Oleh:
ANSHAR HAMIDI
JOSHUA SUGANDI SIREGAR
MUHAMMAD ALFIN KHAIRULLAH
SOAL
1. Benzene akan dipanaskan dari 150oC menjadi 200oC dengan steam 230o C, laju
alir Benzene 9.134,936 kg/jam, steam 269,458 kg/jam. Q = 327.134,16
Btu/jam. Tentukan peralatan perpindahan panas yang dipakai, hitung dirt factor
dan pressure drop masing masing!
2. Ethylbenzene akan didinginkan dari 115o C menjadi 45o C, laju alir 50.749,23
kg/jam, steam 13.912,45 kg/jam. Q = 967.872,49 Btu/jam. Tentukan peralatan
perpindahan panas yang sesuai, hitung dirt factor dan pressure drop masing
masing!
Tube Layout
1. Shell and Tube : Square pitch
2. Double pipe heat exchanger : IPS 2 ½ x 1 ¼
LAMPIRAN A
LEMBAR SPESIFIKASI
1. Heater 1
LEMBAR SPESIFIKASI
Nama Alat Heater Kode Alat HE-101
Fungsi Menaikkan suhu Benzene
Jenis Shell and Tube Heat Exchanger
Kondisi Operasi
Fluida Steam Gas
Laju alir (lb/hr) 594,353 20.142,53
Temperatur masuk (°F) 446 302
Temperatur keluar (°F) 446 392
Temperatur rata-rata (°F) 446 347
Pressure Drop (psi) 0.000289 0.02267
LMTD (°F) 91,76
Beban panas (Q) (Btu/hr) 327.134,16
Material and Design
Shell : Steam (1 Tube : Umpan (2
Pass Passes
OD (in) 1
ID (in) 12
Pitch 1,25 in, Square pitch
Baffle space (in) 2,4
Length (ft) 20
Clean overall coefficient (Uc)
17,068
(Btu/hr ft2 F)
Design overall coefficient (Ud)
15,13
(Btu/hr ft2 F)
Dirt factor (Rd) (hr ft2 F/Btu) 0.0075
Luas Permukaan (A) (ft2) 235,62
Jumlah Tube (Nt) 45
2. Cooler 101
LEMBAR SPESIFIKASI
Kondisi Operasi
Inner Pipe :
Annulus : Air
Ethylbenzene
jH 170 350
Jumlah hairpin 7
LAMPIRAN B
PERHITUNGAN PERALATAN
1. Heater 101
Lembar Perhitungan
446 F
302 F 392 F
446 F
Data yang dibutuhkan untuk perancangan :
Umpan berupa Benzene
Umpan memiliki laju alir sebesar 9134,936 kg/h = 20.142534 lb/h
Umpan memiliki tin = 302 oF dan tout = 392 oF
Viscositas umpan 0,011 cp =0,0266 lbm/ft.h
Steam memiliki laju alir 269,548 kg/jam = 594,353 lb/h
Aliran panas (steam) memiliki Tin = 446 oF dan Tout = 446 oF
Karena umpan pada suhu tav: 347 oF sudah dalam fasa uap maka
menggunakan Ud gasses. dengan rentang Ud 5-50, dan Ud asumsi
yang digunakan adalah 15
Beban panas (Q) = 327134,16 lb/hr
1) Perhitungan Energy Balance
2) Perhitungan LMTD
Hot Fluid Ket Suhu Cold Fluid ∆T
0 Selisih 90 90
54 − 14
𝐿𝑀𝑇𝐷 = = 91,76 ℉
2,3 x log( 54/14)
𝑄 327134,16
𝐴= = = 234,549 𝑓𝑡 2
𝑈𝐷 ∆𝑡 15 × 91,76
Didapatkan untuk nilai A = 234,549 𝑓𝑡 2 , untuk luas perpindahan panas (A) >
200 ft2 , maka digunakan jenis alat penukar panas jenis shell and tube heat exchanger
(Kern, 1950).
𝐴 234,549
𝑁𝑡 = = = 44,795
𝐿 × 𝑎" 20 × 0,2618
Pada Tabel 9 Kern, 1950 digunakan Nt= 45 yang mendekati 44,795 dengan 2 tube
passes, sehingga didapatkan spesifikasi data untuk shell dengan ID=12 in dan 1 shell
pass.
