DYNAMIC

LOADING
TEST
REPORT
(ASTM-D4945-17)
High Strain
Dynamic Testing

RUMAH SAKIT
UMUM DAERAH
TORA BELO

Kabupaten Sigi
Sulawesi Tengah

JOB : 2P.21015

Maret 2021

Prepared by:

Jl. Raya Kebayoran Lama No. 345


Sukabumi Utara, Kebon Jeruk
Jakarta Barat 11540
Telp. (021) 5308689 (Hunting)
bumiyasa@tarumanegara.co.id
marketing_tb@tarumanegara.co.id
www.tarumanegara.co.id
PILE DYNAMIC ANALYSIS REPORT
RUMAH SAKIT UMUM DAERAH TORA BELO
Kabupaten Sigi, Sulawesi Tengah
PT. Dwi Tunggal Surya Jaya

DAFTAR ISI

SURAT PENGANTAR
DAFTAR ISI i

1.0 PENDAHULUAN 1
1.1 UMUM …………………………………………………………..………………………………………… 1
1.2 TUJUAN …………………………………………………………………………………..………….…… 1
1.3 LINGKUP PENGUJIAN …………………………………………………………..…………………… 1

2.0 PROSEDUR PENGUJIAN DAYA DUKUNG TIANG DENGAN PDA 2


2.1 GELOMBANG AKIBAT TUMBUKAN (IMPACT WAVE) …………………………..……. 2
2.2 INSTRUMENTASI PDA ……………………………………………………….……………………… 2
2.2.1 Strain Transducer dan Accelerometer .…………………………………….……………. 2
2.2.2 Computer Laptop PDA …………………………………………………………..……………… 2
2.3 PEMASANGAN INSTRUMEN PDA …..………………………………………………………… 2
2.4 PEKERJAAN PERSIAPAN ……………………………….…………………………………………… 3
2.5 PELAKSANAAN PENGUJIAN DINAMIS PDA ………………………………………………… 3

3.0 DISKUSI DAN EVALUASI 4


3.1 EFISIENSI TUMBUKAN HAMMER …………………………………….………………………… 4
3.2 TEGANGAN TIANG ……………………………………………………………………………………. 4
3.3 DAYA DUKUNG TIANG ……………………………..………………………………………………. 4

4.0 KESIMPULAN DAN REKOMENDASI 5


LAMPIRAN
A. HASIL PDA TEST dan ANALISIS CAPWAP
B. INSTALASI SENSOR dan KALIBRASI SENSOR
C. DOKUMENTASI

PT. TARUMANEGARA Bumiyasa


PILE DYNAMIC ANALYSIS REPORT
RUMAH SAKIT UMUM DAERAH TORA BELO
Kabupaten Sigi, Sulawesi Tengah
PT. Dwi Tunggal Surya Jaya

1.0
PENDAHULUAN

1.1 UMUM
Berdasarkan permintaan dari PT. Dwi Tunggal Surya Jaya pada PT. TARUMANEGARA Bumiyasa Jakarta
untuk melakukan pengujian Pile Driving Analysis, maka pada tanggal 3 Maret 2021 telah dilakukan
pengujian dinamis, Pile Driving Analysis, Bored pile Ø 400 mm pada proyek RUMAH SAKIT UMUM DAERAH
TORA BELO yang berlokasi di Kabupaten Sigi, Sulawesi Tengah dimana pemilihan tiang yang diuji
ditentukan oleh pemberi tugas.

1.2 TUJUAN
Tujuan dari pengujian dinamis, Pile Driving Analysis adalah untuk mengetahui besarnya Daya Dukung
Ultimate Bored pile Ø 400 mm tersebut.

