Anda di halaman 1dari 20

PEMBANGUNAN STASIUN PENGUMPUL

LAPANGAN JATIASRI
No. Doc. JAS-EPC-WKSAI-00-G0-PM-001
PROJECT EXECUTION PLAN Revisi B
Halaman 1 dari 20

NAMA PEMILIK PROYEK : PT. PERTAMINA EP


REGIONAL 2
FUNGSI PROJECT ZONA 7
NAMA PROYEK : PEMBANGUNAN STASIUN PENGUMPUL
JATIASRI
LOKASI : SP JATIASRI
NO. KONTRAK : 002/PEP.80000/SP3MP/2022-S0

REGIONAL 2 – FUNGSI PROJECT ZONA 7


APPROVED FOR CONSTRUCTION

BS/MS TS

C 16 Agt 2022 ISSUED FOR APPROVAL ADN WSN AT BS/MS TS


B 27 Jul 2022 ISSUED FOR REVIEW ADN WSN AT BS/MS TS
A 02 Feb 2022 ISSUED FOR REVIEW RO WB TRI BS/MS TS
REV. TANGGAL DESKRIPSI DISIAPKAN DIPERIKSA DISETUJUI DIPERIKSA DISETUJUI
KONSORSIUM PT. PERTAMINA EP
PT. WAHANAKARSA SWANDIRI
PT.ALDABERTA INDONESIA
TABEL REVISI
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 2 dari 20

REV BAB HALAMA DESKRIPSI KOMENTAR REVISI/TANGGAPAN


N
A 1 Format Cover A, penomoran revisi, ikuti RKS Sudah di revisi
A 1 Format Cover TS Sudah di revisi
A 1 Format Cover Di isikan initial pemeriksa PEP sesuai Sudah di revisi
tabel yang sudah di share melalui
transmittal JAS-EPC-PEP-00-G0-TR-001
A 1 Format Cover initial dan harus di sign sebelum di Sudah di revisi
kirim ke PEP
A 1 Format Cover A Sudah di revisi,
A 1 Format Cover Issued for Review Sudah di revisi
A 1 Format Cover di isikan initial pemeriksa PEP sesuai Sudah di revisi
tabel yang sudah di share melalui
transmittal JAS-EPC-PEP-00-G0-TR-001
A 1 Format Cover isikan dengan initial TS Sudah di revisi
A 1 Format Cover tolong gunakan format tanggal dengan Sudah di revisi
format 02 Feb 2022
A 1 Format Cover Konsorsium Sudah di revisi
A 2 Daftar Isi A Sudah di revisi
A 2 Daftar Isi spasinya mana? Sudah di revisi
A 3 Daftar Isi A Sudah di revisi
A 4 Daftar Isi mana header dokumen seperti Sudah di revisi
halaman sebelumnya?
A 1 5 Lingkup Kerja Ganti dengan project overview Sudah di revisi
Pembangunan SP Jatiasri
A 1 5 Lingkup Kerja KSO buat EPF? Sudah di revisi
Harusnya ada pendahuluan, tujuan, dll
seperti dokumen yang standar
A 1 5 Lingkup Kerja Kelompokan berdasarkan Scope dari Sudah di revisi
masing-masing anggta KSO, mana yang
menjadi scope Aldaberta dan mana
yang menjadi scope Wahanakarsa
A 1 6 Lingkup Kerja pekerjaan instalasi piping system tidak As per RKS, Sudah di
ada details apa saja ? revisi
A 1 6 Lingkup Kerja Pipe support / pipe rack / pipe Termasuk di dalam
stanchion ? Piping System
A 1 7 Lingkup Kerja equipment apa saja? Sudah di revisi
A 1 8 Lingkup Kerja perhatikan cara penulisan, meliputi Sudah di revisi
ukuran font, bullet & numbering, spasi
dan paragraf, dll
A 1 22 Spesifikasi dipisahkan mechanical dan piping Sudah di revisi
Engineering
A 1 22 Spesifikasi Pisah Instrument dengan Electrical Sudah di revisi
Engineering
A 1 23 strategi, milestone dan target pada Sudah ditambahkan
engineering tidak keliatan
A 1 73 Mechanical buatkan bagan mana masuk tahapan Sudah ditambahkan
Installation contruction, mana pre-comm, mana
commissioning, start-up dan uji operasi
sampai handover project
A 1 73 Mechanical jelaskan definisi punch list untuk Sudah ditambahkan
Completion masing-masing step
A 1 74 Mechanical tem apa tim? Sudah di revisi
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 3 dari 20

Acceptance
A 1 98 Commissioning untuk dokumen pre-comm, comm Dokumen pre-comm
& Start-Up kapan dimulai? dan commissioning
Plan sudah mulai di develop
A 1 99 System pre-comm mana? Sudah tergambarkan
Completion pada flowchart. Pre-
Sequence comm masuk diantara
A 1 99 System uji operasi di mana? mechanical completion
Completion dan fase commissioning
Sequence
Uji operasi termasuk
pada saat fase
commissioning

A 1 99 System setiap tahapan ada punch list kah? Punch list ada pada fase
Completion mechanical completion
Sequence setelah inspeksi atau
A 1 99 System BA per equipment atau per sub-sistem walk down
Completion atau per apa? Berita acara per sub
Sequence Harap dijelaskan! system. Sudah
A 1 99 System definisi puch list seperti apa? diperbaiki
Completion
Sequence Punch list muncul ketika
ditemukan adanya
ketidaksesuaian
pekerjaan dengan
desain spesifikasi yang
telah disepakati. Hal ini
terjadi karena adanya
pekerjaan yang terlewat
pada fase konstruksi.
A 1 122 Bagan kapan TBA dilengkapi? Mengacu pada JAS-EPC-
Organisasi WKSAI-00-G0-PM-002
Structure Organization
Chart Document
A 1 124 S-Curve S-curve plan agar disesuaikan dengan Noted, S-Curve
perhitungan progress measurement mengacu pada JAS-EPC-
WKSAI-00-G0-PC-002 S-
Curve
B 1 7 Ruang Lingkup please check Sudah di revisi
B 1 9 Ruang Lingkup Pekerjaan untuk items Safety Sudah ditambahkan
Equipment mana?
Termasuk pondasinya juga
B 1 11 Ruang Lingkup detailkan sesuai dengan dok kontrak Sudah di detailkan
lampiran A.3 18-22A-546-OO-00-HS-
03-EL-001
B 1 13 Ruang Lingkup sesuaikan dengan komen di atas Sudah di detailkan
B 2 16 HSSE sesuaikan dengan HSE Plan Sudah disesuaikan
Coordinator dengan HSE Plan
B Lamp. 23 Engineering ada inter discipline check dan Aktivitas inter-disiplin
A Execution Plan engineering matrix review kah untuk check dan engineering
memastikan kualitas engineering review dilakukan pada
sesuai standard? sub bab 2.4 Engineering
Meeting dan 2.5
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 4 dari 20

