 80
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
9.2.14 Demografi
Berdasarkan data statistik Kecamatan Latimojong tahun 2011, jumlah penduduk kelima desa
tersebut kurang lebih 2.300 jiwa yang terdiri dari hampir 700 kepala keluarga. Wilayah Studi 1
merupakan daerah pedesaan dengan kepadatan penduduk yang rendah, berkisar antara 7
orang/km2 (di desa Ranteballa dan Tobarru) hingga 49 orang/km2 (di desa Boneposi). Rasio laki-
laki dan perempuan di daerah penelitian ini adalah 1:1. Selain desa Area 1, ada desa lain yang
membuat total penduduk di Kecamatan Latimojong sebanyak 5.500, per tahun 2011. Sekitar 54%
(atau sekitar 3.000 orang) dari total penduduk dilaporkan dalam usia produktif (15 sampai 59
tahun), bekerja terutama di budidaya tanaman dan kegiatan pertanian lainnya.
Berdasarkan wawancara yang dilakukan di Wilayah Studi 1 pada tahun 2012, dilaporkan bahwa
hingga 29% responden terdaftar di tingkat pendidikan dasar, 44% di tingkat pendidikan
menengah dan 17% di pendidikan tinggi (diploma atau lulusan universitas). Sisanya 10%
responden tidak bersekolah di lembaga pendidikan formal manapun. Terdapat tiga sekolah dasar
(dikenal sebagai sekolah dasar) dan tiga sekolah menengah pertama (dikenal sebagai sekolah
menengah pertama) di Wilayah Studi 1 pada tahun 2011. Data menunjukkan bahwa tingkat
kehadiran di sekolah <60%. Rasio guru dan siswa berkisar antara 1:6 hingga 1:24 yang mungkin
merupakan situasi umum untuk daerah pedesaan seperti Wilayah Studi 1.
9.2.15 Sosial-Ekonomi
Berdasarkan survei tahun 2011 dan 2012, mata pencaharian utama dan penggerak ekonomi
penduduk yang tinggal di Wilayah Studi 1 adalah kegiatan berbasis pertanian, termasuk sawah
dan perkebunan skala kecil (seperti kopi, sagu, cengkeh, kakao dan nilam) dan tanaman (seperti
tomat, cabai dan sayuran).
Pendapatan responden di Wilayah Studi 1 yang diwawancarai pada tahun 2012 berkisar antara
Rp 500.000 dan Rp 4.000.000 per kapita per bulan tergantung pada pekerjaan mereka.
P:\66021_M\66021_M_J1088_V3.docx 81
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
9.3 Dampak Lingkungan dan Sosial yang Dinilai dan Rencana Pengelolaan
Potensi dampak lingkungan dan sosial untuk Proyek telah dinilai melalui proses AMDAL. AMDAL
mengidentifikasi potensi dampak signifikan selama fase konstruksi, operasi dan penutupan
Proyek. Dampak lingkungan dan sosial utama yang dinilai untuk Proyek dan rencana pengelolaan
terkait untuk mengurangi dampak negatif dan meningkatkan dampak positif dirangkum dalam
bagian ini.
P:\66021_M\66021_M_J1088_V3.docx 82
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
dalam batuan sisa dari uji kinetik adalah arsenik, tembaga, besi, nikel dan seng. Mengingat
potensi pembentukan asam yang rendah dari batuan sisa yang diuji, porsi limbah PAF yang relatif
kecil dan adanya potensi netralisasi yang signifikan pada jenis limbah NAF yang tersisa,
Potensi dampak kualitas air yang terkait dengan tailing tambang berasal dari 2 sumber potensial:
i) peningkatan kandungan sianida dan logam dalam fraksi cair tailing yang dibuang ke TSF; dan,
ii) remobilisasi logam dari padatan tailing yang tersimpan di TSF. Pekerjaan uji geokimia pada
tailing dari Proyek telah mengindikasikan bahwa padatan tailing akan menjadi PAF. Tailing akan
disimpan di TSF, dengan mayoritas tailing berada di bawah penutup air atau jenuh secara
permanen. Ini membatasi kinetika oksidasi sulfida dan mencegah pembentukan asam dan
pencucian logam terkait dari tailing yang diendapkan. Oleh karena itu, dampak kualitas air yang
terkait dengan remobilisasi logam dari endapan tailing diperkirakan dapat diabaikan.
Strategi pengelolaan air khusus untuk mengurangi dampak yang terkait dikembangkan oleh
Masmindo.