1.3 LINGKUP PENGUJIAN


Pengujian dinamis untuk mendeteksi Daya Dukung Ultimate, dilakukan terhadap Bored pile Ø 400 mm,
dengan alat Pile Driving Analyzer (PDA). Lokasi titik tiang bor yang diuji PDA yaitu :

Tabel 1.1. Ringkasan tiang yang di uji

No. No. As-Tiang Dimensi Tiang Tanggal Pengujian

1 BP 10 Bored pile Ø 400 mm 3 Maret 2021

2 BP 26 Bored pile Ø 400 mm 3 Maret 2021

PT. TARUMANEGARABumiyasa |1
PILE DYNAMIC ANALYSIS REPORT
RUMAH SAKIT UMUM DAERAH TORA BELO
Kabupaten Sigi, Sulawesi Tengah
PT. Dwi Tunggal Surya Jaya

2.0
PROSEDUR PENGUJIAN DAYA DUKUNG TIANG DENGAN PDA

2.1 GELOMBANG AKIBAT TUMBUKAN (IMPACT WAVE)


Pengujian dinamis dengan PDA dilaksanakan dengan menginterprestasikan gelombang satu dimensi (one
dimensional wave) yang merambat pada media yang diuji. Gelombang ini di dapat dengan memberikan
tumbukan (impact) pada tiang uji sehingga menghasilkan gelombang yang sesuai dengan kebutuhan
pengujian. Untuk pengujian dinamis PDA, Tiang bor ditumbuk dengan tipe Drop Hammer 3.0 ton.

2.2 INSTRUMENTASI PDA


2.2.1 STRAIN TRANSDUCER DAN ACCELEROMETER
Untuk mengukur regangan dan percepatan selama perambatan gelombang akibat tumbukan yang
diberikan pada tiang, Strain Transducer dan Accelerometer dipasang pada bagian atas tiang dengan jarak
lebih besar dari 1.5W-2W dari ujung atas tiang, dimana W adalah lebar penampang tiang, untuk
mendapatkan hasil rekaman yang baik. Untuk mencegah tidak bekerjanya Instrument pada saat
penumbukan maka dipasang Strain Transducer dan Accelerometer sebanyak masing-masing 2 buah di
keempat sisi tiang.

2.2.2 COMPUTER LAPTOP PDA


Hasil pengukuran direkam dengan alat Computer PDA PAX dari GRL USA di lapangan dan dianalisa dengan
Case Method (CAPWAP) berdasarkan teori gelombang satu dimensi.

2.3 PEMASANGAN INSTRUMEN PDA


Sesuai ketentuan ASTM D 4945-17 maka pemasangan Instrumen Strain Transducer harus dilakukan
sedemikian rupa untuk menghindari pengaruh selama penumbukan. Sehingga pengaruh faktor momen
diabaikan untuk mendapatkan nilai N aksial sebesar mungkin. Pemasangan instrument diletakkan pada titik
sejauh sekitar 90 cm dari kepala tiang (lihat gambar terlampir).

PT. TARUMANEGARABumiyasa |2
PILE DYNAMIC ANALYSIS REPORT
RUMAH SAKIT UMUM DAERAH TORA BELO
Kabupaten Sigi, Sulawesi Tengah
PT. Dwi Tunggal Surya Jaya

2.4 PEKERJAAN PERSIAPAN


Sebelum pengujian dinamis dilaksanakan, telah dilakukan beberapa pekerjaan persiapan untuk PDA dengan
mencatat hal-hal yang perlu diperhatikan antara lain :
a. Pengeboran lubang pada Bored Pile untuk pemasangan Strain Transducer dan Accelerometer PDA.
b. Beberapa hal yang perlu diperhatikan dan dicatat :
1. Nomor Tiang yang akan diuji.
2. Denah lokasi titik yang akan diuji.
3. Berat palu / Hammer.
4. Tinggi jatuh Hammer.
5. Tanggal Pemancangan.
6. Tanggal Pengujian.

2.5 PELAKSANAAN PENGUJIAN DINAMIS PDA


Tiang bor yang akan diuji PDA diberi beberapa kali tumbukan, dimana penumbukan dihentikan jika telah
diperoleh mutu rekaman pada komputer yang cukup baik dan energi tumbukan (EMX) yang relatif cukup
tinggi. Untuk didapatkan kualitas rekaman yang baik tergantung dari beberapa faktor antara lain
pemasangan instrumen terpasang cukup kuat pada tiang beton, sistem elektronik komputer dan efisiensi
hammer yang dipergunakan. Pada saat pengujian secara temporary dilakukan pengecekan / pengencangan
baut-baut instrumen Strain Transducer dan Accelerometer. Dilakukan beberapa tumbukan sesuai
kebutuhan, jika telah didapatkan nilai EMX yang relatif tinggi maka tumbukan dihentikan, dimana nilai EMX
tergantung dari nilai efisiensi Hammer yang dipakai. Semua pengujian dinamis dilaksanakan sesuai dengan
ketentuan ASTM D 4945-17.

