Anda di halaman 1dari 81

14/08/2020

TIPIKAL PERBAIKAN TANAH


SUDUT PANDANG PEMBICARA BERDASARKAN SNI 8460 : 2017

Geotech Efathama | www.geotech-indonesia.com


___________________________________________________________________________________________________
Tipikal Perbaikan Tanah | Geotech Efathama | Universitas Trisakti | 14.08.2020

Aksan Kawanda
An Ordinary Geotechnical Engineer

Bio Skills
Soil Mechanics
Lahir : Makasar, 13 Agustus 1979
Pendidikan : Doktor Geoteknik, Univ. Katolik Parahyangan Foundation
Magister Geoteknik, Univ. Katolik Parahyangan
Sarjana Teknik Sipil, Universitas Trisakti Slope Stability

Sertifikasi : Asesor Uji Kompetensi – BNSP – 2018 Retaining Walls


Ahli Geoteknik Utama – LPJK – HATTI – 2016
Certified International Pile Tester, Expert Level - 2014 Compaction
Asosiasi : Himpunan Ahli Teknik Tanah Indonesia
Soil Improvement
International Society of Soil Mechanics and
Geotechnical Engineering
Geotechnical
Akademis : Dosen KBK Geoteknik – Universitas Trisakti, Instrumentation

Pekerjaan : Direktur Teknik – PT. Geotech Efathama

Aksan Kawanda aksankawanda Aksan Kawanda 0811.851.613

1
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Pemadatan tanah untuk meningkatkan


daya dukung tanah
(Abad 11, Chinese Building Standard)

Pemadatan tanah
menggunakan giant tamper
(2011)

Pendahuluan Chemical Mechanical Drainage

• Soft clay area : east of Sumatera, north of Java, South of Kalimantan, south of Papua 
PVD with vacuum / soil preloading.
• Loose sand area : north and south of Sumatera, most of Sulawesi, NTT, NTB, Maluku 
Dynamic compaction, vibroflotation.
• High working load area  Deep cement mixing, Stone Column.

2
14/08/2020

Pendahuluan Chemical Mechanical Drainage

• Soft clay area : east of Sumatera, north of Java, most of Kalimantan, south of Papua 
PVD with vacuum / soil preloading.
• Loose sand area : north and south of Sumatera, most of Sulawesi, NTT, NTB, Maluku 
Dynamic compaction, vibroflotation.
• High working load area  Deep cement mixing, Stone Column.

Pendahuluan Chemical Mechanical Drainage

Kriteria geoteknik yang digunakan


untuk mengevaluasi suatu proyek:

1. Penurunan – Mengurangi kompresibilitas


2. Daya Dukung & Stabilitas – Meningkatkan kekuatan
3. Menahan Aliran Air – Kurangi permeabilitas
4. Drainase – Tingkatkan permeabilitas
5. Mengurangi dampak bencana likuifaksi
6. Masalah lingkungan

3
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Beberapa faktor yang mempengaruhi pemilihan jenis perbaikan tanah:


Burland et al. (1976)

1. Tentukan perilaku tanah yang diperlukan sesuai kebutuhan


• Beban/deformasi
• Jenis tanah dan properties
Tanah: Peat, Lempung, Lanau, Pasir, Urugan
Ketebalan tanah yang diperbaiki
Karakter geoteknik : compression, shear strength, modulus
Posisi muka air

2. Identifikasi kekurangan dari perilaku tanah

3. Rancang dan implementasikan perbaikan yang sesuai untuk mengatasi kekurangan/kelemahan yang ada.
• Waktu
• Area dan kedalaman tanah yang akan diperbaiki
• Ketersediaan material
• Peralatan dan keahlian yang dimiliki
• Lingkungan
• Pengalaman dan kebiasaan lokal
• Kemungkinan pelaksanaan konstruksi
• Biaya

Pendahuluan Chemical Mechanical Drainage

Lateral Deformation

Sliding due to lateral capacity failure at bridge abutment. The original soil is soft clay
without soil improvement to increase the lateral capacity and increase sliding resistant.
Case : South Sumatera

4
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Sliding
Sliding due to high backfill on untreated
soft soil.
Case : South Sumatera

Improved area
No improvement

Pendahuluan Chemical Mechanical Drainage


Sliding

Sliding due to high backfill on untreated


soft soil.
Case : South Sumatera

Improved area

No improvement

5
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Settlement
Large Post

Road and infrastructure damage due to differential settlement.


Case : East Kalimantan

Pendahuluan Chemical Mechanical Drainage


Negative Skin Friction

Negative skin friction pile failure cause by consolidation settlement process after
all construction on pile is finish.

