Jadwal Perawatan Mesin Coal Pulverizer Type Vertical

Periode 2020-2022
a. Spesifikasi Mesin Coal Pulverizer Type Vertical
Berikut adalah tabel spesifikasi dari coal pulverizer.
Tabel 1.1 Coal Pulverizer
Subject Specifications
Manufacturer MHI
Model MVM31F
Pulverizer
Type Vertical, pressurized
Capacity 108 ton/jam
Manufacturer Hitachi Nico Transmission co., Ltd.
Coupling Model VRP – 140
Type NEH55W (form-flex coupling)
Roller Journal Upper Bearing Cylindrical Roller Bearing 80NU70162
Bearing
Roller Journal Lower Bearing Double Row Tapered Roller Bearing 45T807038
Journal Shaft S45C
Journal Head SC480
Journal Housing SC410
Major
Grinding Table SC480
Material
Grinding Table Liner SC410 with hard overlay welded
Grinder Roller SC410 with hard overlay welded
Deflector Liner Assembly SS 400 & ceramic liner

Tabel 1.2 Planetary Gearbox


Subject Specifications
Type VRP – 140
Power Rating 950 KW
Input Speed 970 rpm
Output Speed 29,5 rpm
Ratio 32,9

Tabel 1.3 Coal Pulverizer Motor


Subject Specifications
Motor Type HRQ3 569-68E
Speed at Rated Load 987 rpm
Rated Output 950 KW
Rated Voltage 13,2 KV
Rated Current 58,2 A
Frequency 50 Hz
Phase 3
Pole 6
Full Load Torque 937,5 kg.m
Gambar 1.1 Coal Pulverizer Type Vertical

Gambar 1.2 Coal Pulverizer Type Vertical


b. Derajat Kerumitan
Repair Complexity (kerumitan perbaikan) adalah suatu index relatif yang memberikan
gambaran derajat kerumitan dari suatu mesin/peralatan dimana didalamnya sudah termasuk
adanya roda-roda gigi, unit-unit hidrolik, dan pneumatic, peluncur dan unit transmisi
lainnya. Setiap peralatan atau mesin akan memiliki suatu index yang dapat memberikan
gambaran tingkat kerumitannya terhadap alat yang lain.
Kegunaan index kerumitan perbaikan adalah untuk menentukan :
1) Ukuran bagian maintenance, syarat-syarat yang diperlukan bagi staff dan pekerjanya.
2) Material dan suku cadang yang dipersyaratkan untuk pekerjaan maintenance.
3) Perkiraaan biaya perbaikan tahunan dari mesin-mesin.
4) Prosentase kerusakan dan efisiensi yang dapat dicapai oleh suatu mesin. (Suparlan,
1999: 40-41)
Tabel 1.4 Index Kerumitan Rata-Rata dari Berbagai Jenis Peralatan Produksi