Hasil pengujian dinamis dengan PDA dianalisa lebih lanjut dengan CAPWAP untuk mendapatkan
perbandingan kekuatan daya dukung termasuk distribusi kekuatan friksi tanah (friction) di setiap lapisan,
tahanan ujung, tegangan tiang, dan lain-lain.

PT. TARUMANEGARABumiyasa |3
PILE DYNAMIC ANALYSIS REPORT
RUMAH SAKIT UMUM DAERAH TORA BELO
Kabupaten Sigi, Sulawesi Tengah
PT. Dwi Tunggal Surya Jaya

3.0

DISKUSI DAN EVALUASI

3.1 EFISIENSI TUMBUKAN HAMMER


Dari beberapa tumbukan pada tiang yang diuji, efisiensi transfer energy hammer pada drop hammer 3.0
ton dengan tinggi jatuh 1.00 meter mencapai sekitar 11.67 % hingga 45.33 % untuk Bored pile Ø 400 mm.

3.2 TEGANGAN TIANG


Tegangan tekan dan tegangan tarik maksimum yang diukur dekat kepala tiang pada saat pengujian tiang
dilaksanakan dapat dilihat pada Tabel 3.1.

Tabel 3.1. Maksimum Tegangan Tekan dan Tegangan Tarik

CSX TSX EMX BTA


No. No. Tiang
(MPa) (MPa) tn-m %

1 BP 10* 7.2 1.8 0.35 39.0

2 BP 26 19.1 5.6 1.36 100.0

Umumnya untuk tiang bor, batas tegangan tekan yang diperbolehkan sebesar 0.85fc’ dan batas tegangan
tarik yang diperbolehkan sebesar 0.7fy(As/Ac).

3.3 DAYA DUKUNG TIANG


Dari hasil pengujian dinamis kondisi “restrike “, kemudian analisa daya dukung dengan program komputer
CAPWAP pada tiang yang diuji, diperoleh daya dukung ultimate tiang seperti pada Tabel 3.2.

Tabel 3.2. Ringkasan hasil PDA test dan CAPWAP adalah sebagai berikut :
Dimensi Tiang
Daya Dukung (ton)
yang Tertanam
No. No. Jenis Uji
PDA CAPWAP
Tiang PDA
Panjang
Penampang RMX Friksi Ujung Total
(m)
Bored pile Ø
1 BP 10* Restrike 17.6 128 112.2 33.2 145.4
400 mm
Bored pile Ø
2 BP 26 Restrike 17.7 206 176.8 51.0 227.8
400 mm

PT. TARUMANEGARABumiyasa |4
PILE DYNAMIC ANALYSIS REPORT
RUMAH SAKIT UMUM DAERAH TORA BELO
Kabupaten Sigi, Sulawesi Tengah
PT. Dwi Tunggal Surya Jaya

4.0
KESIMPULAN DAN REKOMENDASI

Dari hasil evaluasi tersebut di atas, memiliki daya dukung tekan ultimate sebagai berikut :

Tabel 4.1. Daya Dukung Ultimate

No. No. Tiang Penampang Qultimate (ton)

1 BP 10* Bored pile Ø 400 mm 145.4

2 BP 26 Bored pile Ø 400 mm 227.8

Catatan:

∗ Untuk tiang dengan nomor: BP 10 terdapat hal yang harus diperhatikan, antara lain:
1. Nilai BTA yang tersaji pada Tabel 3.1. agar tidak dijadikan sebagai acuan penilaian integritas tiang dikarenakan grafik force-
velocity yang diperoleh tidak proporsional.
2. Kemudian pada Tabel 3.1. terlihat nilai CSX, TSX dan EMX cukup kecil jika dibandingkan dengan tiang BP 26 dimana tinggi
jatuh hammer pada saat pengujian yaitu sama-sama 1.00 meter. Hal ini dapat terjadi mengingat kepala tiang BP 10 pecah
setelah ditumbuk hammer.
• Perlu diingat bahwa daya dukung ultimate tiang tersebut di atas adalah daya dukung ultimate tanah pendukung tiang tunggal
pada saat pengujian, sehingga daya dukung ijin perencanaan harus disesuaikan juga dengan daya dukung ijin bahan tiang yang
digunakan.
• Agar dapat menjadi pertimbangan bahwa daya dukung ijin material tiang boredpile (mutu beton K-300) dengan diameter
400 mm yaitu sebesar 78 ton. Maka sangat tidak disarankan beban rencana melebihi kapasitas bahan tiang yang
digunakan.
• Efisiensi kelompok tiang harus senantiasa diperhitungkan sesuai dengan jumlah, jarak dan susunan kelompok tiang yang
terpasang. Berhubung daya dukung tersebut di atas adalah daya dukung tiang tunggal.
• Penurunan total dan perbedaan penurunan (Differential Settlement) secara long term perlu diperhitungkan sesuai dengan
toleransi yang diijinkan untuk utilitas bangunan di atasnya.

PT. TARUMANEGARABumiyasa |5
LAMPIRAN A

HASIL PDA TEST dan ANALISIS CAPWAP


TARUMANEGARA Bumiyasa
RSUD TORA BELO PILE DRIVING ANALYZER ®
PDA OP: KUS Version 2016.125
BP 10
BOREDPILE 400, DH 3.0 TON
BN 3
3/3/2021 3:48:51 PM
300 2.71 CSX 7.2 MPa
tn m/s TSX 1.8 MPa
BTA 39.0 (%)
F V RAU 0 tn
RA2 123 tn
RSU 155 tn
RMX 128 tn
EMX 0.35 tn-m
DFN 1 mm

LE 17.8 m
AR 1256.64 cm^2
51.2ms
EM 317 t/cm2
9.90 ms SP 2.40 t/m3
WS 3600.0 m/s
300 300 EA/C 110.7 tn-s/m
tn tn LP 17.6 m
WD WU
F12 A1

F1: [F721] 97.8 (1.1)


F2: [R166] 147.8 (1.1)
A1: [32356] 1070 g's/v (0.9)

51.2ms

300 300
tn tn

R[T] R[S]
JC=0.50

51.2ms

6.12 60
tn-m mm

E D

51.2ms
RSUD TORA BELO; Pile: BP 10; BOREDPILE 400, DH 3.0 TON; Blow: 3 (Test: 03-Mar-2021 15:48:) 05-Mar-2021
TARUMANEGARA Bumiyasa CAPWAP(R) 2006-3

250 tons 250 tons


Force Msd Force Msd
Force Cpt Velocity Msd

125 125

5 85 ms 5 85 ms
0 0
12 L/c 12 L/c

-125 -125

Load (tons) 16
Pile Top
Bottom Shaft Resistance
0 40 80 120 160 Distribution
0.000 12

tons/m
8
Ru = 145.4 tons
Rs = 112.2 tons
2.000 Rb = 33.2 tons
Dy = 5.9 mm 4
Displacement (mm)

Dx = 7.0 mm

0
Pile Force
4.000
at Ru
40
tons

80
6.000
120

160
8.000

CAPWAP(R) 2006-3 Licensed to TARUMANEGARA Bumiyasa


RSUD TORA BELO; Pile: BP 10 Test: 03-Mar-2021 15:48:
BOREDPILE 400, DH 3.0 TON; Blow: 3 CAPWAP(R) 2006-3
TARUMANEGARA Bumiyasa OP: KUS
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 145.4; along Shaft 112.2; at Toe 33.2 tons
Soil Dist. Depth Ru Force Sum Unit Unit Smith Quake
Sgmnt Below Below in Pile of Resist. Resist. Damping
No. Gages Grade Ru (Depth) (Area) Factor
m m tons tons tons tons/m tons/m2 s/m mm