6
14/08/2020

Pendahuluan Chemical Mechanical Drainage


Liquefaction
Soil

Pendahuluan Chemical Mechanical Drainage

Opsi alternatif saat ditemukan kondisi tanah yang butuh perbaikan:

• Hindari area tersebut

• Ganti tanah dasar

• Redesain untuk mengakomodir kondisi tanah dan lahan

• Perbaiki tanah dasar untuk meningkatkan properties nya

7
14/08/2020

Pendahuluan Chemical Mechanical Drainage


TIPIKAL TEKNIK PERBAIKAN TANAH
Persentase Butir Berdasarkan Berat

Ukuran Butir (mm)

Pendahuluan Chemical Mechanical Drainage

TIPIKAL TEKNIK PERBAIKAN TANAH

CHEMICAL MECHANICAL DRAINAGE

CMC Dynamic Compaction Dynamic Replacement Vertical Drains

Jet Grouting Vibroflotation Stone Columns Vacuum

8
14/08/2020

Pendahuluan Chemical Mechanical Drainage


TIPIKAL TEKNIK PERBAIKAN TANAH

Pendahuluan Chemical Mechanical Drainage


TIPIKAL TEKNIK PERBAIKAN TANAH

9
14/08/2020

Pendahuluan Chemical Mechanical Drainage


TIPIKAL TEKNIK PERBAIKAN TANAH

Settlement

Loose Flotation Dense

Pendahuluan Chemical Mechanical Drainage


TIPIKAL TEKNIK PERBAIKAN TANAH

10
14/08/2020

Pendahuluan Chemical Mechanical Drainage


TIPIKAL TEKNIK PERBAIKAN TANAH

Pendahuluan Chemical Mechanical Drainage


TIPIKAL TEKNIK PERBAIKAN TANAH

11
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Grouting
GROUTING

DCM
Tipikal dari TEKNIK

CFG
Pendahuluan Chemical Mechanical Drainage

Grouting
Techniques

DCM
Range of Grouting

CFG

12
Range of Grouting
Techniques Range of Grouting Techniques
(Jet Grouting) (Compaction Grouting)

Pendahuluan
Pendahuluan

Chemical
Chemical

Mechanical
Mechanical

Drainage
Drainage

CFG DCM Grouting CFG DCM Grouting

13
14/08/2020
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Grouting
Techniques
(Jet Grouting)

DCM
Range of Grouting

Monitoring

CFG
Tekanan, volume dan lokasi diamati real-time
(meningkatkan efisiensi dan kualitas) untuk
review. Pengamatan campuran grouting juga
dilakukan periodik terhadap viskositas (Marsh
Funnel Test), berat jenis (Baroid Mud Balance),
kohesi dan parameter lainnya (API, 1990)

Pendahuluan CHEMICAL Mechanical Drainage

14
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Grouting
DCM Equipment

DCM
CFG
1- host ; 2 - rack ; 3- mortar mixing machine ; 4- hopper ; 5- mortar pump ; 6- storage tank ;7- cooling water
pump ; 8- rail ; 9- guide tube ; 10- cable ; 11- lose slurry pipe ; 12- pipes

Pendahuluan Chemical Mechanical Drainage


Typical Work Sequence

Grouting
DCM
CFG

15
14/08/2020

Pendahuluan Chemical Mechanical Drainage


Workflow process
Deep Soil Mixing

Grouting
DCM
CFG
Positioning Equipment Positioning Auger Tools Soil Mixing Drawing While Continue Complete Result
Mixing

The columns installed by the dry method are typically circular and about 0.6–1.0 m in diameter, while the
columns installed by the wet method can be of different shape and up to about 2.5m in equivalent diameter.

Pendahuluan Chemical Mechanical Drainage

Grouting
DCM
CFG

Project Reference :
Sarulla Geothermal Power Plant
North Sumatera

16
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Grouting
Site Plan

DCM
CFG
Pendahuluan Chemical Mechanical Drainage

Grouting
Soil Stratigraphy

DCM
CFG

17
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Foundation System

Grouting
DCM
CFG
Pendahuluan Chemical Mechanical Drainage
Cement Mixing Test

Grouting
DCM
CFG

18
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Grouting
Site Activity

DCM
CFG
Pendahuluan Chemical Mechanical Drainage

Grouting
DCM
DCM Post-test

CFG

19
14/08/2020

Pendahuluan Chemical Mechanical Drainage

CFG Pile

Grouting
Cement-Flyash-Gravel(CFG)

DCM
CFG
Cement-Flyash-Gravel(CFG) pile was developed based on stone column.