Index Kerumitan
No Urut Jenis Peralatan Produksi
Rata-Rata
1. Rolling Mil (steel) 15
2. Turbines (steam & hydro) 14
3. Boilers 12
4. Steam Turbines (for ships) 11,5
5. Aviation engines, Heavy Diesel Engines, Heavy 11
Machines Tools
6. Automobile, Heavy Tractor, Ship Air Craft 10
7. Tractor 9,5
8. Rail Way Wagon (good & passengers) 9
9. Machines Tools (Medium Size) 9
10. Ball/Roller Bearing, Motor Cycle 8,5
11. Heavy Electrical Machines, Electric Train, 8,5
Precisions Instrument
12. Cycles, Tractor Spare Parts, Machines for Chemical 8
Industries, Paper from Wood Pulp
13. Compressors, Hydraulic Machines, Light Machine 8
Tools
14. Tools and Cutters 7,5
15. Textile, Food Industry, Leather Fire Protection 7,5
Equipment
Nilai kerumitan yang hampir sama dengan mesin coal pulverizer yaitu tipe produksi
avitation engines, heavy diesel engines, heavy machine tool dengan nilai rata-rata kerumitan
adalah 11.
c. Siklus Perawatan
Setelah mengetahui derajat kerumitan mesin coal pulverizer langkah selanjutnya adalah
menentukan siklus perawatan dengan metode ISMO. Berikut merupakan tabel siklus
perawatan ISMO.
Tabel 1.5 Siklus Perawatan ISMO
Derajat Periode Antara Dua Periode Antara Dua
Siklus Perawatan
Kerumitan Masa Perawatan Overhaul dalam
(Cycle Repair) Tipe Bahan Benda
Perawatan dalam Bulan (t) Tahun (T)
Produksi Produksi
(Repair Jumlah Giliran Kerja/Hari Giliran Kerja/ Hari
Siklus
Complexity) MSI 1 2 3 1 2 3
Baja karbon &
6.0 3.0 2.0 9.5 4.5 3.0
cor
Masal Aluminium cor 6.5 3.5 2.5 10.0 5.0 3.5
Perunggu 7.0 3.5 2.5 10.0 5.5 3.5
Baja Konstruksi 8.5 4.5 3.0 13.0 6.5 4.5
O - I1 - S1 -
I2 - S2 - I3 - Baja karbon &
8.0 4.0 3.0 12.0 6.0 4.0
M1 - I4 - S3 cor
0 s/d 30 - I5 - S4 - I6 269 Seri Aluminium cor 9.0 4.5 3.0 13.0 6.5 4.5
- M2 - I7 - Perunggu 9.5 4.5 3.0 13.5 7.0 4.5
S5 - I8 - S6 Baja Konstruksi 11.5 6.0 4.0 17.0 8.5 6.0
- I9 - O
Baja karbon &
9.5 4.5 3.0 14.0 7.0 4.5
cor
Unit Aluminium cor 10.0 5.0 3.5 15.0 7.5 5.0
Perunggu 10.5 5.5 3.5 16.0 8.0 5.5
Baja Konstruksi 13.0 6.5 4.6 19.5 10.0 6.5
(Sumber : Modul Perawatan Mesin Perkakas, 2018)

Berdasarkan tabel 1.5 didapatkan nilai kerumitan 11 terletak pada range 0 s/d 30. Untuk
menentukan siklus perawatan selama 3 tahun, maka giliran kerja yang dipilih untuk periode
antara masa perawatan dalam bulan dan dalam tahun yaitu dengan melihat tipe produksinya
adalah massal, serta bahan benda produksinya adalah bahan karbon & cor. Maka didapat
antara masa perawatan dalam bulan adalah 2.0 bulan sekali dan giliran kerja untuk periode
antara overhaul dalam tahun dipilih 3 tahun sekali. Sehingga siklus perawatan dan perbaikan
coal pulverizer type vertical kapasitas 108 ton/jam dapat disusun berdasarkan pada siklus
seperti tabel 1.6 berikut ini.

Tabel 1.6 Siklus Perawatan dan Perbaikan Coal Pulverizer Type Vertical Kapasitas 108
ton/jam
Derajat Siklus Perawatan (Cycle Repair) Periode antara dua Periode antara
Kerumitan Siklus Jumlah masa perawatan Overhaul dalam
Perawatan M S I dalam bulan (t) tahun (T)
O - I1 - S1 - I2 - S2 -
I3 - M1 - I4 - S3 - I5 -
11 2 6 9 2.0 3.0
S4 - I6 - M2 - I7 - S5 -
I8 - S6 - I9 - O
Keterangan :
T : lamanya waktu dari siklus perawatan yaitu ditunjukkan oleh waktu antara Overhaul
pertama dengan Ovehaul berikutnya atau O ke O.
t : periode antara dua tingkatan yang berurutan dari kategori perawatan preventive
(ISMO), sebagaimana ditunjukkan oleh tanda.
O – I1 – S1 – I2 – S2 – I3 – M1 – I4 – S3 – I5 – S4 – I6 – M2 – I7 – S5 – I8 – S6 – I9 – O
Berdasarkan siklus perawatan dan perbaikan menggunakan metode ISMO dapat
disimpulkan kegiatan perawatan terdiri dari 9 kali inspection, 6 kali small repair, 2 kali medium
repair, dan 1 kali overhaul. Dan juga dalam 2 bulan sekali dilakukan perawatan dan perbaikan
dan setiap 3 tahun sekali dilakukan overhaul.
Tabel 1.7 Jadwal Perawatan dan Perbaikan Coal Pulverizer Type Vertical Kapasitas 108 Ton/Jam Periode 2020