Koordinasi Antar
Disiplin yang dilakukan
secara periodik 1
minggu sekali.
B Lamp. 47 Construction kok ada di Com yah?? Sudah direvisi, instalasi
B Execution Plan fire & gas detector
masuk ke dalam sub
bab 1.3.8 Pekerjaan
Instrument
B Lamp. 50 Construction spesific dan detail Sudah direvisi
B Execution Plan
B Lamp. 101 Commissioning LOTO sistem dijalankan ( hardware Ya, sistem LOTO
E Strategy Plan LOTO harus sudah siap) dijalankan untuk
equipmen tertentu
seperti di MCC dan
manual valve di field.
B Lamp. 103 Commissioning Safety Equipment Sudah direvisi
E Strategy Plan
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 5 dari 20

DAFTAR ISI

COVER 1
TABEL REVISI 2
DAFTAR ISI 5
1 PENDAHULUAN

1.1. Project Overview 6

1.2. Ruang Lingkup 6

1.3. Pembagian Lingkup Kerja 10

2 BAGAN ORGANISASI 15
3 SCHEDULE & PROJECT PLANNING CHART 19

3.1. Project Master Schedule 19

3.2. Jam Kerja 19

4 INTERFACE PERUSAHAAN DENGAN KONTRAKTOR 20

~ LAMPIRAN A – ENGINEERING PLAN

~ LAMPIRAN B – PROCUREMENT PLAN

~ LAMPIRAN C – CONSTRUCTION PLAN

~ LAMPIRAN D – QA/QC PLAN

~ LAMPIRAN E – COMMISSIONING STRATEGY PLAN

~ LAMPIRAN F – ORGANIZATION CHART

~ LAMPIRAN G – MASTER SCHEDULE

~ LAMPIRAN H – S-CURVE
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 6 dari 20

1. PENDAHULUAN
1.1. Project Overview
EPF ( Early Production Facilities ) Jatiasri merupakan salah satu fasilitas produksi PT. Pertamina EP yang
terletak di daerah Pamanukan, didesa Pusakaratu, Kec. Pusakanagara, Kabupaten Subang, Jawa Barat
sekitar 110 kilometer dari kota Cirebon. Fasilitas ini digunakan sebagai fasilitas pengumpul dan
pemisahan awal dari produksi sumur minyak dan gas di area Jatiasri ( Sumur JAS-01, Sumur JAS-02,
Sumur JAS-03, Sumur JAS-04 ) dst. Dalam proses pengembangan ini, EPF Jatiasri akan di ganti menjadi
Stasiun Pengumpul (SP) Jatiasri. Lokasi SP Jatiasri pada Koordinat : Lintang : -6.2837418,
Bujur :107.8852472,373 dan dapat dilihat pada gambar di bawah ini.

Untuk menyederhanakan istilah selanjutnya PT PERTAMINA EP akan disebut sebagai PERUSAHAAN, dan
KSO PT. Wahanakarsa Swandiri – PT. Aldaberta Indonesia akan disebut sebagai KONTRAKTOR.

1.2. Ruang Lingkup


Lingkup Pekerjaan dari KONTRAKTOR antara lain :
1.2.1. Pekerjaan Persiapan
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 7 dari 20

1.2.1.1. Perijinan dan Persiapan Kerja.


Pada pekerjaan Pembangunan SP Jatiasri, KONTRAKTOR akan mempersiapkan segala
sesuatu terkait pekerjaan Perijinan dan Persiapan Kerja selama 30 hari kalender. Parallel
yang sudah mendapatkan ijin aktivitas pekerjaan, maka KONTRAKTOR akan memulai
aktivitas pekerjaan.
1.2.1.2. Mobilisasi Peralatan dan Tenaga Kerja.
Pada pekerjaan Pembangunan SP Jatiasri, KONTRAKTOR akan mempersiapkan segala
sesuatu terkait Mobilisasi Peralatan dan Personnel selama estimasi 30 HKL yang meliputi
antara lain, Peralatan Survey dan Pendukungnya: 7 Hari setelah Kick Off Meeting, Personnel
Survey dan Engineering 7 Hari setelah Kick Off Meeting,
1.2.1.3. Pembuatan Temporary Site Office, Temporary Workshop, Temporary Warehouse dan
Laydown Area.
KONTRAKTOR menyediakan Temporary Site Office, Temporary Workshop, Temporary
Warehouse dan Laydown Area yang siap digunakan selambat-lambatnya 30 hari kalender
yang bertempat disekitar area SP Jatiasri,
Dan untuk mendukung komunikasi dan koordinasi dengan PERUSAHAAN maka
KONTRAKTOR akan menyediakan kantor di daerah Cirebon.

1.2.2. Pekerjaan Engineering


1.2.2.1. Process Engineering
1.2.2.2. Process Safety Engineering
1.2.2.3. Mechanical Engineering
1.2.2.4. Piping Engineering
1.2.2.5. Electrical Engineering
1.2.2.6. Instrument Engineering
1.2.2.7. Civil Engineering

1.2.3. Pekerjaan Mekanikal


1.2.3.1. Pengadaan dan Instalasi MP Production Separator
1.2.3.2. Pengadaan dan Instalasi MP Test Separator
1.2.3.3. Pengadaan dan Instalasi Gas Scrubber
1.2.3.4. Pengadaan dan Instalasi LP Production Separator
1.2.3.5. Pengadaan dan Instalasi LP Test Separator
1.2.3.6. Pengadaan dan Instalasi Closed Drain Vessel
1.2.3.7. Pengadaan dan Instalasi Settling Tanks
1.2.3.8. Pengadaan dan Instalasi Test Tanks
1.2.3.9. Pengadaan dan Instalasi Crude Oil Storage Tanks
1.2.3.10. Pengadaan dan Instalasi Produced Water Storage Tanks
1.2.3.11. Pengadaan dan Instalasi Diesel Storage Tank
1.2.3.12. Pengadaan dan Instalasi Service and Potable Water Tank
1.2.3.13. Pengadaan dan Instalasi Stabilization Pumps
1.2.3.14. Pengadaan dan Instalasi Liquid Transfer Pumps
1.2.3.15. Pengadaan dan Instalasi Crude Oil Export Pumps
1.2.3.16. Pengadaan dan Instalasi Produced Water Export Pumps
1.2.3.17. Pengadaan dan Instalasi Diesel Transfer Pumps
1.2.3.18. Pengadaan dan Instalasi Closed Drain Pump
1.2.3.19. Pengadaan dan Instalasi Open Drain Pump
1.2.3.20. Pengadaan dan Instalasi Flare KO Drum
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 8 dari 20

