DESIGN RIGID PAVEMENT BINA MARGA
menggunakan EXCEL
oleh : Tony Hartono Bagio - Dini Stiyoningsih, 2018
INPUT DATA
DATA AWAL
Perencanaan Jalan = 1
Tipe Jalan (Lajur) =
Tipe Jalan (Arah) =
UR (Umur Rencana) = 30 TAHUN
Tahun Perencanaan = 2021
Kelandaian Rata-rata = 6 %
Kondisi Iklim = 75 mm (curah hujan rata-rata pertahun)
Mutu beton rencana, K = 400 kg/cm²
fc' = 0.83 * K/g = 33.2 MPa g= 10 m/dt²
fy = 420 MPa
Bahu Jalan
Ruji (Dowel)
Lapis Pemecah Ikatan
Es = 2.E+05 Mpa
K- 400 kg/cm²
Ec = 4700√fc' = 4700√33.2
Ec = 27100 Mpa
n= Es/Ec = 200000/27100
n= 7
fs = n * fc' = 7*33.2 = 232.4 Mpa
fs ≈ 0.6 * fy = 0.6*420 = 252 Mpa
using , fs ≈ 230 Mpa
Strength Tension, fcf = 0.75*√(33.2)
fcf = 4.32 MPa
Modulus of rupture, fr = 0.62*√(33.2)
fr = 3.57 MPa
kuat tarik langsung, fct = 0.45 fcf
fct = 1.944 MPa
tegangan lekat, fb = 6.2*√(33.2)
fb = 35.72 MPa
Syarat
fc' ≥ 30 MPa OK
fr ≥ 3 MPa OK
tonyhartonobeton.blogspot.com
1
INPUT CBR
tony@narotama.ac.id
Data CBR
No CBR (%) CBRrerata = 3.36667
1 2.5 CBRmax = 5
2 2.5 CBRmin = 2
3 2 n CBR = 15
4 3
5 3
6 4
7 3
8 5
9 4
10 3
11 2
12 3.5
13 4
14 4
15 5
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
tonyhartonobeton.blogspot.com
2
INPUT LHR
tony@narotama.ac.id
DATA LALU LINTAS
JUMLAH
No. URAIAN
KENDARAAN
1 Mobil Penumpang (T 1.1) 0
2 Bus Besar (T 1.2M) 344
3 Truk 2 sumbu - berat (T 1.2H) 185
4 Truk tandem 3 as (T 1.2.2) 210
5 Truk tandem 4 as (T 1.2.2.2) 73
6 Truk gandeng 4 as (T 1.2 + 2.2) 51
7 Truk 3 sumbu (T 1.2 + 2) 64
8 Truk 5 sumbu (T 1.2.2 + 2.2) 56
9 Truk 6 sumbu (T 1.2.2 + 2.2.2) 31
TOTAL 1014
tonyhartonobeton.blogspot.com
3
CBR - DDT - Kspring
tony@narotama.ac.id
TABEL CBR
JUMLAH
R
DATA 2 21.05263*Ln(2.42) + 3.51553
2 1.41 14 235.6638608 - √(38932.44801 - 561.1672278*2.42)
3 1.91 39 115.075 * Ln(2.42) - 319.0229
4 2.24
5 2.48
6 2.67
7 2.83
8 2.96
9 3.08
10 3.18
Grafik CBR vs k
CARA ANALITIS
n CBR = 15 →R= 3.18 lihat tabel CBR
CBR = CBRrerata - (CBRmax - CBRmin)/R
3.36666666666667 - (5 - 2)/3.18
CBR = 2.42 %
DDT = 3.390
k = 21.05263*Ln(2.42) + 3.51553
k= 22.12 kPa/mm
tonyhartonobeton.blogspot.com
4
LALU LINTAS
tony@narotama.ac.id
JK = Jumlah Kendaraan
JS = Jumlah Sumbu
[C] = [A] * [B]
tonyhartonobeton.blogspot.com
5
PERTUMBUHAN
LALU LINTAS tony@narotama.ac.id
FAKTOR PERTUMBUHAN LALU LINTAS