When the stone column is applied in soft soil condition, stone column is not reliable due to the confine resistance
is relatively low. Cement and Flyash is mixed with gravel to work as binder therefore CFG column is a rigid
column. Due the CFG column is rigid column, this method could be applied in most of soil conditions.

Pendahuluan Chemical Mechanical Drainage

CFG Pile

Grouting
Perkenalan Metode CFG

CFG Advantages
• Could applied in most soil, such as peat soil, soft clay, fat clay,
sandy soil, complicated layered soil or hard soil conditions.

• Could use a lot of material combination, such as cement-flyash-


gravel, cement-lime-gravel, cement-sand.
DCM

• This method could form a column from low stiffness column


(similar as DCM column) until high stiffness column (similar as
spun pile) which means the bearing capacity of CFG composite
foundation could be designed in quite a big range to fit the
project requirement.

• This CFG pile construction is quite fast and in some cases will
be more cost saving compare to other piles.
CFG

20
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Grouting
Inclusions

DCM
CFG Pile as Rigid

CFG
Pendahuluan Chemical Mechanical Drainage
Tipikal Alat
CFG Vibrating Machine

Grouting
DCM
CFG

Top Mounted Vibrating Machine Long Auger CFG Machine

21
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Grouting
CFG PILE Project Reference

DCM
CFG
Pendahuluan Chemical Mechanical Drainage

Grouting
DCM
CFG

Typical cross section

22
14/08/2020

Pendahuluan Chemical Mechanical Drainage


Cutting CFG pile on top

Grouting
DCM
CFG
Pendahuluan Chemical Mechanical Drainage
Construct the CFG pile cap

Grouting
DCM
CFG

23
14/08/2020

Pendahuluan Chemical Mechanical Drainage


CFG pile cap + Cushion Layer

Grouting
DCM
CFG
Pendahuluan Chemical Mechanical Drainage
Static Load Test on CFG Pile

Grouting
DCM
CFG

24
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Pendahuluan Chemical Mechanical Drainage

Vibro Flotation

V-Flotation V-Replacement D-Compaction


AN INTRODUCTION

Pressing a cylindrical vibrator inside with an eccentric iron into soil, meanwhile jetting
pressure water into soil, and force the saturated sand liquefied under the vibration
strength and rearrange sand become more dense.
• Natural deposits and or reclaimed sands can be compacted to a depth of up to 70 m.
• The intensity of compaction can be varied to meet bearing capacity criteria.
• Other improvement effects such as reduction of settlements are achieved.
• The risk of liquefaction in an earthquake prone area is also drastically reduced.

25
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Working Method

Loose

Press to
Location design
level

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Working Method

Loose Flotation

Press to Vibrate
Location design 20–30
level seconds

26
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Working Method

Loose Flotation

Press to Vibrate Lift and vibrate


Location design 20–30 again. Lift
level seconds height no more
than 0.5 m

Pendahuluan Chemical Mechanical Drainage


Settlement

V-Flotation V-Replacement D-Compaction


Working Method

Loose Flotation Dense

Press to Vibrate Lift and vibrate Finish


Location design 20–30 again. Lift
level seconds height no more
than 0.5 m

27
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Vibration frequency, amplitude and vibration retaining time
Effect

The sand will be more dense with increase of vibration force and amplitude.
Based on the experiment on site, the optimal vibration retaining time will be 20–60
seconds.
Factor to Influence The

Clay content
It is difficult to get a good effect if the clay content is beyond 20%.

Water content
For dry sand or saturated sand, vibroflotation can get a good effect, if the water
content is between the two situation above, the effect is not good.

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction

Project Reference :
Pantai Maju – PIK

28
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Site activity

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Site activity

29
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Improvement result

Pendahuluan Chemical Mechanical Drainage


West Apron Ngurah Rai International Airport

V-Flotation V-Replacement D-Compaction


West Apron, Ngurah Rai International Airport
Location : Bali, Indonesia
Method : Vibro-flotation
Construction start :May 2018

The extension of west apron at Ngurah Rai


International Airport is done to
accommodate International guest for IMF
meeting 2018 in Bali. Due to tight
schedules and work conducted next to
fully operational airport, Vibro-flotation
method is chosen as a solution for Ngurah
Rai west apron extension.

30
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Stone Columns (Wet Method)

Vibro Replacement is a
combination of vibroflotation
with a gravel backfill resulting
in stone columns; not only
increases the amount of
densification, but provides a
degree of reinforcement and
a potentially effective means
of drainage

31
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Advantages: 1. Reduction of Settlement

The graph shows the settlement reduction with different percentages of soil
being replaced by stone columns (after Priebes, 1993)

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Advantages: 2. Increase in Slope Stability

Stone columns have a threefold effect in soil :

 Compaction of compatible layers.