145.4
1 1.0 0.9 0.0 145.4 0.0 0.00 0.00 0.000 1.888
2 2.1 1.9 0.0 145.4 0.0 0.00 0.00 0.000 1.891
3 3.1 3.0 0.3 145.0 0.3 0.33 0.27 0.769 1.891
4 4.2 4.0 1.8 143.3 2.1 1.68 1.34 0.769 1.891
5 5.2 5.1 4.5 138.8 6.6 4.28 3.40 0.769 1.891
6 6.3 6.1 7.9 130.9 14.5 7.54 6.00 0.769 1.891
7 7.3 7.2 10.7 120.2 25.2 10.24 8.15 0.769 1.891
8 8.4 8.2 12.1 108.1 37.3 11.51 9.16 0.769 1.891
9 9.4 9.3 12.0 96.1 49.2 11.42 9.09 0.769 1.891
10 10.5 10.3 11.0 85.1 60.2 10.52 8.37 0.769 1.824
11 11.5 11.4 9.8 75.3 70.0 9.35 7.44 0.769 1.622
12 12.6 12.4 8.7 66.7 78.7 8.30 6.60 0.769 1.412
13 13.6 13.5 7.7 58.9 86.4 7.37 5.87 0.769 1.225
14 14.7 14.5 6.9 52.1 93.3 6.57 5.23 0.769 1.063
15 15.7 15.6 6.4 45.7 99.7 6.07 4.83 0.769 0.926
16 16.8 16.6 6.2 39.5 105.9 5.95 4.73 0.769 0.723
17 17.8 17.6 6.3 33.2 112.2 5.99 4.77 0.769 0.550

Avg. Shaft 6.6 6.36 5.06 0.769 1.532


Toe 33.2 264.20 1.314 1.004
Soil Model Parameters/Extensions Shaft Toe
Case Damping Factor 0.779 0.394
Unloading Quake (% of loading quake) 100 76
Reloading Level (% of Ru) 100 100
Unloading Level (% of Ru) 12
Soil Plug Weight (tons) 0.89

CAPWAP match quality = 4.68 (Wave Up Match) ; RSA = 0


Observed: final set = 1.132 mm; blow count = 883 b/m
Computed: final set = 0.100 mm; blow count = 9999 b/m
max. Top Comp. Stress = 0.079 tons/cm2 (T= 29.7 ms, max= 1.172 x Top)
max. Comp. Stress = 0.092 tons/cm2 (Z= 5.2 m, T= 28.8 ms)
max. Tens. Stress = -0.007 tons/cm2 (Z= 9.4 m, T= 42.2 ms)
max. Energy (EMX) = 0.35 tonne-m; max. Measured Top Displ. (DMX)= 4.80 mm

Page 1 Analysis: 05-Mar-2021


RSUD TORA BELO; Pile: BP 10 Test: 03-Mar-2021 15:48:
BOREDPILE 400, DH 3.0 TON; Blow: 3 CAPWAP(R) 2006-3
TARUMANEGARA Bumiyasa OP: KUS
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.
Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.
No. Gages Stress Stress Energy
m tons tons tons/cm2 tons/cm2 tonne-m m/s mm
1 1.0 99.0 -0.0 0.079 -0.000 0.35 0.7 4.306
2 2.1 104.1 -0.0 0.083 -0.000 0.33 0.7 4.052
3 3.1 109.1 -0.0 0.087 -0.000 0.32 0.6 3.787
4 4.2 113.3 -1.3 0.090 -0.001 0.31 0.6 3.509
5 5.2 116.0 -3.8 0.092 -0.003 0.28 0.6 3.222
6 6.3 115.3 -5.5 0.092 -0.004 0.25 0.5 2.938
7 7.3 110.1 -7.1 0.088 -0.006 0.22 0.5 2.666
8 8.4 101.2 -8.1 0.081 -0.006 0.18 0.5 2.427
9 9.4 92.2 -8.5 0.073 -0.007 0.15 0.4 2.222
10 10.5 82.9 -7.9 0.066 -0.006 0.13 0.4 2.037
11 11.5 75.2 -7.9 0.060 -0.006 0.11 0.4 1.868
12 12.6 67.8 -6.8 0.054 -0.005 0.09 0.4 1.716
13 13.6 59.9 -5.4 0.048 -0.004 0.07 0.3 1.576
14 14.7 52.7 -4.0 0.042 -0.003 0.06 0.3 1.451
15 15.7 48.5 -5.2 0.039 -0.004 0.05 0.3 1.339
16 16.8 45.3 -5.4 0.036 -0.004 0.04 0.3 1.238
17 17.8 38.6 -5.0 0.031 -0.004 0.03 0.3 1.151
Absolute 5.2 0.092 (T = 28.8 ms)
9.4 -0.007 (T = 42.2 ms)

CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
RP 132.7 131.0 129.2 127.5 125.8 124.1 122.3 120.6 118.9 117.1
RX 142.5 139.4 136.3 133.2 130.4 127.8 125.3 122.8 120.3 117.9
RU 153.1 153.4 153.7 154.0 154.3 154.6 154.9 155.2 155.5 155.8
RAU = 0.0 (tons); RA2 = 123.3 (tons)
Current CAPWAP Ru = 145.4 (tons); Corresponding J(RP)= 0.00; J(RX) = 0.00

VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUS
m/s ms tons tons tons mm mm mm tonne-m tons
0.83 25.89 86.9 63.1 92.7 4.797 1.140 1.132 0.4 119.7
Possible Pile Damage at 0.16 L Below Gages?

Page 2 Analysis: 05-Mar-2021


RSUD TORA BELO; Pile: BP 10 Test: 03-Mar-2021 15:48:
BOREDPILE 400, DH 3.0 TON; Blow: 3 CAPWAP(R) 2006-3
TARUMANEGARA Bumiyasa OP: KUS
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.
m cm2 tons/cm2 tons/m3 m
0.00 1256.64 317.2 2.400 1.257
17.80 1256.64 317.2 2.400 1.257
Toe Area 0.126 m2
Top Segment Length 1.05 m, Top Impedance 110.71 tons/m/s

Pile Damping 3.0 %, Time Incr 0.291 ms, Wave Speed 3600.0 m/s, 2L/c 9.9 ms

Page 3 Analysis: 05-Mar-2021


TARUMANEGARA Bumiyasa
RSUD TORA BELO PILE DRIVING ANALYZER ®
PDA OP: KUS Version 2016.125
BP 26
BOREDPILE 400, DH 3.0 TON
BN 2
3/3/2021 5:18:47 PM
500 4.52 CSX 19.1 MPa
tn m/s TSX 5.6 MPa
BTA 100.0 (%)
F V RAU 0 tn
RA2 151 tn
RSU 268 tn
RMX 206 tn
EMX 1.36 tn-m
DFN 1 mm

LE 17.8 m
AR 1256.64 cm^2
102.4ms
EM 317 t/cm2
9.90 ms SP 2.40 t/m3
WS 3600.0 m/s
500 500 EA/C 110.7 tn-s/m
tn tn LP 17.7 m
WD WU
F12 A12

F1: [F721] 97.8 (1)


F2: [R166] 147.8 (1)
A1: [32356] 1070 g's/v (1)
A2: [32354] 1190 g's/v (1)

102.4ms

500 500
tn tn

R[T] R[S]
JC=0.50

102.4ms

6.12 60
tn-m mm

E D

102.4ms
RSUD TORA BELO; Pile: BP 26; BOREDPILE 400, DH 3.0 TON; Blow: 2 (Test: 03-Mar-2021 17:18:) 05-Mar-2021
TARUMANEGARA Bumiyasa CAPWAP(R) 2006-3

450 tons 450 tons


Force Msd Force Msd
Force Cpt Velocity Msd

225 225

5 85 ms 5 85 ms
0 0
12 L/c 12 L/c

-225 -225

Load (tons) 32
Pile Top
Bottom Shaft Resistance
0 70 140 210 280 Distribution
0.000 24

tons/m
16
Ru = 227.8 tons
Rs = 176.8 tons
3.750 Rb = 51.0 tons
Dy = 10.9 mm 8
Displacement (mm)