Tabel Faktor Pertumbuhan
Faktor Pertumbuhan sd 2021 > 2021
Arteri dan perkotaan (%) 7 5
Kolektor rural (%) 3.5 2.5
Jalan desa (%) 1 1
e
R = (1+i)^n / log (1 + i) i = idesign
R = [(1 + 0.05)^30] / [LOGe (1 + 0.05)]
R = (4.32195 - 1)/0.0488
R = 68.086
tonyhartonobeton.blogspot.com
6
PONDASI
BAWAH tony@narotama.ac.id
Rigid Pavement
Pondasi Bawah
Tanah Dasar
tonyhartonobeton.blogspot.com
7
PONDASI
BAWAH tony@narotama.ac.id
Tipe Pondasi
1 BP 100 mm
2 BP 125 mm
3 BP 150 / CBK 100
4 CBK 125
5 CBK 150
tonyhartonobeton.blogspot.com
8
REPETISI BEBAN
tony@narotama.ac.id
tonyhartonobeton.blogspot.com
9
FATIK - EROSI
tony@narotama.ac.id
tplat = 200 mm Rigid Pavement (200) mm
Pondasi Bawah = Beton K ≥ 5 MPa ( 125 mm)
Tebal Pondasi = CBR dasar = 2.42 %
CBR eff = 24.8 % CBR Eff ≥ 24.8 %
CBR asli = 2.42 %
Prakiraan tebal dan jenis Pondasi Bawah CBK , tpondasi(mm) = 123
FATIK & EROSI
No URAIAN AS BS RB FBG BR TE
[1] [2] [3] [4] [10] [11] [12] [13]
1 4 1.1 Mobil Penumpang (T 1.1) STRT 7 0 2 3.85 0.85
2 5 1.2 Mobil Penumpang (T 1.1) STRT 8 0 2 4.4 0.85
3 4 2 Bus Besar (T 1.2M) STRT 26.6 3,745,241 2 14.63 0.85
4 4 3 Truk 2 sumbu - berat (T 1.2H) STRT 44.7 2,014,156 2 24.59 0.85
5 4 4 Truk tandem 3 as (T 1.2.2) STRT 70.1 3,429,508 2 38.56 0.85
6 4 5 Truk tandem 4 as (T 1.2.2.2) STRT 40.5 1,589,550 2 22.28 0.85
7 4 6 Truk gandeng 4 as (T 1.2 + 2.2) STRT 49.1 1,110,507 2 27.01 0.85
8 4 7 Truk 3 sumbu (T 1.2 + 2) STRT 30 1,045,183 2 16.5 0.85
9 4 8 Truk 5 sumbu (T 1.2.2 + 2.2) STRT 58.8 1,524,226 2 32.34 0.85
10 4 9 Truk 6 sumbu (T 1.2.2 + 2.2.2) STRT 52.9 1,012,521 2 29.1 0.85
21 6 2 Bus Besar (T 1.2M) STRG 50.5 3,745,241 4 13.89 1.3
22 6 3 Truk 2 sumbu - berat (T 1.2H) STRG 103.6 2,014,156 4 28.49 1.3
23 6 5 Truk tandem 4 as (T 1.2.2.2) STRG 112.5 1,589,550 4 30.94 1.3
24 6 6.1 Truk gandeng 4 as (T 1.2 + 2.2) STRG 112.6 1,110,507 4 30.97 1.3
25 7 6.2 Truk gandeng 4 as (T 1.2 + 2.2) STRG 84.7 1,110,507 4 23.29 1.3
26 8 6.3 Truk gandeng 4 as (T 1.2 + 2.2) STRG 79 1,110,507 4 21.73 1.3
27 6 7.1 Truk 3 sumbu (T 1.2 + 2) STRG 41 1,045,183 4 11.28 1.3
28 7 7.2 Truk 3 sumbu (T 1.2 + 2) STRG 75 1,045,183 4 20.63 1.3
41 9 4 Truk tandem 3 as (T 1.2.2) STdRG 223.5 6,859,016 8 30.73 1.1
42 9 5 Truk tandem 4 as (T 1.2.2.2) STdRG 200 3,179,100 8 27.5 1.1