Bulan
No Bagian-Bagian
Jan Feb Mar Apr Mei Juni Juli Ags Sept Okt Nov Des
Komponen bagian bawah (bottom
housing assembly) pada coal
pulverizer type vertical :
1 a. Lower side seal air piping I1 S1 I2 S2 I3 M1
arrangement
b. Planetary gearbox and motor
I1 S1 I2 S2 I3 M1
assembly
Komponen bagian tengah (middle
housing assembly) pada coal
pulverizer type vertical :
2 a. Grinding table assembly M1
b. Grinding roller assembly S1 S2 M1
c. Journal hydraulic cylinder I1 S1 I2 S2 I3 M1
d. Accumulator I1 S1 I2 S2 I3 M1
Komponen bagian atas (upper
housing assembly) pada coal
pulverizer type vertical :
a. Upper seal piping and hydrolic
I1 S1 I2 S2 I3 M1
3 oil piping assembly
b. Pulverizer discharge port M1
c. Separator assembly M2
d. Lower inner funnel M2
e. Coal feed pipe S1 S2 M1
Keterangan :
I : Inspection (inspeksi), dilakukan selama 14 jam (warna )
S : Small repair (perbaikan kecil), dilakukan selama 22 jam (warna )
M : Medium repair (perbaikan menengah), dilakukan selama 58 jam (warna )
O : Overhaul, dilakukan selama 88 jam (warna )
Tabel 1.8 Jadwal Perawatan dan Perbaikan Coal Pulverizer Type Vertical Kapasitas 108 Ton/Jam Periode 2021

Bulan
No Bagian-Bagian
Jan Feb Mar Apr Mei Juni Juli Ags Sept Okt Nov Des
Komponen bagian bawah (bottom
housing assembly) pada coal
pulverizer type vertical :
1 a. Lower side seal air piping I4 S3 I5 S4 I6 M2
arrangement
b. Planetary gearbox and motor
I4 S3 I5 S4 I6 M2
assembly
Komponen bagian tengah (middle
housing assembly) pada coal
pulverizer type vertical :
2 a. Grinding table assembly M2
b. Grinding roller assembly S3 S4 M2
c. Journal hydraulic cylinder I4 S3 I5 S4 I6 M2
d. Accumulator I4 S3 I5 S4 I6 M2
Komponen bagian atas (upper
housing assembly) pada coal
pulverizer type vertical :
a. Upper seal piping and hydrolic
I4 S3 I5 S4 I6 M2
3 oil piping assembly
b. Pulverizer discharge port M2
c. Separator assembly M2
d. Lower inner funnel M2
e. Coal feed pipe S3 S4 M2
Keterangan :
I : Inspection (inspeksi), dilakukan selama 14 jam (warna )
S : Small repair (perbaikan kecil), dilakukan selama 22 jam (warna )
M : Medium repair (perbaikan menengah), dilakukan selama 58 jam (warna )
O : Overhaul, dilakukan selama 88 jam (warna )
Tabel 1.9 Jadwal Perawatan dan Perbaikan Coal Pulverizer Type Vertical Kapasitas 108 Ton/Jam Periode 2022