Dx = 12.1 mm

0
Pile Force
7.500
at Ru
70
tons

140
11.250
210

280
15.000

CAPWAP(R) 2006-3 Licensed to TARUMANEGARA Bumiyasa


RSUD TORA BELO; Pile: BP 26 Test: 03-Mar-2021 17:18:
BOREDPILE 400, DH 3.0 TON; Blow: 2 CAPWAP(R) 2006-3
TARUMANEGARA Bumiyasa OP: KUS
CAPWAP SUMMARY RESULTS
Total CAPWAP Capacity: 227.8; along Shaft 176.8; at Toe 51.0 tons
Soil Dist. Depth Ru Force Sum Unit Unit Smith Quake
Sgmnt Below Below in Pile of Resist. Resist. Damping
No. Gages Grade Ru (Depth) (Area) Factor
m m tons tons tons tons/m tons/m2 s/m mm

227.8
1 1.0 0.9 0.0 227.8 0.0 0.00 0.00 0.000 2.484
2 2.1 2.0 1.1 226.7 1.1 1.05 0.84 1.313 2.485
3 3.1 3.0 2.1 224.6 3.2 1.99 1.58 1.313 2.485
4 4.2 4.1 2.2 222.4 5.3 2.06 1.64 1.313 2.485
5 5.2 5.1 4.8 217.6 10.2 4.62 3.68 1.313 2.485
6 6.3 6.2 8.0 209.5 18.2 7.68 6.11 1.313 2.485
7 7.3 7.2 9.7 199.8 28.0 9.29 7.39 1.313 2.485
8 8.4 8.3 9.9 189.9 37.9 9.46 7.53 1.313 2.485
9 9.4 9.3 5.3 184.6 43.2 5.10 4.06 1.313 2.485
10 10.5 10.4 2.4 182.2 45.6 2.24 1.79 1.313 2.485
11 11.5 11.4 2.9 179.3 48.4 2.76 2.20 1.313 2.485
12 12.6 12.5 9.1 170.2 57.6 8.70 6.92 1.313 2.485
13 13.6 13.5 19.3 150.9 76.8 18.42 14.66 1.313 2.485
14 14.7 14.6 23.1 127.9 99.9 22.03 17.53 1.313 2.294
15 15.7 15.6 26.2 101.6 126.1 25.03 19.92 1.313 2.000
16 16.8 16.7 24.1 77.5 150.2 23.04 18.33 1.313 1.783
17 17.8 17.7 26.5 51.0 176.8 25.33 20.16 1.313 1.624

Avg. Shaft 10.4 9.99 7.95 1.313 2.163


Toe 51.0 405.93 0.080 2.061
Soil Model Parameters/Extensions Shaft Toe
Case Damping Factor 2.096 0.037
Damping Type Smith
Unloading Quake (% of loading quake) 34 128
Reloading Level (% of Ru) 100 100
Resistance Gap (included in Toe Quake) (mm) 0.454
Soil Plug Weight (tons) 0.30

CAPWAP match quality = 3.02 (Wave Up Match) ; RSA = 0


Observed: final set = 1.200 mm; blow count = 833 b/m
Computed: final set = 0.043 mm; blow count = 23240 b/m
max. Top Comp. Stress = 0.178 tons/cm2 (T= 23.8 ms, max= 1.067 x Top)
max. Comp. Stress = 0.189 tons/cm2 (Z= 5.2 m, T= 25.0 ms)
max. Tens. Stress = -0.033 tons/cm2 (Z= 5.2 m, T= 38.1 ms)
max. Energy (EMX) = 1.37 tonne-m; max. Measured Top Displ. (DMX)= 6.67 mm