Layers of clean sand and gravel and slightly silty
sand (up to 20 % fines content) are compacted
during the process of stone column installation.

 Reinforcement of the soil.


The screenshot (finite elements software: plaxis®) shows
Column and soil form a reinforced matrix with possible slope failure without stone columns.Safety factor
instantly increased shear resistance and stiffness against slope failure:F = 1.06

modulus. The high friction angle of the column


material gives an immediate overall increase in
shear strength to the composite of soil and
column.

 Drainage.
The columns accelerate drainage (consolidation) of
the cohesive soil, i.e. the columns work as vertical
drains and thereby accelerate reduction of harmful
excess pore pressures
After slope stabilisation with stone columns: F = 1.60

32
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Advantages: 3. Mitigation of Soil Liquefaction

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Advantages: 3. Mitigation of Soil Liquefaction

Liquefaction at pavement surface Liquefaction at building foundation

Settlement
Mass Mass Water
Mass flow
Impermeable soil layer Impermeable soil layer

Impermeable soil layer Impermeable soil layer Impermeable soil layer

Loose Earthquake Dense

33
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Project Reference :
Tarahan Expansion Port, Lampung

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Site activity

34
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Site activity

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Site activity

35
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


• Reduction of settlement :
• Requirement < 20 cm (previous
phase reach 2 m post settlement).
Improvement result

• Increase of slope stability :


• Protect the jetty from land side
sliding.

• Mitigation of Soil Liquefaction :


• Compaction of compressible layer
 average site settle 1 m.
• Reinforcement of the soil
 stone column provide
bearing capacity 25 tons /point.
• Drainage
 provide drainage path for
excess pore water dissipation
during earthquake.

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


EQUIPMENT
Stone Columns :
Dry Method

STONE COLUMN UNIT EXCAVATOR DUMP TRUCK

36
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


STONE COLUMN UNIT
Stone Columns :
Dry Method

SIDE VIEW FRONT VIEW

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Stone Columns :
Dry Method

1. Put machine at position 3. Filling the stone follows the 4. Pull up the tube while vibrate.
2. Push the tube to the design depth designed volume Every 1.5 m lifting pull down the
tube by 0.8 m and keep vibrate for
certain duration
5. Doing step 4 until reach the top.

37
14/08/2020

Pendahuluan Chemical Vibration Drainage

V-Flotation V-Replacement D-Compaction


(Soekarno Hatta Airport)
Dry Method site construction

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction

38
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Dynamic Compaction Introduction

Dynamic compaction method was used for


ground treatment to improve the strength
of the soil and to reduce the
compressibility of ground soil.
Main advantages are simple equipment,
convenient construction and saving
materials.
The method was widely used in sand and
gravelly soil. The effective reinforcement
depth was the main design basis of the
dynamic compaction method.
In this method, a heavy ponder is dropped on
soil surface from various heights with free
drop within a grid-wise manner and hence
subsoil is compacted by means of the
energy delivered to the soil surface.

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction

Project Reference :
Pantai Maju – PIK; NYIA – Yogyakarta; Dubai

39
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Site activity & improvement result

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


– New Yogyakarta Airport
Site activity

40
14/08/2020

Pendahuluan Chemical Mechanical Drainage


DC &DR works for Hassyan Clean Coal Power Plant Phase 1, Jabel Ali, Dubai 2017

V-Flotation V-Replacement D-Compaction


PROJECT PROFILE
Location: Jabel Ali, Dubai
Client: Harbin Electrical International Company LTD
Areas: 197,800m²

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Ground Improvement Works for GRACE FCC Catalyst Plant in Kizad, Dubai

Client:Grace FCC Catalysts Middle East LLC


Consultant:Amar Golden Design (AMGD)
Improvement area: 23,389m²

41
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


RAPID IMPULSE COMPACTION

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Efek Metode Pemadatan Dinamik

STATIC / DYNAMIC ROLLERS RAPID IMPULSE DEEP DYNAMIC DEEP VIBRO COMPACTION
COMPACTION COMPACTION

0.2 m 0.4
0.5 m 1.0 m
m

6m
Depth effect: 10 m
normal range
possible 7.5 - 9.0 m 15 m
range

14 m 25
m

42
14/08/2020

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


S S

Pola pemadatan dikalkulasi berdasarkan:


1. Kondisi tanah (Dibutuhkan Analisa geoteknik)
2. Beban rencana (Dibutuhkan Target Desain)
Pola Pemadatan

Pendahuluan Chemical Mechanical Drainage

V-Flotation V-Replacement D-Compaction


Soft and peat soil:
Pola Pemadatan

Picture: Display of different


layers for Rapid impulse
compaction

Mencapai:
Pemadatan standar 20% organic content
dengan stone column maks. 5m tanah gambut

43
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
PRELOADING PRINCIPLE

Vacuum Preloading + PVD


The principle : If the temporary load exceeds
the final construction load, the excess refers to
as surcharge load.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Vertical Drain PRINCIPLE

Vacuum Preloading + PVD

Clay  Low Permeability  Consolidation settlement of soft clays takes a long time to complete.