1.2.3.21. Pengadaan dan Instalasi Flare KO Drum Pump


1.2.3.22. Pengadaan dan Instalasi Well Water Pump
1.2.3.23. Pengadaan dan Instalasi Service and Potable Water Pump
1.2.3.24. Pengadaan dan Instalasi Gas Pig Launcher
1.2.3.25. Pengadaan dan Instalasi Crude Oil Stabilzation Package
1.2.3.26. Pengadaan dan Instalasi Fuel Gas Scrubber
1.2.3.27. Pengadaan dan Instalasi Fuel Gas Filter
1.2.3.28. Pengadaan dan Instalasi Flare Package
1.2.3.29. Pengadaan dan Instalasi Vent Tip
1.2.3.30. Pengadaan dan Instalasi Air Compressor Package
1.2.3.31. Pengadaan dan Instalasi Utility Air Receiver
1.2.3.32. Pengadaan dan Instalasi Instrument Air Receiver
1.2.3.33. Pengadaan dan Instalasi Potable Water Filter Package
1.2.3.34. Pengadaan dan Instalasi Fire Water Pump
1.2.3.35. Pengadaan dan Instalasi Jockey Pump
1.2.3.36. Pengadaan dan Instalasi Foam Package
1.2.3.37. Pengadaan dan Instalasi Chemical Injection Package
1.2.3.38. Pengadaan dan Instalasi Piping System
1.2.3.38.1. Atmospheric Vent (VA)
1.2.3.38.2. Closed Drain (DC)
1.2.3.38.3. Chemical Injection (CI)
1.2.3.38.4. Diesel Fuel (FO)
1.2.3.38.5. Fuel Gas (FG)
1.2.3.38.6. Firewater (WF)
1.2.3.38.7. Freshwater (WR)
1.2.3.38.8. High Pressure Flare (VH)
1.2.3.38.9. Instrument Air (AI)
1.2.3.38.10. Open Drain (DO)
1.2.3.38.11. Process Gas (PG)
1.2.3.38.12. Process Liquid (PL)
1.2.3.38.13. Production Fluid (PF)
1.2.3.38.14. Produced Water (WP)
1.2.3.38.15. Utility/Plan Air (AP)
1.2.3.38.16. Utility Water (WU)
1.2.3.38.17. Vessel Trim

1.2.4. Pekerjaan Sipil


1.2.4.1. Pekerjaan Land Preparation, Finishing Grading, Road & Pavement (termasuk pembuatan
jalan akses menuju lokasi SP)
1.2.4.2. Pembuatan Pagar Keliling SP (Fence)
1.2.4.3. Pembuatan Sistem Drainase dan Sewer (Sewer and Drainage)
1.2.4.4. Pembuatan Bundwall Tangki (Tank Dike)
1.2.4.5. Pembuatan Control Room (termasuk minilab dan electrical room) termasuk bangunannya
1.2.4.6. Pembuatan Ware House dan bangunannya
1.2.4.7. Pembuatan Fire Water Pond
1.2.4.8. Pembuatan Pondasi Equipment
1.2.4.8.1. Pembuatan Pondasi MP Production Separator
1.2.4.8.2. Pembuatan Pondasi LP Production Separator
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 9 dari 20

1.2.4.8.3. Pembuatan Pondasi MP Test Separator


1.2.4.8.4. Pembuatan Pondasi LP Test Separator
1.2.4.8.5. Pembuatan Pondasi Crude Oil Stabilization Package
1.2.4.8.6. Pembuatan Pondasi Stabilization Pumps
1.2.4.8.7. Pembuatan Pondasi Liquid Transfer Pumps
1.2.4.8.8. Pembuatan Pondasi Crude Oil Export Pumps
1.2.4.8.9. Pembuatan Pondasi Produced Water Pumps
1.2.4.8.10. Pembuatan Pondasi Diesel Transfer Pumps
1.2.4.8.11. Pembuatan Pondasi Open Drain Pump
1.2.4.8.12. Pembuatan Pondasi Well Water Pumps
1.2.4.8.13. Pembuatan Pondasi Service & Potable Water Pump
1.2.4.8.14. Pembuatan Pondasi Fire Water Pumps
1.2.4.8.15. Pembuatan Pondasi Jockey Pumps
1.2.4.8.16. Pembuatan Pondasi Gas Scrubber
1.2.4.8.17. Pembuatan Pondasi Gas Pig Launcher
1.2.4.8.18. Pembuatan Pondasi Closed Drain Vessel dan Pump
1.2.4.8.19. Pembuatan Pondasi Flare KO Drum dan Pump
1.2.4.8.20. Pembuatan Pondasi Settling Tank
1.2.4.8.21. Pembuatan Pondasi Crude Oil Storage Tank
1.2.4.8.22. Pembuatan Pondasi Produced Water Storage Tank
1.2.4.8.23. Pembuatan Pondasi Test Tank
1.2.4.8.24. Pembuatan Pondasi Diesel Storage Tank
1.2.4.8.25. Pembuatan Pondasi Service & Potable Water Tank
1.2.4.8.26. Pembuatan Pondasi Fuel Gas Scrubber
1.2.4.8.27. Pembuatan Pondasi Fuel Gas Filter
1.2.4.8.28. Pembuatan Pondasi Chemical Injection Package
1.2.4.8.29. Pembuatan Pondasi Air Compressor Package
1.2.4.8.30. Pembuatan Pondasi Utility Air Receiver
1.2.4.8.31. Pembuatan Pondasi Instrument Air Receiver
1.2.4.8.32. Pembuatan Pondasi Water Filter Package
1.2.4.8.33. Pembuatan Pondasi Foam Package
1.2.4.8.34. Pembuatan Pondasi Gas Engine Generator
1.2.4.8.35. Pembuatan Pondasi Diesel Engine Generator
1.2.4.8.36. Pembuatan Pondasi Flare Package
1.2.4.8.37. Pembuatan Pondasi Gas Metering Package
1.1.1.1. Pembuatan Shelter Equipment
1.2.4.8.38. Pembuatan Power Generator shelter dan struktur
1.2.4.8.39. Pembuatan Transfer Pump Area shelter area dan struktur
1.2.4.8.40. Pembuatan Fire Water Pump shelter dan struktur
1.2.4.8.41. Pembuatan Closed Drain Pump & Flare KO Drum Pump shelter dan struktur
1.2.4.8.42. Pembuatan Stabilization Pump shelter area dan struktur
1.2.4.8.43. Pembuatan Air Compressor shelter dan struktur
1.2.4.8.44. Pembuatan Open Drain Pump shelter dan struktur
1.2.4.8.45. Pembuatan Diesel Transfer Pump shelter dan struktur
1.2.4.8.46. Pembuatan Well Water Pump shelter dan struktur
1.2.4.8.47. Pembuatan Service & Potable Water Pump shelter dan struktur
1.1.1.2. Pembuatan Bangunan Post Security dan Parking Area (untuk 6 mobil)
1.1.1.3. Pembuatan Pondasi Pipe Rack dan struktur
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 10 dari 20