Bulan
No Bagian-Bagian
Jan Feb Mar Apr Mei Juni Juli Ags Sept Okt Nov Des
Komponen bagian bawah (bottom
housing assembly) pada coal
pulverizer type vertical :
1 a. Lower side seal air piping I7 S5 I8 S6 I9 O
arrangement
b. Planetary gearbox and motor
I7 S5 I8 S6 I9 O
assembly
Komponen bagian tengah (middle
housing assembly) pada coal
pulverizer type vertical :
2 a. Grinding table assembly O
b. Grinding roller assembly S5 S6 O
c. Journal hydraulic cylinder I7 S5 I8 S6 I9 O
d. Accumulator I7 S5 I8 S6 I9 O
Komponen bagian atas (upper
housing assembly) pada coal
pulverizer type vertical :
a. Upper seal piping and hydrolic
I7 S5 I8 S6 I9 O
3 oil piping assembly
b. Pulverizer discharge port O
c. Separator assembly O
d. Lower inner funnel O
e. Coal feed pipe S5 S6 O
Keterangan :
I : Inspection (inspeksi), dilakukan selama 14 jam (warna )
S : Small repair (perbaikan kecil), dilakukan selama 22 jam (warna )
M : Medium repair (perbaikan menengah), dilakukan selama 58 jam (warna )
O : Overhaul, dilakukan selama 88 jam (warna )
Merinci Aktivitas Perawatan Mesin Coal Pulverizer Type Vertical
Pengecekan (Beri tanda
No Bagian Standar Kegiatan Jangka waktu (V)) Kondisi
Harian Mingguan Bulanan Sudah Belum Baik Tidak
Komponen bagian bawah (bottom
1 housing assembly) pada coal pulverizer
type vertical :
a. Lower side seal air piping
Berfungsi Pemeriksaan kebocoran pada pipa
arrangement
Pemeriksaan penyambungan pipa
Pemeriksaan bagian baut
Pembersihan lower side seal air piping
arrangement pada bagian luarnya
b. Planetary gearbox and motor
Berfungsi Pemeriksaan bagian baut
assembly
Pemberian pelumasan
Pemeriksaan pada bearing
Pemeriksaan pelurusan poros
Pembersihan planetary gearbox and
motor assembly pada bagian luarnya
Komponen bagian tengah (middle
2 housing assembly) pada coal pulverizer
type vertical :
a. Grinding table assembly
Berfungsi Pemeriksaan bagian baut
Pemeriksaan keausan/ketebalan
permukaan pada meja grinding
Pemeriksaan kerusakan pada meja
grinding
Pembersihan grinding table assembly
Pemeriksaan keausan/ketebalan pada
b. Grinding roller assembly Berfungsi
permukaaan grinding roller
Pemeriksaan kerusakan pada grinding
roller
Pembersihan grinding roller assembly
Penyetelan gap antara grinding roller
dengan table liner
Pemeriksaan tekanan N2 pada
c. Accumulator Berfungsi
accumulator
Pembersihan accumulator
Pemeriksaan kebocoran pada minyak
d. Journal hydraulic cylinder Berfungsi
hydraulic
Pemeriksaan seal oilpada journal
hydraulic cylinder
Pemeriksaan keausan piston journal
hydraulic cylinder
Pembersihan journal hydraulic cylinder
Komponen bagian atas (upper housing
3 assembly) pada coal pulverizer type
vertical :
a. Upper seal piping and hydrolic oil Pemeriksaan kebocoran pada minyak
Berfungsi
piping assembly hydraulic
Pemeriksaan seal pipingpada journal
hydraulic cylinder
Pembersihan upper seal piping and
hydrolic oil piping assembly
Pemeriksaan pipa minyak hidrolik
b. Pulverizer discharge port Berfungsi Pemeriksaan port
Pembersihan pulverizer discharge port
c. Separator assembly Berfungsi Pembersihan separator assembly
Pemeriksaan bagian separator assembly
Pemeriksaan kerusakan pada bagian
Berfungsi
d. Lower inner funnel inner funnel
Pemeriksaan keausan pada bagian inner
funnel
Pembersihan lower inner funnel
e. Coal feed pipe Berfungsi Pemeriksaan pada pipa
Pembersihan coal feed pipe