To shorten the consolidation time vertical drains are installed  reduces the length of the drainage
path  accelerates the consolidation process  allows the clay to gain rapid strength increase.

44
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
SOIL PRELOADING PRINCIPLE

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
SOIL PRELOADING PRINCIPLE

Vacuum Preloading + PVD

45
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Vertical Drain Type

Vacuum Preloading + PVD


CORRUGATED CORE TYPE FISHBONE CORE TYPE

Corrugated core has a better drainage capacity under large lateral pressure.

Fishbone core has a better drainage capacity under bending or folding condition.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VERTICAL DRAIN INSTALLATION

Vacuum Preloading + PVD

The square pattern is more convenient to lay out and to control in the field. However, a
triangular pattern is usually preferred since it provides a more uniform consolidation
between drains than the square pattern (Holtz et al., 1991).

46
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VERTICAL DRAIN INSTALLATION

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VERTICAL DRAIN INSTALLATION

Vacuum Preloading + PVD

47
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
INSTALLATION

Vacuum Preloading + PVD


HORIZONTAL DRAIN

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VERTICAL DRAIN DISCHARGE CAPACITY ISSUE

The purpose of using prefabricated vertical drains (PVD) is to release the excess pore water
pressure in soil and or to discharge water.

Once the water has entered the drain, it is still possible for the flow in the drain itself to be
reduced for a number of reasons (Bergado et al., 1996):

• By increasing lateral pressure, the filter passes into the core and subsequently decreases the
discharge capacity due to a reduction of the cross-sectional area available for flow (1).
Vacuum Preloading + PVD

• During consolidation, the ground will be subjected to large settlement. Thus, the drains tend to
settle together with the ground which will result in bending of folding of the drain (2).
• In the initial filtering process of flow from the soil through the drain filter, the displaced water
will contain a small portion of fine particles. These may be deposited with the core channels
and may lead to clogging of the drain (3)
• The discharge capacity may be reduced due to aging in the soil after installation, possibly due
to biological and chemical activities.
• The measured discharge capacity varies with different hydraulic gradients and is smaller when
a higher hydraulic gradient is used. This might be due to the loss of flow energy as a result of
turbulent flow at a high hydraulic gradient.

48
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VERTICAL DRAIN DISCHARGE CAPACITY ISSUE

1. reduction of
discharge area

3. Clogging

Vacuum Preloading + PVD


2. Bending or Folding
• Typically if the strain > 15%, bending / folding may influence the drainage capacity.
Lab test is done at 20%-25% strain or under 15 - 30 degree kinked condition.
• If the soil is extra soft in “colloid state” where soil particle may flow with the water
during consolidation process, clogging is highly possible to happen.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
SOIL PRELOADING – THINGS TO BE CONCERN
1. Critical initial backfill height. The original soft soil a low shear strength. Due to this
condition the 1st backfill, typically as working platform, cannot be too high. Slope
stability calculation should perform to estimate the critical initial backfill height for
working platform.
Vacuum Preloading + PVD

49
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
SOIL PRELOADING – THINGS TO BE CONCERN

2. Staging construction. When backfilling, excess pore pressure increase and lead to
lower stability safety factor. The dissipation process (and the consolidation settlement)
will takes some time. After excess pore water dissipate, the soil strength will increase
and the next stage of backfill can proceed.  monitor use piezometer.

3. PVD pull out or broken due to lateral spreading.  monitor use inclinometer.

Vacuum Preloading + PVD


4. Settlement due to vertical compression vs lateral spreading.  monitor use
extensometer.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD

VACUUM PRELOADING + PVD


Vacuum Preloading + PVD

50
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
OBSTACLE OF SOIL PRELOAD SYSTEM

Surcharge Sand / drainage


Vertical layer
drain

Vacuum Preloading + PVD


Oftentimes it is not feasible to use a soil preload because :

• The soft soil is too weak and even a low soil embankment can
cause a stability problem

• Good material for soil embankment is hard to find

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Vacuum + PVD - Characteristics:

Vacuum Load equivalent to Compressible Saturated


4m of surcharge Clay, Silt, Peat
Isotropic load Low permeability

Time and Cost savings


Vacuum Preloading + PVD

Water table close to


compared to piles surface

Foundation on slab and No or few sand contents


footings or pockets ( air and water
leakage )
No risk of slope failure : Light to medium loads
high embankments built
up in reduced period on BEFORE AFTER
soft soils

SITE CHARACTERISTICS :
• Know-how and skilled technicians required
• Difficult and care-needing technique
• Large site, important turn-over and duration exceeding 12 to 24 months

51
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM PRELOADING APPLICATION

Concerned problem What will happen without ground improvement


Bearing capacity Low , before backfill cannot run any heavy equipments.
not suitable for permanent shallow foundation sturctures

Settlement Large, both total and differential settlement, foundation, slab and road may crack

Piling work Large negative friction, reduced pile effective bearing capacity, resulting cost increase etc.

Excavation Stability risky

Vacuum Preloading + PVD


BEFORE AFTER

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
SOIL PRELOADING PRINCIPLE

Soil
preload

Vacuum Preloading + PVD

52
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM PRELOADING PRINCIPLE

Vacuum

Vacuum Preloading + PVD


Vacuum boundary

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM PRELOADING PRINCIPLE

Vacuum

Vacuum Preloading + PVD

53
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM + SOIL PRELOADING

Sealing Layer
(Geomembrane)

VACUUM PUMP Atmospheric Pressure (1Atm) VACUUM PUMP

Vacuum Preloading + PVD


SAND BLANKET

Atmospheric Atmospheric
Pressure Negative Pressure Pressure
(1Atm) (Min. 80kPa) (1Atm)

SOFT SOIL WATER SOFT SOIL

Kjellman first introduce a vacuum preloading to accelerate consolidation in


1952 and a small field test was perform.

In this method the soil load is replace by atmospheric pressure.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM PRELOAD Monitoring Equipment

Surface Settlement Plate


Piezometer
Vacuum Gauge
GEOMEMBRANE
GEOTEXTILE
Extensometer
PHS
Vacuum Preloading + PVD

SAND BLANKET

- 80kPa

Inclinometer
SOFT SOIL

WATER

54
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM + SOIL PRELOADING

Sealing Layer
(Geomembrane)

Atmospheric Pressure (1Atm) +


VACUUM PUMP VACUUM PUMP
Soil for Leveling or extra Preloading

Vacuum Preloading + PVD


SAND BLANKET

Atmospheric Atmospheric
Pressure Negative Pressure Pressure
(1Atm) (Min. 80kPa) (1Atm)

SOFT SOIL WATER SOFT SOIL

If 80 kPa from vacuum load is not enough, additional load could be applied
during improvement such as soil load.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM PRELOADING PRINCIPLE

Vacuum Preloading + PVD

55
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM PRELOADING PRINCIPLE

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Comparison: Soil Preloading and Vacuum Preloading

Soil Preloading Vacuum Preloading


ROW ROW
Surcharge
Surcharge Surcharge
Surcharge

Pavement

SandBlanket
Sand Blanket Berm
Berm Berm
Berm
Vacuum Preloading + PVD

Vertical
Vertical Vertical
Vertical
Drain
Drain Drain
Drain
Soft
SoftClay
Clay Soft
SoftClay
Clay

• Wide area • Narrow area


• High soil surcharge • Lower or no soil surcharge
• Need thick horizontal drain • Relatively thin horizontal drain
• Lower Stability • Better Control of Stability
• Greater Lateral Movement • Lesser Lateral Movement
• Longer Construction Time • Shorter Construction Time

56
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
VACUUM PRELOADING
CONSTRUCTION METHOD

Vacuum Preloading + PVD


CASE : PALEMBANG – INDRALAYA
TOLL ROAD

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Panjang : 21,93 km
Kecepatan Rencana : 100 km/jam

Konstruksi : At grade dgn perbaikan tanah


GENERAL LAYOUT

Jumlah lajur awal : 2x2


Jumlah lajur akhir : 2x3

Lebar jalur lalulintas : 3,6 m


Lebar bahu dalam : 1,5 m
Lebar bahu luar : 3m
Vacuum Preloading + PVD

57
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Depth
BH-01 BH-02 BH-03 BH-04 BH-05 BH-06 BH-07 BH-08 BH-09 BH-10 BH-11 BH-12 BH-13 BH-14
ORIGINAL SOIL CONDITION

(m)
STA 1+000 1+850 3+650 5+900 7+125 8+050 9+625 12+000 14+100 16+100 17+650 19+000 20+050 21+400

