4
PENDAHULUAN
Sumber:
Slide Prof. Bambang Boediono, 2020
6
PEMBEBANAN
D = beban mati
L = beban hidup
Lr = beban hidup atap
R = beban hujan
W = beban angin
E = beban gempa (vertikal dan horizontal)
8
SISTEM STRUKTUR PENAHAN BEBAN GEMPA
SNI 1726:2019
10
PERSYARATAN
MATERIAL
11
MATERIAL BETON
PERSYARATAN
DURABILITAS
BETON
12
MATERIAL BETON
13
SELIMUT BETON
14
MATERIAL TULANGAN
15
MATERIAL TULANGAN
PERSYARATAN
UNTUK SRPMK
& SDSK
16
DESAIN PELAT
17
DESAIN PELAT SATU ARAH
18
DESAIN PELAT SATU ARAH
Sumber: ACI
19
DESAIN PELAT DUA ARAH
20
DESAIN BALOK
21
DESAIN BALOK - UMUM
22
DESAIN BALOK - SRPMB
23
DESAIN BALOK - SRPMM
SYARAT SRPMB
24
DESAIN BALOK - SRPMK
25
DESAIN BALOK - SRPMK
Ketentuan Tulangan Longitudinal
(Pasal 18.6.3)
Sumber:
Slide Prof. Iswandi,Sumber:
2021
Slide Prof. Bambang Boediono,26 2020
DESAIN BALOK - SRPMK
Ketentuan Tulangan Transversal
(Pasal 18.6.4)
27
DESAIN BALOK - SRPMK
Desain terhadap Gaya Geser
(Pasal 18.6.5)
28
DESAIN KOLOM
29
DESAIN KOLOM - UMUM
30
DESAIN KOLOM - SRPMB
31
DESAIN KOLOM - SRPMM
32
DESAIN KOLOM - SRPMK
33
DESAIN KOLOM - SRPMK
34
DESAIN KOLOM - SRPMK
36
DESAIN BEAM-COLUMN JOINT - UMUM
Mitigasi:
max fc’ kolom = 1.4 fc’ balok & pelat
37
DESAIN BEAM-COLUMN JOINT SRPMK
38
DESAIN BEAM-COLUMN JOINT SRPMK
Sumber: NHERP
39
DESAIN
DINDING GESER
40
DESAIN DINDING GESER - UMUM
41
DESAIN DINDING GESER - SDSK
42
DESAIN DINDING GESER - SDSK
Persyaratan Tulangan Lentur
43
DESAIN DINDING GESER - SDSK
Persyaratan Tulangan Geser
44
DESAIN DINDING GESER - SDSK
Persyaratan Elemen Batas Khusus
(Boundary Element)
45
DESAIN DINDING GESER - COUPLING BEAM
46
DESAIN DINDING GESER - COUPLING BEAM
47
DESAIN DINDING GESER - COUPLING BEAM
48
DESAIN DINDING GESER - COUPLING BEAM
49
DESAIN
DIAFRAGMA
50
KOMPONEN DIAFRAGMA
51
DESAIN DIAFRAGMA
52
DESAIN DIAFRAGMA
53
- THANK YOU -
QnA Session
54