1.1.1.4. Pembuatan Pondasi Pipe Bridge dan struktur


1.1.1.5. Pembuatan Pondasi Pipe Support dan Pipe Sleeper
1.1.1.6. Pembuatan API Separator / Oil Catcher / Open Drain Pit

1.1.2. Pekerjaan Elektrikal


1.1.2.1. Pengadaan dan InstalasiSwitchgear/MCC
1.1.2.2. Pengadaan dan Instalasi UPS dan Battery
1.1.2.3. Pengadaan dan Instalasi Small power distribution panel
1.1.2.4. Pengadaan dan Instalasi Power, Control, Lighting, Grounding Cable dan Cable Ladder / Tray
1.1.2.5. Pengadaan dan Instalasi Panel Lampu
1.1.2.6. Pengadaan dan Instalasi Lampu
1.1.2.7. Pengadaan dan Instalasi Lightning Protection

1.1.3. Pekerjaan Instrument


1.1.3.1. Pengadaan dan Instalasi HMI & Process and Safety Control System
1.1.3.2. Relokasi dan Instalasi Custody Gas Metering System
1.1.3.3. Pengadaan dan Instalasi Analyzer & Sampling Unit.
1.1.3.4. Pengadaan dan Instalasi Pressure Safety Valve
1.1.3.5. Pengadaan dan Instalasi Breather Valve
1.1.3.6. Pengadaan dan Instalasi Control Valve
1.1.3.7. Pengadaan dan Instalasi Actuated On-off Valve
1.1.3.8. Pengadaan dan Instalasi Pressure Regulator Valve
1.1.3.9. Pengadaan dan Instalasi Fire & Gas Detector
1.1.3.10. Pengadaan dan Instalasi Field Instrument (electronic transmitter dan local gauge, switch
dll.)
1.1.3.11. Pengadaan dan Instalasi Instrument Cable, Cable Tray, & Junction Box

1.1.4. Pekerjaan Safety Equipment


1.1.4.1. Pengadaan First Aid Kit
1.1.4.2. Pengadaan Stretcher
1.1.4.3. Pengadaan dan Instalasi Safety Sign & Notice beserta pondasi.
1.1.4.3.1. Fire Fighting Sign
1.1.4.3.2. Escape Route Sign
1.1.4.3.3. Safety Equipment Sign
1.1.4.4. Pengadaan dan Instalasi Emergency Shower dengan Eyewash Station.
1.1.4.5. Pengadaan dan Instalasi Smoke-escape Mask Hood
1.1.4.6. Pengadaan dan Instalasi Safety Cabinet

1.1.5. Pekerjaan Comissioning


1.1.5.1. Pembuatan Standard Operating Procedure
1.1.5.2. Pre-Commissioning & Testing (Individual Test)
1.1.5.3. Commisioning & Start Up
1.1.5.4. Training on Site
1.1.5.5. Sertifikasi Seluruh Peralatan Fasilitas Produksi dan Pengurusan Surat Persetujuan Layak
Operasi

1.1.6. Masa Pendampingan Operasi dan Maintenance (Masa Pemeliharaan)


PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 11 dari 20

1.3. Pembagian Lingkup Kerja


Pada pekerjaan Pembangunan SP Jatiasri, KONTRAKTOR bekerja sama dan saling berkoordinasi, serta
membagi ruang lingkup kerja masing-masing anggota konsorsium sebagai berikut :

NO URAIAN PEKERJAAN WKS AI

1 PROJECT MANAGEMENT    
1,1 Site Office (Fabrication, Construction and Commissioning X X
1,2 Miscellaneous (Site Office, Radio Communication, PPE, etc) X
1,3 Coordination Meeting X
2 ENGINEERING WORK
2,1 Pre-Engineering Survey X
2,2 Detail Design & Construction Engineering X
2,3 QA/QC Document X
2,4 Installation Procedure X
2,5 Coordination Meeting X
2,6 HAZOP/ HAZID X

3 PROCUREMENT    
3,1 Mechanical Equipment Procurement    
3.1.1 Tank    
3.1.1.1 Settling Tank X
3.1.1.2 Crude Oil Storage Tank X
3.1.1.3 Produced Water Storage Tank X
3.1.1.4 Test Tank X
3.1.1.5 Diesel Storage Tank X
3.1.1.6 Service & Potable Water Tank X
3.1.2 Pump
3.1.2.1 Stabilization Pumps X
3.1.2.2 Liquid Transfer Pumps X
3.1.2.3 Crude Oil Export Pumps X
3.1.2.4 Produced Water Export Pumps X
3.1.2.5 Diesel Transfer Pumps X
3.1.2.6 Closed Drain Pumps X
3.1.2.7 Open Drain Pumps X
3.1.2.8 Flare KO Drum Pumps X
3.1.2.9 Well Water Pumps X
3.1.2.10 Service & Potable Water Pumps X
3.1.2.11 Jockey Pump X
3.1.3 Pressure Vessel
3.1.3.1 MP Production Separator X
3.1.3.2 LP Production Separator X
3.1.3.3 MP Test Separator X
3.1.3.4 LP Test Separator X
3.1.3.5 Gas Scrubber X
3.1.3.6 Gas Pig Launchers X
3.1.3.7 Closed Drain Vessel X
3.1.3.8 Flare KO Drum X
3.1.4 Packages
3.1.4.1 Crude Oil Stabilization Package X
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 12 dari 20