1.5 0 0 0 0 0 0 2 4 0 19 1 5 0 18
3.0 0 1 0 2 0 0 0 8 0 13 0 7 2 16
4.5 1 1 2 2 0 1 0 9 2 16 0 8 6 16
(Toll road references)

6.0 3 1 0 5 1 5 0 12 2 18 0 7 13 13
7.5 0 1 2 9 1 5 6 9 3 20 4 8 19 14
9.0 0 2 4 17 5 5 6 7 10 17 3 6 31 18
10.5 1 3 7 13 5 2 8 1 7 19 2 11 36 15
12.0 2 4 9 4 7 3 0 1 8 53 2 14 40 18

Vacuum Preloading + PVD


13.5 6 4 12 9 7 10 2 2 3 56 18 14 40 21
15.0 14 12 14 9 15 11 2 3 10 58 13 32 32 15
16.5 8 13 35 9 20 19 4 8 15 36 14 25 35 16
18.0 10 14 50 23 20 18 5 17 24 41 10 26 38 17
19.5 23 16 50 22 20 25 6 15 24 40 14 27 40 21
21.0 24 18 8 26 50 27 13 16 30 34 15 23 41 20
22.5 28 22 43 29 50 40 31 15 27 49 11 21 39 34
24.0 25 24 27 20 50 62 35 17 36 41 50 21 40 39

No CONSISTENCY SPT (N)


1 Very soft <2
STA 0+000 sd 7+000
2 Soft 2-4
3 Medium Stiff 4-8
4 Stiff 8 - 15

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
ORIGINAL SOIL CONDITION
(Toll road references)

Vacuum Preloading + PVD

58
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
ORIGINAL SOIL CONDITION

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
ORIGINAL SOIL CONDITION

Vacuum Preloading + PVD

59
1. Typical initial site condition 1. Typical initial site condition
(toll road references) (toll road references)
Pendahuluan

Pendahuluan
Chemical

Chemical
Mechanical

Mechanical

Tol Kapal Betung


Drainage

Drainage

Vacuum Preloading + PVD Preloading + PVD Vacuum Preloading + PVD Preloading + PVD

60
14/08/2020
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
1. Typical initial site condition
(toll road references)

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
2. Site preparation
(toll road references)

Vacuum Preloading + PVD

Tol Kapal Betung

Stripping work - Geotextile spreading - Access road

61
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Stripping work

Geotextile spreading
2. Site preparation

(with) settlement plate


(toll road references)

Access road

Vacuum Preloading + PVD


Geotextile as separator:
1. To separate backfill
material and original
soft clay
2. To avoid any dispute
about backfill
material calculation.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
2. Site preparation
(toll road references)

Vacuum Preloading + PVD

Stripping work - Geotextile spreading - Access road

62
14/08/2020

Pendahuluan Chemical Mechanical Drainage


3. Construct working platform
(toll road references)

Typically working platform use all sand or soil with top 0.5 m sand as drainage layer
(sand permeability > 5 x 10-3 cm/sec).
Under certain condition, sand is really difficult to get or very expensive. Here soil can
use as platform with modification on horizontal drainage system.
Cannot use organic soil, expansive soil or other problematic soil type.

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
3. Construct working platform
(toll road references)

Vacuum Preloading + PVD

63
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
4. Install PVD on sand platform
(toll road references)

Vacuum Preloading + PVD


Aware of soil type below the PVD

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
5. Install PHD on sand platform
(toll road references)

Vacuum Preloading + PVD

Aware of sharp material


on ground

64
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
5. Install PHD on sand platform
(toll road references)

Vacuum Preloading + PVD


Aware of sharp material
on ground

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
6. Geotextile installation (1st layer)
(toll road references)

Vacuum Preloading + PVD

Aware of connection
between geotextile

65
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
7. Geomembrane installation
(toll road references)

Vacuum Preloading + PVD


Aware of broken membrane

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
7. Geomembrane installation
(toll road references)

Vacuum Preloading + PVD

Aware of broken membrane

66
14/08/2020

67
Preloading + PVD Vacuum Preloading + PVD
Preloading + PVD Vacuum Preloading + PVD Preloading + PVD Vacuum Preloading + PVD
Drainage

Drainage
Mechanical

Mechanical
Chemical

Chemical
Pendahuluan

Pendahuluan
(toll road references) (toll road references)
7. Geomembrane installation 7. Geomembrane installation
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
8. Geomembrane lock at perimeter
(toll road references)

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
8. Geomembrane lock at perimeter
(toll road references)

Vacuum Preloading + PVD

Aware of leakage from


the ditch

68
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
8. Geomembrane lock at perimeter
(toll road references)

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
8. Geomembrane lock at perimeter
(toll road references)