P:\66021_M\66021_M_J1088_V3.docx 83
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Sumber kontaminan yang signifikan ke udara untuk Proyek adalah emisi Gas Rumah Kaca (GRK)
dari armada pertambangan dan kendaraan ringan, yang akan menggunakan diesel, dan debu
halus (partikulat udara). Emisi debu-debu halus terjadi karena gangguan mekanis material
granular yang terpapar udara. Debu yang dihasilkan dari sumber non-titik ini disebut "buronan"
karena tidak dibuang ke atmosfer dalam aliran aliran terbatas.
P:\66021_M\66021_M_J1088_V3.docx 84
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
visual pada penutupan. Dampak visual dari pit Salu Bulo tidak akan dapat dikembalikan dimana
tembok tinggi dan danau pit akan terlihat setelah penutupan tambang.
Secara keseluruhan, dampak visual yang terkait dengan Tambang Awak Mas pada masyarakat
yang terkena dampak dapat diabaikan dan tidak ada strategi pengelolaan dampak visual fisik
khusus yang diusulkan. Namun, dampak terhadap masyarakat kecil Dusun Bungadidi diharapkan
dapat diperbaiki melalui rencana pengelolaan sosial.
P:\66021_M\66021_M_J1088_V3.docx 85
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
dan tidak digunakan untuk kegiatan konstruksi lokasi akan dikubur (terutama di tempat
pembuangan sampah) di lokasi.
Sampah yang dapat didaur ulang akan dikumpulkan di tempat sampah berkode warna di
beberapa lokasi di lokasi Proyek. Semua sampah daur ulang yang dikumpulkan akan diangkut
ke Resource Recovery Center (RRC) di lokasi dan halaman daur ulang yang akan menjadi area
kerja yang dibangun khusus. RRC akan menampung baling press (untuk kaleng, karton, kertas
dan plastik), meja sortasi dan peralatan penanganan tempat sampah. RRC akan menyediakan
lokasi sentral bagi Masmindo/kontraktor untuk memisahkan dan menyimpan bahan daur ulang
sebelum dikumpulkan oleh kontraktor daur ulang dan/atau diangkut ke pusat daur ulang di luar
lokasi.
Kategori ketiga dari limbah tidak berbahaya yang dihasilkan oleh Proyek adalah limbah
organik/limbah yang terutama merupakan limbah domestik/makanan dari ruang makan, kantor
dan sumber perumahan lainnya, yang akan dibuang di tempat pembuangan limbah domestik
yang diizinkan di lokasi. Selain itu, sampah umum, yang tidak dapat didaur ulang, akan
dikumpulkan di seluruh lokasi Proyek dan dibuang di fasilitas TPA. Fasilitas ini akan terdiri dari
serangkaian parit yang akan digali secara berurutan dan ditutup dengan tanah lapisan atas dan
ditanami kembali setelah kapasitas tercapai. Penutupan dan reklamasi limbah domestik yang
terpapar akan sering dilakukan untuk mengurangi risiko peningkatan populasi hama/kutu di
lokasi.
9.3.7 Dampak yang Dinilai terhadap Pekerjaan Masyarakat dan Pendapatan dan
Manajemen
Dampak besar terhadap lapangan kerja dan pendapatan masyarakat terkait dengan perekrutan
dan pemutusan hubungan kerja tenaga kerja Masmindo untuk Proyek. Rekrutmen selama tahap
konstruksi dan operasi Proyek akan memberikan dampak positif bagi masyarakat yang terkena
dampak, serta daerah lain di Kabupaten Luwu dan Indonesia, sedangkan pengurangan tenaga
kerja dari tahap konstruksi ke tahap operasi dan penghentian pada penutupan tambang akan
berdampak negatif. berdampak pada pekerjaan dan tingkat pendapatan. Rekrutmen dan
pemutusan tenaga kerja Masmindo juga akan berdampak tidak langsung terhadap penyerapan
tenaga kerja dan tingkat pendapatan masyarakat karena berdampak pada penyerapan tenaga
kerja dan pendapatan penduduk lokal yang menyediakan barang dan jasa bagi tenaga kerja
Masmindo. Dampak ini secara keseluruhan akan positif, Rencana pengelolaan umum yang
diusulkan untuk mengatasi dampak ini akan melibatkan penyediaan sumber daya dan dukungan
oleh Masmindo untuk meningkatkan kesempatan kerja bagi penduduk lokal serta
memaksimalkan penyediaan barang dan jasa oleh masyarakat setempat.
