REFRACTORY DRYING OUT ( RDO )

BOILER # 1 PLTU TIDORE 2 X 7 MW


MALUKU - UTARA

By :SUPRIYONO & SUFIYANTO


PROJECT DIVISION
DIRECTORAT OPERASI
PENDAHULUAN :

SESUAI DI KETAHUI BERSAMA BAHWA BOILER SETELAH DI CHEMICAL


CLEANNING DI LANJUTKAN PROSES YAITU REFRACTORY DRYING OUT
( RDO ) YANG BERTUJUAN UNTUK MENGERINGKAN BATU & SEMEN
TAHAN API YANG BERADA DI DALAM FURNACE ( RUANG BAKAR )
DENGAN SUHU BERKISAR 90°C SAMPAI DENGAN SUHU 120°C.TAHAP
INI SANGAT MENENTUKAN KEAWETAN REFRACTORY JIKA SUHU DI
BUAT LEBIH MAKA AKAN TERJADI RETAK & PECAH PADA BATU &
SEMEN TAHAN API TERSEBUT,WALAUPUN DALAM OPERASI NANTI
SUHU FURNACE BERKISAR 850°C PADA BOILER STOKER SEMEN &
BATU TAHAN API TETAP LENGKET KARENA PROSES PENGERINGAN
DENGAN SUHU YANG TEPAT.
PROSES BOILER :

CHEMICAL
CLEANNING

R.D.O

STEAM
BLOWING
PREPARE 1ST FIRING :
TIM PJBS SELAKU O & M DI PLTU TIDORE WAJIB MENGIKUTI TAHAPAN DEMI TAHAPAN

YANG DI LAKUKAN OLEH PIHAK KONTRAKTOR SEBAGAI PROSES

PEMBELAJARAN,PENGALAMAN DAN MENGUMPULKAN DATA PERALATAN SEBAGAI

REFERENCI DI KEMUDIAN HARI JIKA ADA MASALAH ATAU KENDALA YANG DI TEMUI PADA

PERALATAN TERSEBUT.

1.KOORDINASI 2.CEK LIST 3.BOILER LIST


EQUIPMENT

• PT.REKADAYA.ELTK • DEMIN TANK A/B • SISTEM DRAIN


• PT.KUWERA • DEMIN PUMP A/B • SISTEM VENT
• PT.MAHARANI.P • CHAIN GREATE • SISTEM BB
• PT.PJBS • ASH COOLER • SISTEM UDARA
• PT.PLN ( Persero ) • ID FAN • BAHAN BKR AWAL
GROUP ABSTAIN • PROTEKSI ( SABUT & BATOK
JMK,UIP,UPK,JASER • DCS KELAPA )
,WILAYAH. • JML MAN POWER
TEAM RDO PLTU TIDORE # 1 :

CONTRAKTOR

1.PT.REKADAYA ELTRK 2.PT.MAHARANI PRIMA 3.PT.KUWERA / DEN


TEAM PT.PJBS :
JUMLAH PERSONIL 11 ORANG :
1 KOORDINATOR,4 ODP 7,6 OPRT EX GALANG BATANG

OPERATOR EX.GALANG
BATANG 6 PERSONIL
LEBIH MEMILIH
1.KOORDINATOR BERLIBUR DARI PADA
MASUK KERJA PADA
TGL 1 JUNI HARI
MINGGU SAAT 1ST
FIRING BOILER DI
LAKSANAKAN,KARENA
KALAU MEREKA
MASUK KERJA PT.PJBS
2 PERSONIL OPRTR DCS 2 PERSONIL OPRTR HARUS MEMBAYAR
( ODP 7 ) BOILER LOCAL ( ODP 7 )
PREMI / UANG
LEMBUR.
AKTIVITAS :

1.MENYEDIAKAN APAR ( ALAT


PEMADAM API RINGAN )
1.SAVETY K3
2.MOBIL DAMKAR STAND BY

3.SAFETY BRIFING
IMAGE :
1.FILLING BOILER ± 40 M³
2.BOILER

1.MASUKKAN BATOK / SABUT


KELAPA ± 5 M³,SIRAM DEGAN
SOLAR & SULUT DENGAN API

3.JIKA PEMBAKARAN SDH MERATA


START ID FAN
IMAGE :
TABEL :
3.PENDATAAN
1.PIHAK CONTRAKTOR (
PT.REKADAYA ELTK,PT.KUWERA /
DEN,PT.MARANI PRIMA

2.PT.PJBS
( DCS & BOILER LOCAL )
IMAGE :
RINGKASAN KEGIATAN :

01 JUNI 2014 TEPAT 15:03 TEMPERATUR 17:35 TEMPERATUR


13:25 WITA 1ST FIRING FURNACE LEFT 80°C & FURNACE LEFT 110°C
BOILER RIGHT 90°C & RIGHT 120°C

19:45 BOILER SHUT


DOWN LEBIH CEPAT
17:35 TEMPERATUR
DARI RENCANA HASIL
FURNACE LEFT 110°C
PENGERINGAN BAIK
& RIGHT 120°C
INFO PT.REKADAYA &
PT.KUWERA / DEN
KESIMPULAN :
ITEM REMARKS

1.KOORDINASI YG BAIK KERJA & TARGET TERCAPAI

2.OPERATOR PJBS DPT BELAJAR START BOILER JIKA SUATU SAAT PIHAK CONTRAKTOR SDH
DARI AWAL MENYERAHKAN KE PLN WILAYAH PJBS SUDAH SIAP

MEMUDAHKAN MENCARI PARAMETER YG HRS DI


3.MEMBIASAKAN OPERATOR PJBS FAMILIAR
AMATI JIKA TERJADI PENYIMPANGAN PERALATAN (
DGN PERALATAN YANG BEROPERASI
TROUBLE SHOOTING )/ ANALISA
TIDAK GUGUP / GROGI MELAKSANAKAN START &
4.MEMBANGUN MENTAL PERCAYA DIRI
STOP PERALATAN BAIK DI DCS ATAU LOCAL
5.MEMBAGUN JIWA LOYALITAS / DEDIKASI MENUNJUKKAN KEMAMPUAN & MENIMBA ILMU
TERHADAP PERUSAHAAN DARI PENGALAMAN DI PEMBANGKIT
TIDAK BISA DI INGKARI PROYEK PLTU TIDORE
6.MENUMBUHKAN JIWA NASIONALISME MERUPAKAN PROGRAM NEGARA ( MERAH PUTIH )
AGAR INDONESIA TIMUR KRISIS LISTRIK DI TERATASI

7.PENDATAAN BELAJAR MENYUSUN LAPORAN ( WORD , XCEL,PPT )


SEMOGA BERMANFAAT

SEKIAN TERIMA KASIH