43 9 8.1 Truk 5 sumbu (T 1.2.2 + 2.2) STdRG 200.7 3,048,452 8 27.6 1.1
44 10 8.2 Truk 5 sumbu (T 1.2.2 + 2.2) STdRG 142.5 3,048,452 8 19.59 1.1
45 9 9 Truk 6 sumbu (T 1.2.2 + 2.2.2) STdRG 163.6 2,025,043 8 22.5 1.1
47 11 9 Truk 6 sumbu (T 1.2.2 + 2.2.2) STrRG 233.4 3,037,564 12 21.4 0.87
49,439,355
AS Sumbu FKB = 1.1
BS Beban Sumbu (kN) [10] = dari "REPETISI"
RB Repetisi Beban [11] = Tabel Faktor Pembagi
FBG Faktor Pembagi AS FBG
BR Beban Rencana (kN)/roda STRT 2
TE Tegangan Ekivalen STRG 4
STdRG 8
STrRG 12
[12] = FKB * [4] / [11]
[13] = =Fak_TE([3],tplat, CBR_Eff, Bahu)
[13] = merupakan fungsi macro , berdasarkan : Pd T 14 -2003 (Tabel 8 dan Tabel 9 )
Bagian Tegangan Setara
tonyhartonobeton.blogspot.com
10
FATIK - EROSI
tony@narotama.ac.id
Rigid Pavement (200) mm
Pondasi Bawah Beton K ≥ 5 MPa ( 125 mm)
Tanah Dasar CBR dasar = 2.42 %
CBR Eff ≥ 24.8 %
Catatan,
[15] = merupakan fungsi macro , berdasarkan : Pd T 14 -2003 (Gambar 19)
[17] = merupakan fungsi macro , berdasarkan : Pd T 14 -2003 (Tabel 8 dan Tabel 9 )
Bagian Faktor Erosi
[18] = merupakan fungsi macro , berdasarkan : Pd T 14 -2003 (Gambar 20 dan Gambar 21)
tonyhartonobeton.blogspot.com
11
TULANGAN PLAT
tony@narotama.ac.id
PENULANGAN PADA PERKERASAN BERSAMBUNG
Lplat
Lplat
Pplat
tonyhartonobeton.blogspot.com
12
TULANGAN PLAT
tony@narotama.ac.id
PENULANGAN PELAT PERKERASAN BETON
Luas tulangan pada perkerasan ini dihitung dari persamaan sebagai berikut :
Dowel
Pplat
tonyhartonobeton.blogspot.com
13
TULANGAN PLAT
tony@narotama.ac.id
dimana :
Ec = 27100 MPa N/mm2
fct = 1.944 Mpa N/mm2
fb_ = fb/D = 35.72/16
fb_ = 2.2325 Mpa N/mm2
εs = 0.0004
ρ= As/(b * h )
ρ= 1608/(210*1000)
ρ= 0.77%
u= 4/d = 4/(16)
u= 0.25 /mm
n= 7
Lcr = 1.944²/[7*(0.0077²)*0.25*2.2325*{(0.0004 * 27100) - 1.944}]
1833.947 mm syarat Lcr <= 2500 mm
tonyhartonobeton.blogspot.com
14
TULANGAN PLAT
tony@narotama.ac.id
TIE BAR
At = 204 * b * h
I= 38.3 * Ø + 75
L= 750 mm (jarak antara tie Bar , PdT-13-2003, pasal 5.3.6.1)
gunakan Ø = 16 mm
I= 687.8 mm ≈ 700 mm
D16 - 750
210
350 350
Dowel (Ruji)
Tebal pelat Diameter ruji
No
beton, h (mm) (mm)
1 125 < h ≤ 140 20
2 140 < h ≤ 160 24
3 160 < h ≤ 190 28
4 190 < h ≤ 220 33
5 220 < h ≤ 250 36
6 250 < h ≤ 350 38
DOWEL
h = tplat = 210 mm
Ø= 33 mm
L= 450 mm
Sp = 300 mm
210
225 225
P33 - 300
tonyhartonobeton.blogspot.com
15