Page 1 Analysis: 05-Mar-2021


RSUD TORA BELO; Pile: BP 26 Test: 03-Mar-2021 17:18:
BOREDPILE 400, DH 3.0 TON; Blow: 2 CAPWAP(R) 2006-3
TARUMANEGARA Bumiyasa OP: KUS
EXTREMA TABLE
Pile Dist. max. min. max. max. max. max. max.
Sgmnt Below Force Force Comp. Tens. Trnsfd. Veloc. Displ.
No. Gages Stress Stress Energy
m tons tons tons/cm2 tons/cm2 tonne-m m/s mm
1 1.0 223.1 -27.9 0.178 -0.022 1.37 1.9 7.579
2 2.1 228.7 -33.8 0.182 -0.027 1.35 1.9 7.243
3 3.1 232.5 -37.6 0.185 -0.030 1.31 1.8 6.889
4 4.2 234.9 -39.8 0.187 -0.032 1.25 1.7 6.524
5 5.2 238.0 -41.4 0.189 -0.033 1.19 1.6 6.143
6 6.3 233.1 -38.9 0.185 -0.031 1.09 1.5 5.751
7 7.3 218.6 -33.2 0.174 -0.026 0.96 1.4 5.359
8 8.4 199.7 -25.8 0.159 -0.021 0.83 1.4 4.972
9 9.4 186.3 -17.9 0.148 -0.014 0.70 1.3 4.602
10 10.5 187.0 -15.1 0.149 -0.012 0.63 1.2 4.247
11 11.5 194.4 -15.3 0.155 -0.012 0.59 1.1 3.899
12 12.6 198.4 -15.1 0.158 -0.012 0.55 1.0 3.545
13 13.6 187.4 -8.8 0.149 -0.007 0.48 0.9 3.199
14 14.7 162.8 -1.3 0.130 -0.001 0.38 0.8 2.882
15 15.7 130.2 -1.0 0.104 -0.001 0.28 0.8 2.603
16 16.8 97.6 -0.6 0.078 -0.001 0.19 0.8 2.371
17 17.8 78.8 -0.4 0.063 -0.000 0.05 0.8 2.183
Absolute 5.2 0.189 (T = 25.0 ms)
5.2 -0.033 (T = 38.1 ms)

CASE METHOD
J = 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
RP 282.3 267.0 251.8 236.5 221.3 206.1 190.8 175.6 160.3 145.1
RX 282.3 267.0 251.8 236.5 221.3 206.1 190.8 175.6 160.3 145.1
RU 323.9 312.8 301.7 290.6 279.5 268.5 257.4 246.3 235.2 224.1
RAU = 0.0 (tons); RA2 = 151.4 (tons)
Current CAPWAP Ru = 227.8 (tons); Corresponding J(RP)= 0.36; J(RX) = 0.36

VMX TVP VT1*Z FT1 FMX DMX DFN SET EMX QUS
m/s ms tons tons tons mm mm mm tonne-m tons
1.74 23.56 192.8 241.9 244.9 6.669 1.336 1.200 1.4 346.6

Page 2 Analysis: 05-Mar-2021


RSUD TORA BELO; Pile: BP 26 Test: 03-Mar-2021 17:18:
BOREDPILE 400, DH 3.0 TON; Blow: 2 CAPWAP(R) 2006-3
TARUMANEGARA Bumiyasa OP: KUS
PILE PROFILE AND PILE MODEL
Depth Area E-Modulus Spec. Weight Perim.
m cm2 tons/cm2 tons/m3 m
0.00 1256.64 317.2 2.400 1.257
17.80 1256.64 317.2 2.400 1.257
Toe Area 0.126 m2
Top Segment Length 1.05 m, Top Impedance 110.71 tons/m/s

Pile Damping 2.0 %, Time Incr 0.291 ms, Wave Speed 3600.0 m/s, 2L/c 9.9 ms

Page 3 Analysis: 05-Mar-2021


LAMPIRAN B

INSTALASI SENSOR dan KALIBRASI SENSOR


PILE DYNAMIC ANALYSIS REPORT
Typical Arrangement
for Attaching Transducers
to Bore Piles

ACCELEROMETER 1
STRAIN GAGE 1
STRAIN GAGE 4

ACCELEROMETER 3
STRAIN GAGE 3

ACCELEROMETER 4
ACCELEROMETER 2
STRAIN GAGE 2

PT. TARUMANEGARA Bumiyasa


LAMPIRAN C

DOKUMENTASI
PILE DYNAMIC ANALYSIS REPORT
RUMAH SAKIT UMUM DAERAH TORA BELO
Kabupaten Sigi, Sulawesi Tengah
PT. Dwi Tunggal Surya Jaya

BP 10

BP 26

PT. TARUMANEGARA Bumiyasa