3.1.4.2 Gas Metering Package


3.1.4.3 Fuel Gas System Package X
3.1.4.4 Flare Tip Package X
3.1.4.5 Vent Tip Package X
3.1.4.6 Air Compressor Package X
3.1.4.7 Utility Air Receiver Package X
3.1.4.8 Air Dryer Package X
3.1.4.9 Instrument Air Receiver Package X
3.1.4.10 Water Filter Package X
3.1.4.11 Fire Water Pump Packages X
3.1.4.12 Foam Package X
3.1.4.13 Chemical Injection Package X
3.1.4.14 Diesel Engine Generator (DEG) Package X
3,2 Piping System Material Procurement X
3,3 Electrical Material & Equipment
3.3.1 LV Switchgear/MCC (2-13-SWG-01) X
3.3.2 230V AC UPS System (2-13-UPS-01) X
3.3.3 Lighting Panel and Small Power Panel (2-13-LP-01 and 2-13-LP-02) X
3.3.4 Bulk Material
3.3.4.1 Lighting System X
3.3.4.2 Local Control Station X
3.3.4.3 Power Cable X
3.3.4.4 Cable Gland X
3.3.4.5 Cable Ladder X
3.3.4.6 Grounding & Lightning Protection X
3.3.4.7 Multi Cable Transit (MCT) X
3,4 Instrument Material & Equipment
3.4.1 FIRE & GAS DETECTOR X
3.4.2 CONTROL VALVES X
3.4.3 SHUTDOWN VALVES X
3.4.4 PRESSURE SAFETY/RELIEF VALVES X
3.4.5 PRESSURE REGULATING VALVES (PRV) X
3.4.6 PRESSURE VACUUM SAFETY VALVE (PVSV) X
3.4.7 FIELD INSTRUMENT
3.4.7.1 TEMPERATURE TRANSMITTER X
3.4.7.2 LEVEL GAUGE AND LEVEL INDICATOR FOR TANK AND VESSEL   X
3.4.7.3 LEVEL TRANSMITTER FOR TANK AND VESSEL   X
3.4.7.4 PRESSURE GAUGE   X
3.4.7.5 PRESSURE TRANSMITTER   X
3.4.7.6 TEMPERATURE GAUGE/THERMOWELL   X
3.4.7.7 TEMPERATURE ELEMENT   X
3.4.7.8 FLOW ELEMENT   X
3.4.7.9 PIG SIGNALLER   X
3.4.7.10 ROTAMETER   X
3.4.7.11 LEVEL SWITCH   X
3.4.8 BULK INSTRUMENT MATERIAL    
3.4.8.1 CABLES X  
3.4.8.2 JUNCTION BOX X  
3.4.8.3 CABLE GLAND & ACCESSORIES X  
3.4.8.4 WIRING ACCESSORIES X  
3.4.8.5 EARTHING X  
3.4.8.6 MULTI CABLE TRANSIT X  
3.4.8.7 CABLE LADDER, FITTING AND ACCESSORIES (STEEL HOT DIP X  
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 13 dari 20

GALVANIZED AFTER FABRICATION)


3.4.8.8 CABLE TRAY, FITTING AND ACCESSORIES (STEEL HOT DIP  
GALVANIZED AFTER FABRICATION) X
3.4.8.9 TUBING, FITTING & ACCESSORIES X  
3.4.8.10 STEEL SUPPORT & ACCESSORIES X  
3.4.8.11 Concrete Base Support X
3.4.9 PCS - SIS System   X
3,5 HSE Material & Equipment
3.5.1 Safety Equipment  
3.5.1.1 First Aid Kit X
3.5.1.2 Stretcher X
3.5.1.3. Safety Sign and Notice X
3.5.1.4 Emergency Shower with Eyewash Station X
3.5.1.5 Smoke-escape Mask Hood X
3.5.1.6 Safety Cabinet X
3.5.2 Fire Fighting Equipment  
3.5.2.1 Portable Dry Chemical Fire Extinguisher X
3.5.2.2 Portable Carbon Dioxide (CO2) Fire Extinguisher X
3.5.2.3 Wheeled Dry Chemical Fire Extinguisher X
3.5.2.4 Fire Monitor X  
3.5.2.5 Fire Hydrant X
 

4 CONSTRUCTION AND INSTALLATION  


4,1 Mechanical Equipment Installation  
4.1.1 Tank Installation  
4.1.1.1 Settling Tank Installation X  
4.1.1.2 Crude Oil Storage Tank Installation X  
4.1.1.3 Produced Water Storage Tank Installation X  
4.1.1.4 Test Tank Installation X  
4.1.1.5 Diesel Storage Tank Installation X  
4.1.1.6 Service & Potable Water Tank Installation X  
4.1.2 Pump Installation    
4.1.2.1 Stabilization Pumps Installation X  
4.1.2.2 Liquid Transfer Pumps Installation X  
4.1.2.3 Crude Oil Export Pumps Installation X  
4.1.2.4 Produced Water Export Pumps Installation X  
4.1.2.5 Diesel Transfer Pumps Installation X  
4.1.2.6 Closed Drain Pumps Installation X  
4.1.2.7 Open Drain Pumps Installation X  
4.1.2.8 Flare KO Drum Pumps Installation X  
4.1.2.9 Well Water Pumps Installation X  
4.1.2.10 Service & Potable Water Pumps Installation X  
4.1.2.11 Jockey Pump Installation X  
4.1.3 Pressure Vessel Installation    
4.1.3.1 MP Production Separator Installation X  
4.1.3.2 LP Production Separator Installation X  
4.1.3.3 MP Test Separator Installation X  
4.1.3.4 LP Test Separator Installation X  
4.1.3.5 Gas Scrubber Installation X  
4.1.3.6 Gas Pig Launchers Installation X  
4.1.3.7 Closed Drain Vessel Installation X  
4.1.3.8 Flare KO Drum Installation X  
4.1.4 Packages Installation    
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 14 dari 20