9.3.8 Dampak yang Dinilai terhadap Demografi dan Sosial Ekonomi dan Manajemen
Dampak utama pada profil demografis masyarakat yang terkena dampak adalah migrasi masuk
yang terkait dengan tenaga kerja untuk Proyek. Masyarakat lokal memiliki kapasitas sumber daya
manusia yang terbatas, dengan tingkat pertumbuhan penduduk yang lambat. Anggota
masyarakat yang lebih muda, yang mampu, juga meninggalkan daerah tersebut untuk mencari
pendidikan lebih lanjut dan kesempatan kerja ke daerah lain di Kabupaten Luwu atau daerah lain
di Indonesia. Oleh karena itu, relatif sedikit penduduk usia kerja (biasanya berusia 20 hingga 50
tahun). Hal ini mengharuskan Masmindo merekrut dari daerah selain masyarakat yang terkena
dampak untuk memenuhi kebutuhan tenaga kerja untuk pembangunan dan operasi tambang.
Dampak utama terhadap kondisi sosial ekonomi masyarakat yang terkena dampak terkait dengan
dampak positif terkait dengan dimulainya dan beroperasinya Tambang Emas Awak Mas dan
dampak negatif terkait dengan penutupannya.
P:\66021_M\66021_M_J1088_V3.docx 86
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
9.3.9 Dampak yang Dinilai terhadap Infrastruktur dan Layanan dan Manajemen
Sumber utama dampak pada infrastruktur dan layanan yang ada di masyarakat yang terkena
dampak adalah migrasi masuk yang terkait dengan Proyek. Migrasi masuk akan terjadi karena
kurangnya sumber daya manusia lokal untuk memenuhi tenaga kerja yang dibutuhkan untuk
pembangunan dan operasi tambang di masa depan. Migrasi masuk ini akan menambah
permintaan pada daerah yang tidak memiliki infrastruktur dan layanan yang berkembang dengan
baik.
Besarnya dampak terhadap sumber daya dan layanan lokal akan tergantung pada tingkat
pertambahan penduduk akibat migrasi masuk di masyarakat yang terkena dampak. Tenaga kerja
terampil dari tempat lain di Indonesia akan bekerja dengan sistem roster, bertempat tinggal di
camp dan fly-in-fly-out (FIFO). Mayoritas pekerjaan semi-terampil dan tidak terampil yang
bersumber dari daerah lain di Kabupaten akan menggunakan bus-in-bus-out (BIBO) dan akan
bolak-balik antara lokasi tambang dan rumah mereka. Kelompok-kelompok ini tidak akan memiliki
dampak yang signifikan terhadap sumber daya lokal. Namun, sebagian dari pekerjaan semi-
terampil dan tidak terampil dari daerah lain kemungkinan akan dipindahkan (beberapa dengan
keluarga mereka) ke masyarakat yang terkena dampak agar lebih dekat dengan lokasi kerja.
Selain itu, beberapa orang yang tidak dipekerjakan secara langsung oleh Masmindo (yaitu,
mereka yang menyediakan barang dan jasa untuk situs dan karyawannya), akan diharapkan
untuk pindah ke masyarakat lokal karena peningkatan peluang ekonomi. Oleh karena itu,
meskipun jumlah pasti migran ke daerah tersebut tidak dapat diprediksi, beberapa tingkat migrasi
masuk yang terkait dengan pengembangan Proyek tidak dapat dihindari.
Pusat Kesehatan Masyarakat (Puskesmas) di Desa Ranteballa dan posyandu di masyarakat
terdampak memberikan tingkat pelayanan kesehatan tertentu kepada warga setempat. Namun,
masyarakat di daerah pengembangan jauh dari fasilitas kesehatan utama, seperti rumah sakit,
membuat akses ke perawatan kesehatan profesional yang lebih tinggi menjadi mahal. Kurangnya
layanan kesehatan lokal akan diperburuk oleh migrasi masuk yang terkait dengan
pengembangan Proyek. Masmindo akan bekerja sama dengan otoritas kesehatan setempat
untuk memungkinkan otoritas ini meningkatkan kualitas pemberian layanan kesehatan.