Vacuum Preloading + PVD

Aware of non-uniform
mixture or gap between
slurry pile. Permeability < 1 x 10-5 cm/sec

69
9. Install instrumentation 8. Geomembrane lock at perimeter
(toll road references) (toll road references)

Pendahuluan
Pendahuluan

Chemical
Chemical

Mechanical
Mechanical

Drainage
Drainage

Vacuum Preloading + PVD Preloading + PVD

70
14/08/2020
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
9. Install instrumentation
(toll road references)

Vacuum Preloading + PVD


Settlement plate Extensometer
Piezometer reader

extensometer Vacuum
Inclinometer Vacuum Gauge
degree

Piezometer Piezometer reading

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
9. Install instrumentation
(toll road references)

Vacuum Preloading + PVD

Settlement but no pore pressure dissipation?

71
9. Install instrumentation 9. Install instrumentation
(toll road references) (toll road references)

Pendahuluan
Pendahuluan

Chemical
Chemical

Mechanical
Mechanical

Drainage
Drainage

Vacuum Preloading + PVD Preloading + PVD Vacuum Preloading + PVD Preloading + PVD

72
14/08/2020
10. Install and start vacuum process 10. Install and start vacuum process
(toll road references) (toll road references)

Pendahuluan
Pendahuluan

Chemical
Chemical

Mechanical
Mechanical

Drainage
Drainage

Vacuum Preloading + PVD Preloading + PVD Vacuum Preloading + PVD Preloading + PVD

73
14/08/2020
10. Install and start vacuum process
11. Backfill during vacuum process (toll road references)
Pendahuluan

Pendahuluan
Chemical

Chemical
Mechanical

Mechanical
Drainage

Drainage

Vacuum Preloading + PVD Preloading + PVD Vacuum Preloading + PVD Preloading + PVD

74
14/08/2020
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
11. Backfill during vacuum process

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
11. Backfill during vacuum process

Vacuum Preloading + PVD

Aware of backfill quality, both material


and compaction techniques.

CONTROL THE OPTIMUM WATER


CONTENT is the most important but very
difficult.

75
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
11. Backfill during vacuum process

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
11. Backfill during vacuum process

Vacuum Preloading + PVD

Aware of backfill method  may


broken the membrane.

76
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Before and After Vacuum Preloading
(Power Plant references)

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Before and After Vacuum Preloading
(Sinarmas Pulp and Paper Factory, South Sumatera)

 Before Vacuum
Preloading
Vacuum Preloading + PVD

After Vacuum Preloading 

77
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Before and After Vacuum Preloading
(Industrial Estate references)

Vacuum Preloading + PVD


Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Toll road monitoring

TOTAL SETTLEMENT (MM) VS TIME (DATE)


0 10

-200 0

-400 -10
(references only)

-600 -20

-800 -30
No.1
-1000 -40
Vacuum Preloading + PVD

No.2
-1200 -50

No.3
-1400 -60

-1600 No.4 -70

-1800 No.5 -80

-2000 -90

Left : Consolidation settlement at Palindra


Toll Road, South Sumatera.

Right : Consolidation settlement at Ho Chi


Minh - Long Thanh - Dau Giay
Expressway, Vietnam

78
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Toll road monitoring
(references only)

Vacuum Preloading + PVD


Pore Water Pressure and Time in Zone 5.

Relationship between Load vs Settlement Lateral displacement curves near zone 5

Distributions of Layered Settlement in Zone 5 (STA 4+925)

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Toll road monitoring
(references only)

Vacuum Preloading + PVD

Compared CPT Results between before and after


Vacuum in Zone 5 (Sta 4+925)

79
14/08/2020

Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Preloading + PVD
Degree of Consolidation
(references only)

Vacuum Preloading + PVD


Vacuum Preloading + PVD
Pendahuluan Chemical Mechanical Drainage

Preloading + PVD
Degree of Consolidation
(references only)

Vacuum Preloading + PVD

Asaoka method to predict the total consolidation settlement


and calculate the degree of consolidation.

80
14/08/2020

Penutup
(6) Faktor yang Mempengaruhi Pemilihan Metode Perbaikan

Jenis Tanah Ketersediaan Material


Butir halus atau butir kasar
Lokasi, material, biaya.

Area, Kedalaman, Lokasi


Self explanation
Ketersediaan SDM
terutama pada metode baru dan
‘unproven’.

Lingkungan Ekonomi
Penggunaan material & dampak
Biaya.
pekerjaan terhadap lingkungan.

Aksan KAWANDA

0811.851.613 aksan.geotech@gmail.com aksankawanda

81

Anda mungkin juga menyukai