Dimensi design:
0,0833
OD (in) 1
3 Ft
BWG 18
0,0751
ID (in) 0,902
7 Ft
Flow areal
0,639
tube (a't)(in2)
surface (a"t) 0,2618
Panjang (L) 20
1 1/4 Square
Pitch
pitch
Koreksi Koefisien UD :
𝑄 327134,16
𝑈𝐷 = = = 15,13
𝐴𝑘𝑜𝑟𝑒𝑘𝑠𝑖 × ∆𝑡 235,62 × 91,76
Mencari Baffle of space dengan menggunakan persamaan 11.4 (kern, 1950) dengan
pengambilan minimum baffle of space :
ID 12 in Nt and L 45 dan 20 ft
= 2,4 in
Passes 2
Pass 1
Steam sebagai fluida panas yang Benzene sebagai fluida dingin yang
dialirkan pada shell. dialirkan pada tube side.
pT = 1,25 in
C’ = Pt – OD = 1,25 - 1 = 0,25 in 𝑁𝑡 × 𝑎𝑡 45 × 0,639
𝐴𝑡𝑢𝑏𝑒 = =
144 𝑁𝑝 144 × 1
C’ = 0,02083 ft
= 0,0998 𝑓𝑡 2
𝐼𝐷 × 𝐶 ′ 𝐵 12 × 0,25 × 2,4
𝐴𝑠 = = Kecepatan Perpindahan Massa
144𝑃𝑇 144 × 1,25
= 0,0625 𝑓𝑡 2 𝑊 20142,534
𝐺𝑡 = =
𝐴𝑡𝑢𝑏𝑒 0,0998
= 201740,57 𝑙𝑏𝑚
Kecepatan Perpindahan Massa /ℎ 𝑓𝑡 2
𝑗𝐻 = 80
Pada Tc = 446 oF 1 1
𝑐𝜇 3 0,55 × 0,0266 3
( ) =( )
c (Btu/(lb)(F)) = 0,48 pada Fig 3, Kern 𝑘 0,015
= 0,7441
k (Btu/hr.ft2.F) = 0,0205 pada Tabel 5, 𝑘 0,015
Kern 𝑗𝐻 ( ) = 900 × = 155,78
𝐷 0,07516
1 1 1
𝑐𝜇 3 0,48 × 0,041 3 𝑘 𝐶𝜇 3
( ) =( ) = 0,9869 ℎ𝑖 = 𝑗𝐻 ( ) ( ) 𝜑𝑖
𝑘 0,0205 𝐷 𝑘
ℎ𝑖
= 155,78 × 0,7441
𝜑𝑖
𝑘 0,0205
𝑗𝐻 ( ) = 80 ( ) = 19,9
𝐷 0,0825 ℎ𝑖
= 130,8 (Btu/hr.ft2.F)
𝜑𝑖
ℎ𝑖𝑜 ℎ𝑖 𝐼𝐷 0,902
= × = 91,8 ×
𝜑𝑖 𝜑𝑖 𝑂𝐷 1
Menghitung h0
= 117,99 (𝐵𝑡𝑢
1 /ℎ𝑟. 𝑓𝑡2. 𝐹)
𝑘 𝐶𝜇 3
ℎ𝑜 = 𝑗𝐻 ( ) ( ) 𝜑𝑜
𝐷 𝑘
ℎ𝑜 Menentukan Tw
= 289,46 × 0,9869
𝜑𝑜
Pada tc = 347 °F
= 19,65 (𝐵𝑡𝑢
ℎ𝑜 ⁄𝜑𝑜
/ℎ𝑟. 𝑓𝑡2. 𝐹) 𝑡𝑤 = 𝑡𝑐 + (𝑇 − 𝑡𝑐 )
ℎ𝑖𝑜 ⁄𝜑𝑖 + ℎ𝑜 ⁄𝜑𝑜 𝑐
19,65
𝑡𝑤 = 347 + (446
Pada tw 𝟑𝟔𝟏, 𝟏𝟑 dari fig 15 117,99 + 19,65
− 347)
𝜇𝑤 = 0,015 × 2,419 = 0,03628 𝑡𝑤 = 361,13 ℉
ℎ𝑖𝑜
Clean Overall Coefficient Uc ℎ𝑖𝑜 = 𝜑𝑖 = 117,99 × 0,9878
𝜑𝑖
= 116,56 Btu
ℎ𝑖𝑜 × ℎ𝑜 116,56 × 19,996
𝑈𝑐 = = /hr. ft2. F
ℎ𝑖𝑜 + ℎ𝑜 116,56 + 19,996
Menghitung RD
𝑈𝑐 − 𝑈𝐷
𝑅𝐷 =
𝑈𝑐 × 𝑈𝐷
17,068 − 15,13
𝑅𝐷 =
17,068 × 15,13
𝑅𝐷 = 0,0075 (hr.ft2.F/Btu) karena RD >
0,003 Maka layak di terima
Summary
Ho h outside Hi
19,96 116,56
UC = 17,068 Btu/hr.ft2.F
UD = 15,13 Btu/hr.ft2.F
𝐷𝑠 = 1 𝑓𝑡 1. ∆Pt
No. Of crosses, N+1 = 12 L/B 1 𝑓𝐺 2 𝐿𝑁𝑝
∆𝑃𝑡 =
2 5,22 × 1010 × 𝐷𝑠𝜑𝑖
𝑁 + 1 = 12 × 20⁄2,4 = 100
∆𝑃𝑡
1 0,000095 × 201740,6^2 × 20 × 1
=
2 5,22 × 1010 × 0,07516 × 0,88 × 0,9878
1. ∆Ps
∆𝑃𝑠
𝑓𝐺 2 𝐷𝑠 (𝑁 + 1) ∆𝑃𝑡 = 0,02267 𝑝𝑠𝑖
=
5,22 × 1010 × 𝐷𝑒 𝑠𝜑𝑜
∆𝑃𝑠
0,0017 × 95102 × 1 × 100
=
5,22 × 1010 × 1 × 1 × 1,0176
∆P untuk shell and tube harus <10 psi, sedangkan nilai Rd memenuhi syarat, sehingga
Heater ini layak untuk dirancang dalam perancangan alat perpindahan panas.