Program pelayanan kesehatan akan fokus pada kebutuhan kesehatan masyarakat, termasuk: air
bersih dan sanitasi; kesehatan ibu dan anak; pengendalian malaria; pengendalian tuberkulosis;
pencegahan penyakit menular seksual; dan, pendidikan dan kesadaran masyarakat tentang
masalah kesehatan. Program umum yang digariskan dalam rencana ini akan dirinci dan
diselesaikan setelah berkonsultasi dengan masyarakat yang terkena dampak dan pejabat
departemen kesehatan pemerintah daerah.
Kesempatan pendidikan terbatas di wilayah Proyek, dengan sebagian besar masyarakat hanya
memiliki sekolah dasar yang belum sempurna, dengan tingkat sumber daya manusia dan materi
pembelajaran yang buruk. Imigrasi yang terkait dengan pengembangan Proyek akan
memberikan tekanan tambahan pada infrastruktur pendidikan dan sumber daya manusia yang
sudah terbatas.
P:\66021_M\66021_M_J1088_V3.docx 87
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 88
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
10 EVALUASI EKONOMI
Berdasarkan biaya-biaya ini, nilai NPV proyek diestimasi untuk sebelum pajak dan sesudah
pajak. Sebelum pajak, nilai NPV dan IRR untuk proyek Awak Mas diestimasi masing-masing
P:\66021_M\66021_M_J1088_V3.docx 89
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
sebesar 491 juta USD dan 28%. Sedangkan sesudah pajak, NPV dan IRR diestimasi masing-
masing sebesar 383 juta USD dan 25%. NPV ini dihitung menggunakan discount rate 5%.
P:\66021_M\66021_M_J1088_V3.docx 90
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Site Klasifikasi Tonnes (Juta Tonnes) Kadar Emas (g/t) Kandungan Emas (juta oz)
Terbukti 0 0 0
Awak Mas
Terkira 31,0 1,33 1,33
Terbukti 0,6 1,92 0,04
Salu Bulo
Terkira 1,4 1,93 0,09
Terbukti 0,6 1,92 0,04
Total Terkira 32,4 1,36 1,42
Total 33,0 1,37 1,45
Catatan: Kadar batas 0.5 g/t; kesalahan pembulatan mungkin terjadi
P:\66021_M\66021_M_J1088_V3.docx 91
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Ievan Ludjio
ST Tambang, CPI Perhapi, MAusIMM CP (Min), RPEQ
P:\66021_M\66021_M_J1088_V3.docx 92
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
13 REFERENSI
1. Milad M, Independent Technical Report, Mineral Resource Estimate, Awak Mas Gold
Project, Awak Mas and Salu Bulo Deposits, Cube Consulting Pty Ltd, July 2021.
2. Viqnoriva, SN, Proyek Emas Awak Mas, Laporan Sumber Daya Mineral KCMI untuk PT
Masmindo Dwi Area, September 2021
3. Varco, D., 2021, AMC220029 Awak Mas Ore Reserve Update June 2021, AMC Consultants.
4. Nusantara Resources Limited, 2019, 210-1000-FS-REP-0001 Awak Mas DFS, Chapter1.
Executive Summary.
5. Nusantara Resources Limited, 2019, 210-1000-FS-REP-0007 Awak Mas DFS, Chapter 7
Mining and Ore Reserves.
6. Nusantara Resources Limited, 2019, 210-1000-FS-REP-0009 Awak Mas DFS, Chapter 6B
Geotechnical and Hydrogeology Mining.
7. Herath, A., 2021, AMC220029 Modified WRD Geotech Designs 210601, AMC Consultant.
8. Herath, A., 2021, AMC220029_Geotech Review Pit Designs-Additional Data - 210518, AMC
Consultant.
9. Osiejak, M., 2021, Mineral Resource Block Model Handover Document, Cube Consulting.
10. PT Masmindo Dwi Area, 2021, Dokumen Perhitungan Biaya Rencana Tambang
11. PT. Nadal Persada Utama Raya, 2019, Adendum ANDAL dan RKL-RPL rencana kegiatan
penambangan dan pengolahan dan Pemurnian Emas PT Masmindo Dwi Area, di
Kecamatan Latimojong Kabupaten Luwu, Provinsi Sulawesi Selatan.
12. 20210621 Banking Model AwakMasv1,01_Managment Case(estimation2) V1 – Summary
Financials.xlsx
13. AMC Consultants, 2020, Memo Awak Mas Ore Reserves Update June 2021
14. Coffey Geotechnics, 2021, Factual Geotechnical Report, Awak Mas Gold Project TSF
Detailed Design
15. Coffey Geotechnics, 2021, Geoctechnical Interpretative Report, Awak Mas Gold Project TSF
Detailed Design
16. Coffey Geotechnics, 2021, Design Report, Awak Mas Gold Project TSF Detailed Design
17. Nusantara Resources Limited, 2021, Chapter 8 - Metallurgy and Mineral Processing, Post
Feed 2021 Report.