4.1.4.1 Crude Oil Stabilization Package Installation X  


4.1.4.2 Gas Metering Package Installation (Relokasi Meter dari SP PDT  
ke SP Jatiasri) X
4.1.4.3 Fuel Gas System Package Installation X  
4.1.4.4 Flare Tip Package Installation X  
4.1.4.5 Vent Tip Package Installation X  
4.1.4.6 Air Compressor Package Installation X  
4.1.4.7 Utility Air Receiver Package Installation X  
4.1.4.8 Air Dryer Package Installation X  
4.1.4.9 Instrument Air Receiver Package Installation X  
4.1.4.10 Water Filter Package Installation X  
4.1.4.11 Fire Water Pump Packages Installation X  
4.1.4.12 Foam Package Installation X  
4.1.4.13 Chemical Injection Package Installation X  
4.1.4.14 Diesel Engine Generator (DEG) Package Installation X  
4,2 Piping Construction X  
4,3 Electrical Construction & Installation    
4.3.1 LV Switchgear/MCC (2-13-SWG-01) Installation X  
4.3.2 230V AC UPS System (2-13-UPS-01) Installation X  
4.3.3 Lighting Panel and Small Power Panel (2-13-LP-01 and 2-13-LP-02)  
Installation X
4.3.4 Bulk Material Installation    
4.3.4.1 Lighting System Installation X
4.3.4.2 Local Control Station Installation X
4.3.4.3 Power Cable Installation X
4.3.4.4 Cable Gland Installation X
4.3.4.5 Cable Ladder Installation X
4.3.4.6 Grounding & Lightning Protection Installation X
4.3.4.7 Multi Cable Transit (MCT) Installation X
4,4 Instrument Material Installation
4.4.1 Install FIRE & GAS DETECTOR X
4.4.2 Install CONTROL VALVES X  
4.4.3 Install SHUTDOWN VALVES X  
4.4.4 Install PRESSURE SAFETY/RELIEF VALVES X  
4.4.5 Install PRESSURE REGULATING VALVES (PRV) X  
4.4.6 Install PRESSURE VACUUM SAFETY VALVE (PVSV) X  
4.4.7 Install FIELD INSTRUMENT  
4.4.7.1 Install TEMPERATURE TRANSMITTER X  
4.4.7.2 Install LEVEL GAUGE AND LEVEL INDICATOR FOR TANK AND  
VESSEL X
4.4.7.3 Install LEVEL TRANSMITTER FOR TANK AND VESSEL X  
4.4.7.4 Install PRESSURE GAUGE X  
4.4.7.5 Install PRESSURE TRANSMITTER X  
4.4.7.6 Install TEMPERATURE GAUGE/THERMOWELL X  
4.4.7.7 Install TEMPERATURE ELEMENT X  
4.4.7.8 Install FLOW ELEMENT X  
4.4.7.9 Install PIG SIGNALLER X  
4.4.7.10 Install ROTAMETER X  
4.4.7.11 Install LEVEL SWITCH X  
4.4.8 Install BULK INSTRUMENT MATERIAL  
4.4.8.1 Install CABLES X  
4.4.8.2 Install JUNCTION BOX X  
4.4.8.3 Install CABLE GLAND & ACCESSORIES X  
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 15 dari 20

4.4.8.4 Install WIRING ACCESSORIES X  


4.4.8.5 Install EARTHING X  
4.4.8.6 Install MULTI CABLE TRANSIT X  
4.4.8.7 Install CABLE LADDER, FITTING AND ACCESSORIES (STEEL HOT  
DIP GALVANIZED AFTER FABRICATION) X
4.4.8.8 Install CABLE TRAY, FITTING AND ACCESSORIES (STEEL HOT DIP
GALVANIZED AFTER FABRICATION) X
4.4.8.9 Install TUBING, FITTING & ACCESSORIES X
4.4.8.10 Install STEEL SUPPORT & ACCESSORIES X
4.4.8.11 Install Concrete Base Support X
4.4.9 Install PCS - SIS System X
4,5 Civil Construction
4.5.1 LAND PREPARATION, FINISHING GRADING, ROAD & PAVEMENT X
4.5.2 FENCE X
4.5.3 SEWER AND DRAINAGE X
4.5.4 TANK DIKE X
4.5.5 CONTROL ROOM X
4.5.6 WAREHOUSE X
4.5.7 FIRE WATER POND X
4.5.8 OVERALL EQUIPMENT FOUNDATION X
4.5.9 PIPE SLEEPER X
4.5.10 PIPE RACK X
4.5.11 PIPE BRIDGE X
4.5.12 OVERALL EQUIPMENT SHELTER X  
4.5.13 GUARD POST X  
4,6 HSE Material Installation  
4.6.1 Safety Equipment Installation  
4.6.1.1 First Aid Kit X
4.6.1.2 Stretcher X
4.6.1.3 Safety Sign and Notice X
4.6.1.4 Emergency Shower with Eyewash Station X
4.6.1.5 Smoke-escape Mask Hood X
4.6.1.6 Safety Cabinet X
4.6.2 Fire Fighting Equipment Installation
4.6.2.1 Portable Dry Chemical Fire Extinguisher X
4.6.2.2 Portable Carbon Dioxide (CO2) Fire Extinguisher X
4.6.2.3 Wheeled Dry Chemical Fire Extinguisher X
4.6.2.4 Fire Monitor X  
4.6.2.5 Fire Hydrant X  

5 PRE-COMMISSIONING, COMMISSIONING & START-UP


5,1 Pre_Commissioning X
5,2 Commissioning Team X
5,3 Spare Parts and First Fill X X
5,4 Vendor Support X X

6 FINISHING
6,1 DEMOLITION X
6,2 DEMOBILISATION X
6,3 SERTIFIKASI X
 
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 16 dari 20

2. BAGAN ORGANISASI
Bagan Organisasi untuk proyek ini mengacu pada dokumen JAS-EPC-WKSAI-00-G0-PM-002 Structure
Organization Chart.
Sesuai dengan kebutuhan PERUSAHAAN, KONTRAKTOR menugaskan Project Manager, Site Manager,
Construction Superintendent, Project Control, dan para Engineer akan bekerja berdasarkan sistem matriks. Tim
Manajemen Proyek (PMT) dibentuk dalam organisasi Proyek yang dipimpin oleh Project Manager. Untuk tugas,
tanggung jawab serta alur komunikasi tim proyek sesuai dengan bagan organisasi.

2.1. Project Manager


Proyek ini akan berada dibawah pengawan Project Manajer dan sebagai manajemen teratas selama
pelaksanaan proyek.
2.1.1. Peran
 Mengelola dan mengatur organisasi di Site
 Menyediakan sumber daya yang produktif dan memadai sebagai persyaratan kontrak
 Menjaga sumber daya di jalur yang tepat untuk mencapai tujuan yang ditentukan
 Delegasikan semua pekerjaan secara efisien kepada bawahan dan pengukuran produktivitas
 Melakukan rapat koordinasi eksternal dan internal secara berkala dan melaksanakan
pengontrolan tim proyek dengan tetap menjaga kedisiplinan, kerja tim, produktivitas, dan
moral
2.1.2. Tanggung Jawab
 Mengelola proyek secara keseluruhan
 Bertanggung jawab untuk memantau, mengontrol dan menjaga kinerja proyek ke dalam
semua aspek seperti: HSE, Kualitas, produktifitas sesuai dengan tata waktu yang sudah
ditentukan
 Melaporkan kepada Direktur Proyek dan perwakilan Pertamina EP secara berkala semua
perkembangan proyek
 Project Manager harus menjalankan serta memelihara komunikasi yang baik kepada
semua stake holder yang terlibat dalam pelaksanaan proyek
 Membuat laporan secara berkala kepada Pertamina EP sehubungan dengan koordinasi
dan pengendalian proyek, serta menghadiri rapat koordinasi dengan Pertamina EP
 Membentuk, menjalankan dan memelihara kinerja tim proyek tetap solid dan
berorientasi pada target penyelesaian proyek dengan tetap mengutamakan aspek HSE