2. Cooler 101
LEMBAR PERHITUNGAN
Ethylbeneze Ethylbenzene
T =239 °F T = 113°F
1. Heat balance
Nilai Q diketahui sebesar 647.158,76 Btu/hr
2. 𝛥𝑇
Ethylbenzene Air pendingin Difference
(°F) 239 High Temp (°F) 176 63
(°F) 113 Low Temp (°F) 86 27
(°F) 126 Difference (°F) 90 36
Δt1 = 239 - 176 = 63°F
t 2 t1 63 27
𝛥𝑇LMTD = 42,48 F
t 2 63
ln ln
t1 27
( D D1 ) 0,2508 2 0,1383 2
2 2
a 2 3,14 0,0182 ft 2
4 4
D2 D1 0,2058 2 0,13832
2 2
De 2
0,1677 ft
D1 0,13832
(D 2 ) (0,1152 )
a( pipa ) 3,14 0,0104 ft 2
4 4
3 Menghitung jH 3 Menghitung jH
Pada Fig.24 jH = 170 Pada Fig.24 jH = 350
4 Menghitung (cµ/k)1/3 4 Menghitung (cµ/k)1/3
Pada tc = 131°F Pada tc = 176°F
c = 0,996343682 Btu/(lb)(°F) c = 0,49 Btu/(lb)(°F)
k = 0,3467 Btu/(hr)(ft2)(°F/ft) k = 0,0725 Btu/(hr)(ft2)(°F/ft)
1 1 1 1
c 3
0,9963 1,331 3
c 3
0,49 0,9196 3
k 0,3467 k 0,78
= 1,275 = 0,192
5 Menghitung ho 5 Menghitung hi
1 0 ,14 1 0 ,14
k c 3 k c 3
ho j H hi j H
De k w D k
w
0,3467 0,78
ho 170 1,275 1 hi 350 0,192 1
0,1677 0,115
ho 448,137 Btu/(hr)(f t 2 )( F ) hi 457,134 Btu/(hr)(f t 2 )( F )
6 Menghitung hio
ID
hio hi
OD
0,115
hio 457,134
0,138
hio 380,02 Btu/(hr)(f t 2 )( F )
Menghitung tw
ho
o
tw tc (Tc t c )
hio ho
t o
448,137
t w 131 (176 131)
380,02 448,137
t w 151,65 F
U D 127,616 Btu/(hr)(ft2)(oF)
Required surface:
Q 647.158,76
A 119,354 ft2
U D t 127,616 42,48
Karena Required Length sepanjang 274,377 ft, berdasarkan halaman 103 process
heat transfers by kern bahwa DPHE biasanya menggunakan panjang pipa 12, 15,
atau 20 ft, maka digunakan pipa dengan panjang 20 ft (2 x 20 ft =40 ft). sehingga
jumlah hairpin adalah sebagai berikut:
L 274,377
Jumlah hairpin 6,859 7 hairpin
40 40
Surface Actual :
L aktual = jumlah hairpin x panjang pipa = 7 x (2x20) = 280 ft
A aktual = jumlah hairpin (2 20) a 7 2 20 0,435 121,8 ft2
Q 647.158,76
UD 125,05 Btu/(hr)(ft2)(oF)
At 121,8 42,48
U C U D 206.783 125,05
Rd 0,0032 (hr)(ft2)(°F)/Btu
U C U D 206.783 125,05
Summary
466,95 h outside 371,137
UC 206,783
UD 35.89
Rd Calculated 0,0032
Pressure Drop
Berdasarkan process heat transfers by donal.q. kern halaman 109, allowable
pressure drop berkisar dari 5 sampai 10 psi.
Cold fluid; Annulus; Hot fluid; Inner Pipe;
Air pendingin Triacetin and Glycerol
10 De’ yang berbeda dari De untuk HE
De’ = (D2 – D1)
De’ = (0,2058– 0,138) = 0,06742 ft
11 Reynold number, Re 11 Reynold number, Re
Tc =31°F DG 0,115 1.077.885,71
Re p
µ = 1,331 lb/(ft)(hr) 0,9196
15 V 2
F 3
l 2g'
1,788 2
F 3 0,149 ft
l 2 32,2
Pa
Fa Fl Fp
144
Pp
144
Pa
0,8934 0,149 62,5 3,5230 54 ,1875
144 Pp
144
Pa 0.452 psi Pp 1,3257 psi
LAMPIRAN C
GAMBAR ALAT
1. Cooler 101
Tin
tout
Tout
tin
2. Heater 101
T out
t in
T out
T in
t out