18. Nusantara Resources Limited, 2021, Chapter 11 – Infrastructure and Non-Processing
Facilities, Post Feed 2021 Report.
19. Consensus Economics Inc, 2021, Energy & Metal Consensus Forecasts, 15 March 2021.
P:\66021_M\66021_M_J1088_V3.docx 93
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Lampiran A
Kode KCMI, Tabel 1
P:\66021_M\66021_M_J1088_V3.docx 94
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Estimasi Deskripsi estimasi Proyek ini dimiliki oleh Nusantara melalui anak
Sumberdaya Mineral Sumberdaya Mineral yang perusahaan yang dimiliki sepenuhnya, PT
untuk konfersi ke digunakan sebagai dasar Masmindo Dwi Area (Masmindo), Estimasi
Cadangan Bijih untuk konversi ke Cadangan Sumberdaya Mineral yang digunakan sebagai
Bijih dasar penentuan Cadagan Bijih untuk Awak Mas
Gold Project (“Proyek”) terdiri dari Deposit Awak
Mas dan Salu Bulo.
P:\66021_M\66021_M_J1088_V3.docx 95
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Kunjungan Lapangan Uraian dari setiap kunjungan Karena keterbatasan perjalanan akibat pandemi
(site) lapangan (site) diambil alih COVID19, kunjungan lapangan oleh CPI tidak
oleh orang yang dilakukan. Observasi dilakukan terhadap foto-
berkompeten dan foto, video dan informasi yang dilakukan oleh
berdasarkan hasil Masmindo. Karena proyek masih dalam tahap
kunjungan tersebut. greenfield, efek dari tidak adanya kunjungan
lapangan dianggap minimum dan tidak akan
Jika tidak ada kunjungan
mempengaruhi pelaporan Cadangan Bijih untuk
lapangan yang dilakukan,
Proyek,
berikan alasan mengenai
hal tersebut.
Status studi Jenis dan tingkat studi yang Estimasi Cadangan Bijih KCMI merupakan hasil
dilakukan untuk kajian terhadap pelaporan laporan Cadangan
memungkinkan Bijih JORC 2021 yang merupakan pemuktahiran
Sumberdaya Mineral dari Definitive Feasibility Study (DFS) dan
dikonversi menjadi Cadangan Bijih JORC 2020 yang diselesaikan
Cadangan Bijih. oleh tim yang terdiri dari personel Masmindo dan
konsultan eksternal independen.
Persyaratan bahwa untuk
setidaknya tingkat Pra-Studi Penilaian mengacu pada pekerjaan yang
Kelayakan telah dilakukan sebelumnya telah diselesaikan oleh DFS dan
untuk mengkonversi Cadangan Bijih JORC 2020 di dua deposit, Awak
Sumberdaya Mineral ke Mas dan Salu Bulo. Kontributor utama DFS dan
Cadangan Bijih. penilaian saat ini termasuk pemilik Masmindo
dan konsultan dari AMC Consultants, Cube
Studi tersebut telah
Consulting, Golder, DRA, Coffey Services,
dilakukan dan akan
Lorax, dan Resindo Resources & Energy
menentukan rencana
(Resindo).
tambang yang dapat dicapai
secara teknis dan ekonomis, Rencana tambang yang diusulkan yang
dan bahwa Faktor mendukung Estimasi Cadangan Bijih dianggap
Pengubah (Modifying dapat dicapai secara teknis. Seluruh usulan
Factors) material telah teknis yang dibuat untuk tahap operasional
dipertimbangkan. melibatkan penerapan teknologi penambangan
terbuka konvensional, pengolahan emas dan
pembuangan tailing yang banyak digunakan
dalam operasi penambangan emas di Indonesia.
P:\66021_M\66021_M_J1088_V3.docx 96
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Parameter kadar Dasar dari nilai kadar batas Kadar batas yang ditetapkan dalam estimasi
batas atau parameter kualitas Cadangan Bijih adalah 0,5 g/t. Nilai tersebut
yang diterapkan. diatas nilai estimasi kadar batas marjinal sekitar
0,4 g/t. Nilai kadar batas dihitung dengan
mempertimbangkan parameter berikut:
• Harga emas.