2.2. Site Manager


2.2.1. Peran
 Mengelola dan mengatur organisasi di Site
 Menyediakan sumber daya yang produktif dan memadai sebagai persyaratan kontrak
 Menjaga sumber daya di jalur yang tepat untuk mencapai tujuan yang ditentukan
 Delegasikan semua pekerjaan secara efisien kepada bawahan dan pengukuran
produktivitas
 Melakukan rapat koordinasi eksternal dan internal secara berkala dan melaksanakan
pengontrolan tim proyek dengan tetap menjaga kedisiplinan, kerja tim, produktivitas, dan
moral
 Mengadakan koordinasi intensif dengan Project Manager, Superintendent dan team.
2.2.2. Tanggung Jawab
 Mengelola pelaksanaan proyek dilapangan sesuai dengan dokumen yang telah disetujui
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 17 dari 20

 Bertanggung jawab untuk memantau, mengontrol dan menjaga kinerja proyek ke dalam
semua aspek seperti: HSE, Kualitas, produktifitas sesuai dengan tata waktu yang sudah
ditentukan
 Melaporkan kepada Project Manager secara berkala semua kemajuan konstruksi di proyek
 Site Manager harus menjalankan serta memelihara komunikasi yang baik kepada semua
stake holder yang terlibat dalam pelaksanaan proyek
 Membuat laporan secara berkala kepada Pertamina EP sehubungan dengan koordinasi
dan pengendalian proyek, serta menghadiri rapat koordinasi dengan Pertamina EP
 Membentuk, menjalankan dan memelihara kinerja tim proyek tetap solid dan berorientasi
pada target penyelesaian proyek dengan tetap mengutamakan aspek HSE.

2.3. Construction Superintendent


2.3.1. Peran
 Memimpin tim konstruksi selama fase konstruksi sesuai dengan dokumen kerja yang telah
disepakati
 Mengelola tim konstruksi dan membuat perencanaan penyusunan tim kerja, peralatan, alat
dan material agar efisien dan efektif pemanfaatannya
 Mengidentifikasi ruang lingkup pekerjaan dan menyiapkan urutan pekerjaan konstruksi sesuai
dokumen kerja yang telah disepakati
 Melaporkan dan berkoordinasi intensif dengan Project Manager, Site Manager dan tim proyek
lainnya
2.3.2. Tanggung Jawab
 Untuk mengelola dan memelihara sumber daya konstruksi, biaya dan jadwal pada
penyerahan kontrak
 Memastikan semua pekerjaan sesuai dengan desain, gambar, prosedur, spesifikasi dan
didokumentasikan dengan baik
 Melakukan pekerjaan mengacu kepada jadwal konstruksi
 Membuat laporan kepada Site Manager, Project Manager seperti catatan waktu tenaga kerja,
pemanfaatan peralatan, produktivitas, dan kemajuan proyek
 Menginformasikan kepada Site Manager jika ada perubahan pekerjaan dilpangan yang tidak
sesuai dengan dokumen proyek.

2.4. Project Control


2.4.1. Peran
 Menyiapkan jadwal pekerjaan proyek
 Evaluasi dan memeriksa kinerja proyek melalui semua parameter seperti kemajuan pekerjaan,
biaya, kebutuhan tenaga kerja, kebutuhan material dan peralatan serta produktivitas kerja.
 Mengumpulkan data HSE dan Kualitas, informasi dan kondisi apa pun yang berdampak pada
kinerja proyek.
 Menyiapkan laporan progress proyek mingguan dan bulanan serta melaporkan kepada
manajemen dan diteruskan ke tim yang terlibat dalam proyek
 Membuat laporan yang mencakup semua informasi yang menjelaskan perkembangan
kemajuan proyek sehari-hari dan untuk ditinjau oleh manajemen

2.4.2. Tanggung Jawab


 Mendokumentasikan kinerja proyek dan melaporkannya kepada Project Manager termasuk
informasi biaya/keuangan, jadwal dan tugas-tugas tertentu yang dimasukkan ke dalam kinerja
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 18 dari 20

proyek.
 Setiap penyimpangan dari jalur perencanaan akan dilaporkan sesegera mungkin kepada
Project Manager.
 Membuat perkiraan biaya/keuangan, jadwal waktu, dan alokasi sumber daya
 Menyiapkan tagihan proyek yang sudah dikerjakan sesuai dengan dokumen kerja yang sudah
disetujui
 Menyiapkan jadwal konstruksi secara mingguan atau bulanan

2.5. HSSE Coordinator


2.5.1. Peran:
 Mengaudit dan melaksanakan perencanaan, pelaksanaan, dan pengawasan kerja.
 Memberikan peraturan-peraturan standart dalam setiap Prosedur pekerjaan.
2.5.2. Tanggung Jawab:
 Melaksanaan RENCANA K3LL.
 Melaksanaan prosedur K3LL dalam PROYEK.
 Mengembangkan dan melaksanakan pelatihan terkait K3LL yang dibutuhkan oleh pekerja.
 Mengembangkan dan melaksanakan jadwal audit.
 Melakukan investigasi apabila terjadi kecelakaan.
 Menyiapkan laporan kecelakaan dan saran untuk tindakan perbaikan.
 Memberikan solusi untuk isu-isu K3LL.
 Membuat prosedur K3LL.
 Membuat laporan K3LL mingguan dan bulanan.
 Memberikan saran dan rekemendasi K3LL kepada manajemen.
 Berkoordinasi dan bertatapmuka dengan perwakilan K3LL PERUSAHAAN.
 Berkoordinasi dan mengontrol kegiatan K3LL di dalam wilayah kerja.
 Berpartisipasi dan safety committee meetings dan inspeksi dengan manajemen.
 Membuat rencana pelatihan untuk pekerja.
 Meninjau secara berkala performa dari K3LL proyek.
 Berpartisipasi dalam penyelidikan kecelakaan bila diperlukan.
 Mengelola sistem laporan kecelakaan dan memastikan bahwa hasil penyelidikan dibagikan
kepada departemen terkait.
 Memastikan kegiatan drill dilakukan secara berkala di lapangan.
 Menyediakan checklist dan laporan pemeriksaan K3LL secara berkala.
 Memberikan pelatihan K3LL yang dibutuhkan oleh pekerja.
 Memastikan bahwa semua pekerja di proyek melaksanakan K3LL Plan ini.
 Berpartisipasi dalam rapat proyek di lapangan