• Biaya operasional.
• Biaya royalti.
Faktor atau asumsi Metode dan asumsi yang Deposit saat ini yang terkait dengan Proyek
penambangan digunakan seperti yang Emas Awak Mas akan ditambang dengan
dilaporkan dalam dokumen metode penambangan terbuka menggunakan
Pra-Kelayakan atau Studi peralatan penambangan konvensional. Desain
Kelayakan untuk mengubah pit dan desain tempat pembuangan limbah telah
Sumberdaya Mineral diselesaikan sebagai bagian dari penilaian yang
menjadi Cadangan Bijih diperbarui ini. Estimasi Sumberdaya Mineral
(yaitu dengan penerapan Terukur dan Tertunjuk dalam desain pit
faktor-faktor yang sesuai merupakan dasar estimasi Cadangan Bijih.
dengan optimasi atau
Metode penambangan, desain, dan urutan
dengan desain awal atau
ekstraksi yang dipilih disesuaikan dengan
rinci).
kondisi lokal di Indonesia, pemindahan dan
Pilihan, sifat dan kesesuaian penyimpanan batuan sisa, karakteristik badan
metode penambangan yang bijih, meminimalkan pengenceran dan
dipilih dan parameter kehilangan bijih. Urutan ini dirancang untuk
penambangan lainnya menunda pergerakan limbah dan pengeluaran
termasuk masalah desain modal, memanfaatkan kapasitas pabrik proses
terkait seperti pre-strip, yang diusulkan dan mempercepat perolehan kas
akses, dll. bebas dengan cara yang aman dan ramah
lingkungan.
P:\66021_M\66021_M_J1088_V3.docx 97
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 98
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 99
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Faktor atau asumsi Proses metalurgi yang Flowsheet pengolahan, neraca massa, neraca
metalurgi diusulkan dan kesesuaian air, identifikasi peralatan, desain mekanik dan
proses tersebut dengan listrik semuanya dikembangkan dengan standar
gaya mineralisasi. Australia dan sesuai dengan standar Indonesia.
P:\66021_M\66021_M_J1088_V3.docx 100
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Lingkungan Status studi potensi dampak Studi dasar lingkungan yang ekstensif telah
lingkungan dari operasi dilakukan di lokasi Proyek Emas Awak Mas dari
penambangan dan tahun 2013 hingga 2017. Studi tersebut telah
pengolahan. menetapkan database musiman untuk
komponen lingkungan utama, yang meliputi:
Rincian karakteristik batuan
meteorologi, hidrologi, ekologi darat (flora dan
sisa dan pertimbangan
fauna); ekologi perairan (alga, plankton,
lokasi potensial, status opsi
invertebrata bentik, nekton dan biota kandungan
desain yang
logam jaringan); hidrogeologi; kualitas air
dipertimbangkan dan, jika
permukaan; kualitas sedimen sungai/sungai;
berlaku, status persetujuan
tanah, kualitas udara dan kebisingan.
untuk penyimpanan residu
proses dan pembuangan Studi dasar telah dipertimbangkan dalam
limbah harus dilaporkan. penilaian environmental and social impact
assessment (ESIA) untuk proyek Awak Mas.
ESIA (AMDAL) menentukan dampak signifikan
proyek dan rencana pengelolaan lingkungan
telah dikembangkan untuk menghilangkan, dan
jika tidak memungkinkan, mengurangi dampak
lingkungan negatif yang terkait dengan operasi
penambangan dan pengolahan. Pemantauan
komponen utama lingkungan dan sosial akan
dilanjutkan selama tahap konstruksi, operasi dan
penutupan proyek sebagaimana diatur dalam
P:\66021_M\66021_M_J1088_V3.docx 101
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 102
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
Lampiran B
Sertifikat Competent Person Indonesia
P:\66021_M\66021_M_J1088_V3.docx 103
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
P:\66021_M\66021_M_J1088_V3.docx 104
PROYEK EMAS AWAK MAS
LAPORAN CADANGAN BIJIH KCMI
DOCUMENT INFORMATION
Status Final
Version 3
Pathname P:\66021_M PT Masmindo Dwi Area Awak Mas Independent Mine Cost
Estimate\WPO\KCMI Report
Job No 66021_M
1 Draft IL 09/07/2021
2 Draft IL 24/09/2021
3 Final IL 07/04/2022
P:\66021_M\66021_M_J1088_V3.docx 105