2.6. QA-QC Cordinator


2.6.1. Peran:
 Memantau dan memeriksa kualitas pekerjaan sesuai dengan spesifikasi proyek
 Menangani semua penilaian kualitas, inspeksi dan pengujian serta berkoordinasi dengan tim
konstruksi untuk mencapai kinerja kualitas sesuai spesifikasi proyek.
2.6.2. Tanggung Jawab:
 Mengelola, mengendalikan dan memelihara sumber daya serta membuat semua hasil
konstruksi memenuhi persyaratan mutu
 Akan memenuhi ketentuan persyaratan inspeksi dan pengujian. Ketentuan tersebut akan
dicatat dan dilaporkan ke dalam bentuk standar dokumen kerja yang disetujui.
PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 19 dari 20

 Menjaga komunikasi apapun yang berhubungan dengan penilaian kualitas, inspeksi dan
pengujian yang dilakukan secara jelas dan terencana.
 Membuat laporan ke Project Manager, project control dan tim yang terlibat dalam
pelaksanaan proyek

2.7. Engineer
2.7.1. Peran:
 Mengarahkan dan mengkoordinasikan kegiatan engineering untuk meninjau gambar,
menentukan metode konstruksi, jenis material sesuai spesifikasi dan standar.
 Menyediakan gambar yang dibangun sebagai panduan untuk pelaksanaan konstruksi.
 Membantu survei di lapangan untuk memastikan kesesuaian pelaksanaan konstruksi.
 Mengembangkan perhitungan yang akurat dari aspek engineering.
 Menyiapkan gambar kerja dan Material Take Off (MTO) sesuai kebutuhan proyek
 Melakukan pengecekan terhadap dokumen engineering yang sudah disetujui terkait dengan
kesesuaian antar disiplin pekerjaan

2.7.2. Tanggung Jawab:


 Memeriksa pekerjaan yang dilakukan oleh tim konstruksi untuk memastikan kesesuaian
dengan design.
 Memeriksa data vendor, dokumen, dan gambar, untuk memastikan kepatuhan dengan
spesifikasi proyek dan standar yang berlaku.
 Meninjau semua permintaan kebutuhan material untuk instalasi.
 Memastikan dokumen yang dihasilkan oleh disiplin lain tidak bertentangan dengan
persyaratan disiplin engineering.
 Melakukan perhitungan engineering sesuai dengan basis design proyek.

3. SCHEDULE & PROJECT PLANNING CHART


3.1. Project Master Schedule
Project Master Schedule (TERLAMPIR) akan diperbarui menggunakan tampilan split bar dimana
bagian bawah bar mewakili tanggal yang direncanakan dan bagian atas menunjukkan tanggal penyelesaian
aktual. Master Schedule Level 5 harus diperbarui setiap bulan pada tanggal batas akhir bulan.
Untuk mengetahui apakah project berjalan sesuai plan maka itu dapat dilakukan dengan
membandingkan kemajuan actual yang dicapai dengan kemajuan yang direncanakan yang biasanya
digambarkan oleh S-Curves. (TERLAMPIR)
Jika kemajuan aktual berada di bawah kemajuan yang direncanakan, ini mengindikasikan bahwa
proyek berjalan di belakang timeline target. Mempercepat kegiatan yang diperkirakan selesai di bagian
akhir project adalah cara untuk meningkatkan tingkat progress setiap kali proyek terlambat.

3.2. Jam Kerja


Jam kerja normal KSO PT. Wahanakarsa Swandiri – PT. Aldaberta Indonesia adalah sebagai berikut :

Hari Jam Kerja Istirahat

Senin - Kamis 07.00 – 18.00 12.00 – 13.00


PROJECT EXECUTION PLAN JAS-EPC-WKSAI-00-G0-PM-001
PT. PERTAMINA EP / REGIONAL 2 – FUNGSI PROJECT ZONA 7 Rev.B
PEMBANGUNAN STASIUN PENGUMPUL JATIASRI Halaman 20 dari 20

Jumat 07.00 – 18.00 11.30 – 13.30

Sabtu & Minggu 07.00 – 16.00 12.00 – 13.00


(jika diperlukan)

Jika memang karena tuntutan pekerjaan dan dalam rangka menjaga jadwal proyek maka KSO WKS-AI akan
melakukan kerja tambah sesuai dengan kebutuhan proyek.
Proses Pengendalian Jam Kerja diringkas sebagai berikut:
 Setelah Kebutuhan Tenaga Kerja memenuhi kebutuhan Pertamina EP maka Semua Tenaga Kerja akan
dijadwalkan untuk bekerja sesuai dengan perintah kerja.
 Setiap diperlukan untuk tambahan kerja diluar jam kerja normal maka KSO WKS – AI akan
mempersiapkan otorisasi lembur yang akan disetujui oleh Perwakilan Konstruksi Pertamina EP,
kemudian diserahkan kepada Tim Kontrol Proyek untuk dicatat.
 Kontrol Proyek harus menyiapkan perkiraan jam kerja yang dibutuhkan berdasarkan persyaratan
proyek. Perkiraan ditentukan dengan mempertimbangkan pekerjaan yang tersisa.
 Jam kerja yang dibutuhkan untuk sisa pekerjaan akan diatur oleh Personil Kontrol Proyek.

4. INTERFACE PERUSAHAAN DENGAN KONTRAKTOR


Selama pelaksanaan proyek pembangunan EPC SP Jatiasri ini segala surat menyurat resmi keluar dan
masuk dari KONTRAKTOR kepada pihak lain yang terlibat di dalam pelaksanaan proyek harus melalui satu pintu
yaitu manajer proyek kontraktor. Yang dimaksud dengan surat menyurat resmi antara lain adalah:
 Surat
 Facsimile
 Transmittal
 Minute of meeting
 Report
Untuk komunikasi yang sifatnya belum final dapat dilakukan langsung antara masing masing person
incharge dari kontraktor dengan pihak lain yang berkepentingan (vendor, subkontraktor dll) melaui antara lain :
 E-mail
 Telepon.

Anda mungkin juga menyukai